Arizona prevailing wage rates: AZ20260049
Highway construction in Yavapai County.
AZ20260049, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| CARPENTER | $35.89 | $14.98 | $50.87 | CARP1912-002 eff. 07/01/2024 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $35.56 | $18.12 | $53.68 | ENGI0012-046 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: PAVER/SPREADER/FINISH EQUIPMENT (ASPHALT, AGGREGATE, & CONCRETE) | $35.56 | $18.12 | $53.68 | ENGI0012-051 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: SCRAPER | $35.56 | $18.12 | $53.68 | ENGI0012-052 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: TRACTOR | $35.56 | $18.12 | $53.68 | ENGI0012-053 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: (DRILL RIG/AUGER) | $36.64 | $18.12 | $54.76 | ENGI0012-057 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $32.29 | $18.12 | $50.41 | ENGI0012-064 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: BACKHOE/BACKHOE & LOADER COMBO/TRACK BACKHOE | $35.56 | $18.12 | $53.68 | ENGI0012-066 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: COMPACTOR/ROLLER | $35.56 | $18.12 | $53.68 | ENGI0012-067 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: LOADER/FRONT END LOADER | $35.56 | $18.12 | $53.68 | ENGI0012-069 eff. 12/01/2024 |
| TRUCK DRIVER: OFF ROAD TRUCK | $35.56 | $18.12 | $53.68 | ENGI0012-070 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: CRANE/DERRICK | $36.64 | $18.12 | $54.76 | ENGI0012-071 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE (GREATER THAN 1/2 CUBIC YARD) | $36.64 | $18.12 | $54.76 | ENGI0012-072 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE (1/2 CUBIC YARD OR SMALLER) | $35.56 | $18.12 | $53.68 | ENGI0012-072 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: MOTOR GRADER/BLADE | $36.64 | $18.12 | $54.76 | ENGI0012-074 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: MECHANIC | $37.67 | $18.12 | $55.79 | ENGI0012-075 eff. 12/01/2024 |
| POWER EQUIPMENT OPERATOR: HORIZONTAL DIRECTIONAL DRILL | $31.98 | $9.26 | $41.24 | LABO1184-016 eff. 06/01/2025 |
| LABORER: FENCE ERECTOR | $27.41 | $9.26 | $36.67 | LABO1184-017 eff. 06/01/2025 |
| LABORER: GRADE SETTER | $27.41 | $9.26 | $36.67 | LABO1184-018 eff. 06/01/2025 |
| TRAFFIC CONTROL | $27.41 | $9.26 | $36.67 | LABO1184-021 eff. 06/01/2025 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $29.91 | $9.26 | $39.17 | LABO1184-025 eff. 06/01/2025 |
| POWER EQUIPMENT OPERATOR: TRENCHER | $30.88 | $9.26 | $40.14 | LABO1184-033 eff. 06/01/2025 |
| LABORER: GENERAL | $27.41 | $9.26 | $36.67 | LABO1184-039 eff. 06/01/2025 |
| LABORER: MASON TENDER | $27.41 | $9.26 | $36.67 | LABO1184-041 eff. 06/01/2025 |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $30.88 | $9.26 | $40.14 | LABO1184-044 eff. 06/01/2025 |
| TRUCK DRIVER: CONCRETE | $30.88 | $9.26 | $40.14 | LABO1184-047 eff. 06/01/2025 |
| TRUCK DRIVER: DUMP | $30.88 | $9.26 | $40.14 | LABO1184-048 eff. 06/01/2025 |
| TRUCK DRIVER: WATER | $30.88 | $9.26 | $40.14 | LABO1184-049 eff. 06/01/2025 |
| TRUCK DRIVER: SWEEPER | $20.24 | $5.48 | $25.72 | SUAZ2023-026 eff. 11/19/2024 |
| TRUCK DRIVER: OIL DISTRIBUTOR | $29.75 | $8.04 | $37.79 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: OILER | $31.56 | $10.69 | $42.25 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: MILLING MACHINE | $30.09 | $6.45 | $36.54 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: GRADE CHECKER | $29.74 | $13.07 | $42.81 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: FIELD EQUIPMENT SERVICEPERSON | $35.39 | $11.50 | $46.89 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: CONCRETE SCREED | $25.70 | $7.15 | $32.85 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: CONCRETE PUMP TRUCK | $43.11 | $10.87 | $53.98 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: BROOM/SWEEPER | $26.47 | $7.26 | $33.73 | SUAZ2023-026 eff. 11/19/2024 |
| POWER EQUIPMENT OPERATOR: BOOM/CRANE TRUCK | $43.11 | $10.87 | $53.98 | SUAZ2023-026 eff. 11/19/2024 |
| PAINTER: SIGN AND DISPLAY ERECTOR | $18.03 | $0.00 | $18.03 | SUAZ2023-026 eff. 11/19/2024 |
| PAINTER: PAVEMENT MARKING | $24.60 | $6.34 | $30.94 | SUAZ2023-026 eff. 11/19/2024 |
| LABORER: PIPELAYER | $25.85 | $7.09 | $32.94 | SUAZ2023-026 eff. 11/19/2024 |
| LABORER: LANDSCAPE LABORER | $18.03 | $0.00 | $18.03 | SUAZ2023-026 eff. 11/19/2024 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | $25.22 | $5.08 | $30.30 | SUAZ2023-026 eff. 11/19/2024 |
| IRONWORKER | $33.15 | $18.57 | $51.72 | SUAZ2023-026 eff. 11/19/2024 |
| ELECTRICIAN | $29.00 | $7.58 | $36.58 | SUAZ2023-026 eff. 11/19/2024 |
| CEMENT MASON/CONCRETE FINISHER | $30.09 | $0.00 | $30.09 | SUAZ2023-026 eff. 11/19/2024 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.