DE20260008, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No existing rate changed amount.
1 classifications added, 2 removed or reworded
- added BRICKLAYER $34.19 + $27.98 fringe
- removed BRICKLAYER: Brick Refractory/Brick Placement Worker was $35.00 + $24.57 fringe
- removed BRICKLAYER: Bricklayer was $34.19 + $27.98 fringe
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| BOILERMAKER | $55.00 | $35.48 | $90.48 | BOIL0013-009 eff. 01/01/2025 |
| BRICKLAYER | $34.19 | $27.98 | $62.17 | BRDE0001-001 eff. 05/01/2021 |
| CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, SCAFFOLD BUILDING, EXCLUDES MASONRY/BRICK, AND EXCLUDES SOFT FLOOR LAYER) | $38.27 | $25.34 | $63.61 | CARP0173-009 eff. 05/01/2025 |
| SOFT FLOOR LAYER | $38.02 | $25.39 | $63.41 | CARP0251-008 eff. 05/01/2025 |
| MILLWRIGHT | $51.54 | $39.26 | $90.80 | CARP1906-003 eff. 05/01/2025 |
| ELECTRICIAN (INCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF ALARMS, HVAC/TEMPERATURE CONTROLS AND SOUND AND COMMUNICATION SYSTEMS) | $47.50 | $35.93 | $83.43 | ELEC0313-002 eff. 06/03/2024 |
ELEVATOR MECHANICScope and notesFOOTNOTES FOR ELEVATOR MECHANICS: A. PAID VACATION: EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OR 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY | $71.85 | $38.44 | $110.29 | ELEV0005-003 eff. 01/01/2025 |
POWER EQUIPMENT OPERATOR: FORKLIFTScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY (PROVIDED THE EMPLOYEE WORKS THE SCHEDULED WORK DAY FOLLOWING THE HOLIDAY.) | $48.73 | $32.23 | $80.96 | ENGI0542-003 eff. 05/01/2025 |
IRONWORKER: ORNAMENTAL, REINFORCING, AND STRUCTURALScope and notesTHE FOLLOWING HOLIDAYS SHALL BE OBSERVED, AND WHEN WORK IS PERFORMED THEREON IT SHALL BE PAID FOR AT TWICE THE BASE WAGE RATE: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.10 | $38.23 | $79.33 | IRON0451-005 eff. 07/01/2024 |
| LABORER: BACKFILLER, COMMON OR GENERAL, JACK HAMMER, MASON TENDER - BRICK, PIPELAYER, SCAFFOLD BUILDER (BRICK AND MASONRY), TAMPER (HAND HELD) | $29.45 | $25.70 | $55.15 | LABO0199-005 eff. 02/01/2024 |
| LABORER (MASON TENDER - CEMENT/CONCRETE) | $31.45 | $25.70 | $57.15 | LABO0199-005 eff. 02/01/2024 |
| GLAZIER | $49.96 | $37.56 | $87.52 | PAIN0252-002 eff. 05/01/2025 |
| PLASTERER: FIREPROOFER | $38.37 | $31.64 | $70.01 | PLAS0008-006 eff. 05/01/2021 |
| CEMENT MASON/CONCRETE FINISHER | $41.69 | $27.28 | $68.97 | PLAS0592-009 eff. 05/01/2025 |
PIPEFITTER: INCLUDES HVAC PIPE INSTALLATION AND EXCLUDES INDUSTRIAL WORKScope and notesFOOTNOTE A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,INDEPENDENCE DAY, THANKSGIVING DAY,LABOR DAY, CHRISTMAS DAY, AND GENERAL ELECTION DAY | $41.35 | $38.19 | $79.54 | PLUM0074-002 eff. 09/30/2024 |
PIPEFITTER: INDUSTRIALScope and notesFOOTNOTE A: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,INDEPENDENCE DAY, THANKSGIVING DAY,LABOR DAY, CHRISTMAS DAY, AND GENERAL ELECTION DAY | $56.43 | $43.35 | $99.78 | PLUM0074-003 eff. 09/30/2024 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $46.47 | $29.56 | $76.03 | SFDE0669-002 eff. 04/01/2025 |
| SHEET METAL WORKER (INCLUDES HVAC DUCT INSTALLATION) | $33.63 | $40.60 | $74.23 | SHEE0019-021 eff. 07/01/2020 |
| TILE SETTER | $57.98 | $1.11 | $59.09 | SUDE2014-005 eff. 01/20/2016 |
| TILE FINISHER | $35.40 | $4.31 | $39.71 | SUDE2014-005 eff. 01/20/2016 |
| ROOFER, EXCLUDES INSTALLATION OF METAL ROOFS | $27.98 | $27.90 | $55.88 | SUDE2014-005 eff. 01/20/2016 |
| ROOFER (INSTALLATION OF METAL ROOFS ONLY) | $39.09 | $30.77 | $69.86 | SUDE2014-005 eff. 01/20/2016 |
| PLUMBER | $47.73 | $18.40 | $66.13 | SUDE2014-005 eff. 01/20/2016 |
| PAINTER (BRUSH AND ROLLER) | $38.80 | $0.91 | $39.71 | SUDE2014-005 eff. 01/20/2016 |
| OPERATOR: CRANE | $32.40 | $18.27 | $50.67 | SUDE2014-005 eff. 01/20/2016 |
| OPERATOR: BULLDOZER | $25.89 | $0.00 | $25.89 | SUDE2014-005 eff. 01/20/2016 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $33.96 | $0.00 | $33.96 | SUDE2014-005 eff. 01/20/2016 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.