Florida prevailing wage rates: FL20260024
Building construction in Putnam County.
FL20260024, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| ELECTRICIAN (THAT PORTION EAST OF THE ST. JOHN'S RIVER AND SOUTH OF THE FLORIDA EAST COAST RAILWAY TRACT BEGINNING AT THE ST. JOHN'S RIVER BRIDGE AT PALATKA, FL AND RUNNING SOUTHEAST TO THE PUTNAM-ST. JOHN'S COUNTY LINE.) | $31.02 | $14.43 | $45.45 | ELEC0756-004 eff. 09/01/2025 |
| ELECTRICIAN (REMAINDER OF COUNTY.) | $33.50 | $13.85 | $47.35 | ELEC1205-006 eff. 06/01/2025 |
| OPERATOR: CRANE (TOWER CRANE; LOCOMOTIVE CRANE; CRAWLER CRANE; TRUCK CRANE; & HYDRO CRANE) | $35.41 | $13.60 | $49.01 | ENGI0673-007 eff. 05/01/2024 |
| OPERATOR: CRANE (GANTRY CRANE & BRIDGE CRANE) | $35.41 | $13.60 | $49.01 | ENGI0673-007 eff. 05/01/2024 |
| IRONWORKER: STRUCTURAL AND REINFORCING | $29.50 | $12.98 | $42.48 | IRON0597-004 eff. 04/01/2024 |
SHEET METAL WORKER: INCLUDES HVAC DUCT INSTALLATIONScope and notesA: HOLIDAY PAY: NEW YEAR'S DAY, MEMORIAL DAY, JULY FOURTH, LABOR DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY | $31.64 | $15.98 | $47.62 | SHEE0435-005 eff. 04/01/2025 |
| TRUCK DRIVER, INCLUDES DUMP AND 10 YARD HAUL AWAY | $8.00 EO 13658 minimum $13.65 may apply | $0.15 | $8.15 | SUFL2009-061 eff. 05/22/2009 |
| ROOFER: BUILT UP, COMPOSITION, HOT TAR AND SINGLE PLY | $12.00 EO 13658 minimum $13.65 may apply | $0.00 | $12.00 | SUFL2009-061 eff. 05/22/2009 |
| PLUMBER | $12.27 EO 13658 minimum $13.65 may apply | $3.33 | $15.60 | SUFL2009-061 eff. 05/22/2009 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $10.42 EO 13658 minimum $13.65 may apply | $0.00 | $10.42 | SUFL2009-061 eff. 05/22/2009 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $9.58 EO 13658 minimum $13.65 may apply | $0.00 | $9.58 | SUFL2009-061 eff. 05/22/2009 |
| OPERATOR: BACKHOE/EXCAVATOR | $13.19 EO 13658 minimum $13.65 may apply | $0.00 | $13.19 | SUFL2009-061 eff. 05/22/2009 |
| LABORER: PIPELAYER | $11.42 EO 13658 minimum $13.65 may apply | $1.95 | $13.37 | SUFL2009-061 eff. 05/22/2009 |
| LABORER: COMMON OR GENERAL | $9.33 EO 13658 minimum $13.65 may apply | $0.00 | $9.33 | SUFL2009-061 eff. 05/22/2009 |
| CEMENT MASON/CONCRETE FINISHER | $16.79 | $0.00 | $16.79 | SUFL2009-061 eff. 05/22/2009 |
| CARPENTER, INCLUDES FORM WORK | $14.46 | $3.39 | $17.85 | SUFL2009-061 eff. 05/22/2009 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.