PrevailCrew

Illinois prevailing wage rates: IL20260008

Building, Residential construction in Du Page, Grundy, Kane, Kendall, Lake, McHenry, Will Counties.

IL20260008, modification 3, published 10/22/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 2

  • changed OPERATOR: POWER EQUIPMENT, GROUP 1 (BUILDING AND RESIDENTIAL) MECHANIC; ASPHALT PLANT*; ASPHALT SPREADER; AUTOGRADE*; BACKHOES WITH CAISSON ATTACHMENT*:BATCH PLANT*; BENOTO(REQUIRES TWO ENGINEERS); BOILER AND THROTTLE VALVE; CAISSON RIGS*; CENTRAL REDI-MIX PLANT*; COMBINATION BACKHOE FRONT ENDLOADER MACHINE; COMPRESSOR AND THROTTLE VALVE; CONCRETE BREAKER (TRUCK MOUNTED)*; CONCRETE CONVEYOR; CONCRETE CONVEYOR, TRUCK MOUNTED; CONCRETE PAVER OVER 27E CU. FT.*; CONCRETE PAVER 27E CU FT AND UNDER*; CONCRETE PLACER*; CONCRETE PLACING BOOM; CONCRETE PUMP (TRUCK MOUNTED); CONCRETE TOWER; CRANES*; CRANES, HAMMERHEAD*; CRANES, (GCI AND SIMILAR TYPE REQUIRES TWO OPERATORS ONLY); CRETER CRANE; CRUSHER, STONE, ETC; DERRICKS; DERRICKS, TRAVELING*; FORMLESS CURB AND GUTTER MACHINE*; GRADER, ELEVATING; GROUTING MACHINES; HIGHLIFT SHOVELS OR FRONT ENDLOADER 2 1/4 YD. AND OVER; HOISTS, ELEVATORS, OUTSIDE TYPE RACK AND PINION AND SIMILAR MACHINES; HOISTS, ONE, TWO, AND THREE DRUM; HOISTS, TWO TUGGER ONE FLOOR; HYDRAULIC BACKHOES*; HYDRAULIC BOOM TRUCKS; HYDRAULIC VAC (AND SIMILAR EQUIPMENT);LOCOMOTIVES; MOTOR PATROL*; PILE DRIVERS AMD SKID RIG*; POST HOLE DIGGER; PRE- STRESS MACHINE; PUMP CRETES DUAL RAM(REQUIRING FREQUENT LUBRICATION AND WATER); PUMP CRETES; SQUEEZE CRETES-SCREW TYPE PUMPS GYPSUM BULKER AND PUMP; RAISED AND BLIND HOLE DRILL*; ROTO MILL GRINDER (36" AND OVER)*; ROTO MILL GRINDER (LESS THAN 36")*; SCOOPS-TRACTOR DRAWN; SLIP-FORM PAVER*; STRADDLE BUGGIES; TOURNAPULL; TRACTOR WITH BOOM, AND SIDE BOOM; AND TRENCHING MACHINES*. *-REQUIRES OILER base $64.80 → $68.80 (+$4.00), fringe $51.00 → $53.05 (+$2.05) New rates effective 06/01/2026 (previously 06/01/2025).
  • changed OPERATOR: POWER EQUIPMENT, GROUP 2 (BUILDING AND RESIDENTIAL) BOBCAT (OVER 3/4 CU YD); BOILERS; BRICK FORKLIFT; BROOM, POWER PROPELLED; BULLDOZERS; CONCRETE MIXER (TWO BAG AND OVER); CONVEYOR, PORTABLE; FORKLIFT TRUCKS; GREASER ENGINEER; HIGHLIFT SHOVELS OR FRONT END LOADERS UNDER 2 1/4 CU YD; AOTOMATIC HOISTS, HOISTS, INSIDE ELEVATORS; HOISTS, SEWER DRAGGING MACHINE; HOISTS, TUGGER SINGLE DRUM; LASER SCREED; ROCK DRILL (SELF-PROPELLED); ROCK DRILL (TRUCK MOUNTED)*; ROLLERS; STEAM GENERATORS; TRACTORS; TRACTOR DRAWN VIBRATORY ROLLER (RECEIVES AN ADDITIONAL $.50 PER HOUR); WINCH TRUCKS WITH "A" FRAME. *-REQUIRES OILER base $63.50 → $67.50 (+$4.00), fringe $51.00 → $53.05 (+$2.05) New rates effective 06/01/2026 (previously 06/01/2025).
  • changed OPERATOR: POWER EQUIPMENT, GROUP 3 (BUILDING AND RESIDENTIAL) AIR COMPRESSOR-SMALL 250 AND UNDER (1 TO 5 NOT TO EXCEED A TOTAL OF 300 FT); AIR COMPRESSOR-LARGE OVER 250; COMBINATION-SMALL EQUIPMENT OPERATOR; GENERATOR- SMALL 50 KW AND UNDER; GENERATOR-LARGE OVER 50 KW; HEATERS, MECHANICAL; HOISTS, INSIDE ELEVATORS (REMODELING OR RENOVATIN WORK); HYDRUALIC POWER UNITS (PILE DRIVING, EXTRACTING, AND DRILLING); LOW BOYS; PUMPS OVER 3" (1 TO 3 NOT TO EXCEED A TOTAL OF 300 FT); PUMPS, WELL POINTS; WELDING MACHINES (2 THROUGH 5); WINCHES, 4 SMALL ELECTRIC DRILL WINCHES; BOBCAT (UP TO AND INCLUDING 3/4 CU YD) base $60.95 → $64.95 (+$4.00), fringe $51.00 → $53.05 (+$2.05) New rates effective 06/01/2026 (previously 06/01/2025).
  • changed OPERATOR: POWER EQUIPMENT, GROUP 4 (BUILDING AND RESIDENTIAL) BOBCATS AND/OR OTHER SKID STEER LOADERS; BRICK FORKLIFTS; OILERS base $59.20 → $63.20 (+$4.00), fringe $51.00 → $53.05 (+$2.05) New rates effective 06/01/2026 (previously 06/01/2025).

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

IL20260008 wage rates
ClassificationBaseFringeTotalRate ID
HAZARDOUS MATERIAL HANDLER (INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT)$41.27$32.76$74.03ASBE0017-005
eff. 06/01/2024
FIRE STOP TECHNICIAN$44.02$32.76$76.78ASBE0017-005
eff. 06/01/2024
ASBESTOS WORKER/INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS)$55.02$35.75$90.77ASBE0017-005
eff. 06/01/2024
BOILERMAKER (DU PAGE, GRUNDY, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES)$53.10$38.54$91.64BOIL0001-003
eff. 05/01/2024
BRICKLAYER (DU PAGE, GRUNDY, LAKE, AND WILL COUNTIES)$48.56$34.05$82.61BRIL0014-001
eff. 06/01/2021
MARBLE SETTER$47.71$33.20$80.91BRIL0021-002
eff. 06/01/2021
TILE SETTER$49.75$30.79$80.54BRIL0021-008
eff. 06/01/2021
TILE FINISHER$42.80$26.97$69.77BRIL0021-008
eff. 06/01/2021
TERRAZZO WORKER/SETTER$48.38$30.79$79.17BRIL0021-008
eff. 06/01/2021
MARBLE FINISHER$33.95$26.03$59.98BRIL0021-010
eff. 06/01/2017
BRICKLAYER (KANE, KENDALL, AND MCHENRY COUNTIES)$44.88$26.62$71.50BRIL0027-002
eff. 06/01/2016
CARPENTER: HEAVY & HIGHWAY (DUPAGE ANE LAKE COUNTIES)$52.01$38.85$90.86CARP0555-003
eff. 06/01/2022
CARPENTER: BUILDING (DUPAGE ANE LAKE COUNTIES)$52.01$38.85$90.86CARP0555-003
eff. 06/01/2022
CARPENTER: RESIDENTIAL (DU PAGE AND LAKE COUNTIES)$45.61$35.31$80.92CARP0555-004
eff. 10/01/2023
CARPENTER; MILLWRIGHT; PILEDRIVERMEN (WILL COUNTY BUILDING)$52.01$41.41$93.42CARP0555-006
eff. 06/01/2022
CARPENTER (WILL COUNTY RESIDENTIAL)$45.61$35.31$80.92CARP0555-007
eff. 10/01/2023
CARPENTER: CARPENTER, FLOOR LAYER, LATHER, MILLWRIGHT, AND PILEDRIVER (KANE, KENDALL, AND MCHENRY COUNTIES BUILDING)$52.01$38.86$90.87CARP0555-009
eff. 06/01/2022
CARPENTER (KANE, KENDALL, AND MCHENRY COUNTIES RESIDENTIAL)$45.61$35.31$80.92CARP0555-010
eff. 10/01/2023
CARPENTER, CARPENTER, MILLWRIGHT, PILEDRIVER, AND SOFT FLOOR LAYER (GRUNDY COUNTY)$45.61$35.31$80.92CARP0555-012
eff. 10/01/2023
LINE CONSTRUCTION: LINEMAN AND EQUIPMENT OPERATOR (WILL COUNTY)$62.10$37.29$99.39ELEC0009-002
eff. 05/26/2024
LINE CONSTRUCTION: GROUNDMAN (WILL COUNTY)$48.44$29.09$77.53ELEC0009-002
eff. 05/26/2024
ELECTRICIAN: BUILDING (KANE (NORTHERN HALF) AND MCHENRY COUNTIES)$59.11$42.23$101.34ELEC0117-002
eff. 06/02/2025
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES (VOICE, SOUND, DATA AND VIDEO), TELEPHONE, SECURITY, FIRE ALARM SYSTEMS THAT ARE A COMPONENT OF A MULTIPLEX SYSTEM AND SHARE A COMMON CABLE, AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICE, PABX AND EQUIPMENT, MICRO WAVES, V-SAT, BYPASS, CATV, WAN, (WIDE AREA NETWORKS), LAN (LOCAL AREA NETWORKS), AND ISDN (INTEGRATED SYSTEM DIGITAL NETWORK).THE WORK SHALL COVER THE PULLING OF WIRE IN RACEWAYS, BUT NOT THE INSTALLATION OF RACEWAYS.: KANE (NORTHERN HALF), AND MCHENRY COUNTIES)$48.71$35.87$84.58ELEC0117-003
eff. 11/03/2025
ELECTRICIAN: RESIDENTIAL (KANE (NORTHERN HALF) AND MCHENRY COUNTIES)$44.40$34.59$78.99ELEC0117-004
eff. 11/04/2024
ELECTRICIAN: BUILDING (LAKE COUNTY)$51.87$51.77$103.64ELEC0150-002
eff. 06/02/2025
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES (VOICE, SOUND, DATA AND VIDEO), TELEPHONE, SECURITY, FIRE ALARM SYSTEMS THAT ARE A COMPONENT OF A MULTIPLEX SYSTEM AND SHARE A COMMON CABLE, AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICE, PABX AND EQUIPMENT, MICRO WAVES, V-SAT, BYPASS, CATV, WAN, (WIDE AREA NETWORKS), LAN (LOCAL AREA NETWORKS), AND ISDN (INTEGRATED SYSTEM DIGITAL NETWORK).THE WORK SHALL COVER THE PULLING OF WIRE IN RACEWAYS, BUT NOT THE INSTALLATION OF RACEWAYS.: (LAKE COUNTY)$48.00$39.85$87.85ELEC0150-003
eff. 12/01/2025
ELECTRICIAN: RESIDENTIAL (GRUNDY AND WILL COUNTIES)$46.87$33.38$80.25ELEC0176-003
eff. 06/01/2023
ELECTRICIAN: BUILDING (GRUNDY AND WILL COUNTIES)$52.00$45.01$97.01ELEC0176-008
eff. 06/01/2023
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES (VOICE, SOUND, DATA AND VIDEO), TELEPHONE, SECURITY, FIRE ALARM SYSTEMS THAT ARE A COMPONENT OF A MULTIPLEX SYSTEM AND SHARE A COMMON CABLE, AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICE, PABX AND EQUIPMENT, MICRO WAVES, V-SAT, BYPASS, CATV, WAN, (WIDE AREA NETWORKS), LAN (LOCAL AREA NETWORKS), AND ISDN (INTEGRATED SYSTEM DIGITAL NETWORK).THE WORK SHALL COVER THE PULLING OF WIRE IN RACEWAYS, BUT NOT THE INSTALLATION OF RACEWAYS. (GRUNDY AND WILL COUNTIES)$44.00$37.91$81.91ELEC0176-015
eff. 06/01/2024
ELECTRICIAN: BUILDING (KANE (SOUTHERN HALF) AND KENDALL COUNTIES)$60.17$43.50$103.67ELEC0461-002
eff. 06/02/2025
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES (VOICE, SOUND, DATA AND VIDEO), TELEPHONE, SECURITY, FIRE ALARM SYSTEMS THAT ARE A COMPONENT OF A MULTIPLEX SYSTEM AND SHARE A COMMON CABLE, AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICE, PABX AND EQUIPMENT, MICRO WAVES, V-SAT, BYPASS, CATV, WAN, (WIDE AREA NETWORKS), LAN (LOCAL AREA NETWORKS), AND ISDN (INTEGRATED SYSTEM DIGITAL NETWORK).THE WORK SHALL COVER THE PULLING OF WIRE IN RACEWAYS, BUT NOT THE INSTALLATION OF RACEWAYS.: (KANE (SOUTHERN HALF), AND KENDALL COUNTIES)$49.70$38.45$88.15ELEC0461-005
eff. 11/03/2025
ELECTRICIAN: RESIDENTIAL (DUPAGE COUNTY)$39.60$32.25$71.85ELEC0701-002
eff. 11/04/2019
ELECTRICIAN: ELECTRICAL TECHNICIAN: WORK INCLUDES THE INSTALLATION, MAINTENANCE AND REMOVAL OF TELECOMMUNICATION FACILITIES (VOICE, SOUND, DATA AND VIDEO), TELEPHONE, SECURITY, FIRE ALARM SYSTEMS THAT ARE A COMPONENT OF A MULTIPLEX SYSTEM AND SHARE A COMMON CABLE, AND DATA INSIDE WIRE, INTERCONNECT, TERMINAL EQUIPMENT, CENTRAL OFFICE, PABX AND EQUIPMENT, MICRO WAVES, V-SAT, BYPASS, CATV, WAN, (WIDE AREA NETWORKS), LAN (LOCAL AREA NETWORKS), AND ISDN (INTEGRATED SYSTEM DIGITAL NETWORK).THE WORK SHALL COVER THE PULLING OF WIRE IN RACEWAYS, BUT NOT THE INSTALLATION OF RACEWAYS. (DU PAGE COUNTY)$40.90$44.32$85.22ELEC0701-003
eff. 09/01/2025
ELEVATOR MECHANIC (DU PAGE, KANE, KENDALL, LAKE, & WILL COUNTIES)
Scope and notes

FOOTNOTES: A) PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; DAY AFTER THANKSGIVING DAY; VETERANS' DAY AND CHRISTMAS DAY. B) EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEE WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR EMPLOYEE WITH LESS THAN 5 YEARS SERVICE

$70.68$38.44$109.12ELEV0002-002
eff. 01/01/2025
ELEVATOR MECHANIC MCHENRY COUNTY)
Scope and notes

FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR UNDER 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING DAY, VETERANS' DAY AND CHRISTMAS DAY

$61.96$38.44$100.40ELEV0015-002
eff. 01/01/2025
ELEVATOR MECHANIC (GRUNDY COUNTY)
Scope and notes

FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR UNDER 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; DAY AFTER THANKSGIVING; VETERANS' DAY & CHRISTMAS DAY

$57.99$38.44$96.43ELEV0055-001
eff. 01/01/2025
OPERATOR: POWER EQUIPMENT, GROUP 4 (BUILDING AND RESIDENTIAL) BOBCATS AND/OR OTHER SKID STEER LOADERS; BRICK FORKLIFTS; OILERS$63.20$53.05$116.25ENGI0150-026
eff. 06/01/2026
OPERATOR: POWER EQUIPMENT, GROUP 3 (BUILDING AND RESIDENTIAL) AIR COMPRESSOR-SMALL 250 AND UNDER (1 TO 5 NOT TO EXCEED A TOTAL OF 300 FT); AIR COMPRESSOR-LARGE OVER 250; COMBINATION-SMALL EQUIPMENT OPERATOR; GENERATOR- SMALL 50 KW AND UNDER; GENERATOR-LARGE OVER 50 KW; HEATERS, MECHANICAL; HOISTS, INSIDE ELEVATORS (REMODELING OR RENOVATIN WORK); HYDRUALIC POWER UNITS (PILE DRIVING, EXTRACTING, AND DRILLING); LOW BOYS; PUMPS OVER 3" (1 TO 3 NOT TO EXCEED A TOTAL OF 300 FT); PUMPS, WELL POINTS; WELDING MACHINES (2 THROUGH 5); WINCHES, 4 SMALL ELECTRIC DRILL WINCHES; BOBCAT (UP TO AND INCLUDING 3/4 CU YD)$64.95$53.05$118.00ENGI0150-026
eff. 06/01/2026
OPERATOR: POWER EQUIPMENT, GROUP 2 (BUILDING AND RESIDENTIAL) BOBCAT (OVER 3/4 CU YD); BOILERS; BRICK FORKLIFT; BROOM, POWER PROPELLED; BULLDOZERS; CONCRETE MIXER (TWO BAG AND OVER); CONVEYOR, PORTABLE; FORKLIFT TRUCKS; GREASER ENGINEER; HIGHLIFT SHOVELS OR FRONT END LOADERS UNDER 2 1/4 CU YD; AOTOMATIC HOISTS, HOISTS, INSIDE ELEVATORS; HOISTS, SEWER DRAGGING MACHINE; HOISTS, TUGGER SINGLE DRUM; LASER SCREED; ROCK DRILL (SELF-PROPELLED); ROCK DRILL (TRUCK MOUNTED)*; ROLLERS; STEAM GENERATORS; TRACTORS; TRACTOR DRAWN VIBRATORY ROLLER (RECEIVES AN ADDITIONAL $.50 PER HOUR); WINCH TRUCKS WITH "A" FRAME. *-REQUIRES OILER$67.50$53.05$120.55ENGI0150-026
eff. 06/01/2026
OPERATOR: POWER EQUIPMENT, GROUP 1 (BUILDING AND RESIDENTIAL) MECHANIC; ASPHALT PLANT*; ASPHALT SPREADER; AUTOGRADE*; BACKHOES WITH CAISSON ATTACHMENT*:BATCH PLANT*; BENOTO(REQUIRES TWO ENGINEERS); BOILER AND THROTTLE VALVE; CAISSON RIGS*; CENTRAL REDI-MIX PLANT*; COMBINATION BACKHOE FRONT ENDLOADER MACHINE; COMPRESSOR AND THROTTLE VALVE; CONCRETE BREAKER (TRUCK MOUNTED)*; CONCRETE CONVEYOR; CONCRETE CONVEYOR, TRUCK MOUNTED; CONCRETE PAVER OVER 27E CU. FT.*; CONCRETE PAVER 27E CU FT AND UNDER*; CONCRETE PLACER*; CONCRETE PLACING BOOM; CONCRETE PUMP (TRUCK MOUNTED); CONCRETE TOWER; CRANES*; CRANES, HAMMERHEAD*; CRANES, (GCI AND SIMILAR TYPE REQUIRES TWO OPERATORS ONLY); CRETER CRANE; CRUSHER, STONE, ETC; DERRICKS; DERRICKS, TRAVELING*; FORMLESS CURB AND GUTTER MACHINE*; GRADER, ELEVATING; GROUTING MACHINES; HIGHLIFT SHOVELS OR FRONT ENDLOADER 2 1/4 YD. AND OVER; HOISTS, ELEVATORS, OUTSIDE TYPE RACK AND PINION AND SIMILAR MACHINES; HOISTS, ONE, TWO, AND THREE DRUM; HOISTS, TWO TUGGER ONE FLOOR; HYDRAULIC BACKHOES*; HYDRAULIC BOOM TRUCKS; HYDRAULIC VAC (AND SIMILAR EQUIPMENT);LOCOMOTIVES; MOTOR PATROL*; PILE DRIVERS AMD SKID RIG*; POST HOLE DIGGER; PRE- STRESS MACHINE; PUMP CRETES DUAL RAM(REQUIRING FREQUENT LUBRICATION AND WATER); PUMP CRETES; SQUEEZE CRETES-SCREW TYPE PUMPS GYPSUM BULKER AND PUMP; RAISED AND BLIND HOLE DRILL*; ROTO MILL GRINDER (36" AND OVER)*; ROTO MILL GRINDER (LESS THAN 36")*; SCOOPS-TRACTOR DRAWN; SLIP-FORM PAVER*; STRADDLE BUGGIES; TOURNAPULL; TRACTOR WITH BOOM, AND SIDE BOOM; AND TRENCHING MACHINES*. *-REQUIRES OILER$68.80$53.05$121.85ENGI0150-026
eff. 06/01/2026
IRONWORKER: STRUCTURAL AND REINFORCING (DU PAGE (EASTERN 1/4), LAKE, AND MCHENRY (HEBRON, WOODSTOCK, AND EAST THEREOF) COUNTIES)$62.46$46.58$109.04IRON0001-014
eff. 06/01/2025
IRONWORKER: SHEETER (DU PAGE (EASTERN 1/4), LAKE, AND MCHENRY (HEBRON, WOODSTOCK, AND EAST THEREOF) COUNTIES)$62.71$46.58$109.29IRON0001-014
eff. 06/01/2025
IRONWORKER, ORNAMENTAL (LAKE, DUPAGE (EASTERN 1/4) AND MCHENRY (HEBRON, WOODSTOCK & EAST THEREOF) COUNTIES)$59.26$44.81$104.07IRON0063-003
eff. 06/01/2025
IRONWORKER: FENCE ERECTOR (LAKE, DUPAGE (EASTERN 1/4), AND MCHENRY (HEBRON, WOODSTOCK & EAST THEREOF) COUNTIES)$52.25$34.31$86.56IRON0063-004
eff. 06/01/2025
IRONWORKER: MASTER RIGGERS (LAKE, DUPAGE (EASTERN 1/4) AND MCHENRY (HEBRON, WOODSTOCK & EAST THEREOF) COUNTIES)$56.75$47.38$104.13IRON0136-002
eff. 07/01/2025
IRONWORKER: MACHINERY MOVERS; RIGGERS; MACHINERY ERECTORS (LAKE, DUPAGE (EASTERN 1/4) AND MCHENRY (HEBRON, WOODSTOCK & EAST THEREOF) COUNTIES)$54.25$47.38$101.63IRON0136-002
eff. 07/01/2025
IRONWORKER (DUPAGE (REMAINDER), KANE, KENDALL (NORTHERN PART), AND MCHENRY (SOUTHEAST 1/4) COUNTIES)$48.83$39.84$88.67IRON0393-002
eff. 06/01/2021
IRONWORKER (DUPAGE (ARGONNE & VIC), GRUNDY, KENDALL (SOUTHERN PART), AND WILL COUNTIES)$47.80$42.50$90.30IRON0444-002
eff. 06/01/2022
IRONWORKER (MCHENRY COUNTY (NORTHWEST PART))$41.37$44.41$85.78IRON0498-006
eff. 06/01/2021
LABORER GROUP 12 DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSURE); ASBESTOS ABATEMENT LABORERS; TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS (DU PAGE COUNTY)$52.40$36.94$89.34LABO0002-003
eff. 06/01/2025
LABORER GROUP 11 JACKHAMMERMEN ON FIRE BRICK WORK ONLY (DU PAGE COUNTY)$51.68$36.94$88.62LABO0002-003
eff. 06/01/2025
LABORER GROUP 10 BOILER SETTER PLASTIC LABORERS (DU PAGE COUNTY)$51.85$36.94$88.79LABO0002-003
eff. 06/01/2025
LABORER GROUP 9 CHIMNEY ON FIRE BRICK; CAISSON DIGGERS; WELL POINT SYSTEM MEN (DU PAGE COUNTY)$51.75$36.94$88.69LABO0002-003
eff. 06/01/2025
LABORER GROUP 8 FIREBRICK & BOILER LABORERS (DU PAGE COUNTY)$51.73$36.94$88.67LABO0002-003
eff. 06/01/2025
LABORER GROUP 7 JACKHAMMERMEN, POWER DRIVEN CONCRETE SAWS AND OTHER POWER EQUIPMENT (DU PAGE COUNTY)$51.63$36.94$88.57LABO0002-003
eff. 06/01/2025
LABORER GROUP 6 STONE DERRICKMEN AND HANDLERS (DU PAGE COUNTY)$51.60$36.94$88.54LABO0002-003
eff. 06/01/2025
LABORER GROUP 5 CEMENT GUN NOZZLE (GUNITE) LABORERS; WINDLASS AND CAPSTAN PERSON (DU PAGE COUNTY)$51.55$36.94$88.49LABO0002-003
eff. 06/01/2025
LABORER GROUP 4 CHIMNEY OVER 40 FEET; SCAFFOLD LABORERS; WELDMAN-WRECKERS BURNERS (DU PAGE COUNTY)$51.50$36.94$88.44LABO0002-003
eff. 06/01/2025
LABORER GROUP 3 CEMENT GUN LABORERS AND HOSE (DU PAGE COUNTY)$51.48$36.94$88.42LABO0002-003
eff. 06/01/2025
LABORER GROUP 2 FIREPROOFING AND FIRE SHOP LABORERS (DU PAGE COUNTY)$51.40$36.94$88.34LABO0002-003
eff. 06/01/2025
LABORER GROUP 1 BUILDING LABORERS, PLASTERER TENDERS, PUMPS FOR DEWATERING & OTHER UNCLASSIFIED LABORERS (DU PAGE COUNTY)$51.40$36.94$88.34LABO0002-003
eff. 06/01/2025
LABORER GROUP 7 DOSIMETER (ANY DEVICE) USED FOR MONITORING NUCLEAR EXPOSURE; ASBESTOS ABATEMENT WORKER; TOXIC AND HAZARDOUS WASTE REMOVAL LABORER; AND CHIMNEY AND SILO LABORERS FOR EVERY ADDITIONAL 50 FEET OR ANY PART THEREOF ABOVE 100 FEET HIGH (GRUNDY AND WILL COUNTIES)$47.60$33.16$80.76LABO0075-001
eff. 06/01/2022
LABORER GROUP 6 ALL UNDERGROUND CAVERN LABORERS; CAISSON LABORERS 50 FEET OR MORE BELOW GROUND LEVEL; LABORERS WORKING UNDER RADIO ACTIVE CONDITIONS (SUITING UP); BLASTING MEN (POWDERMEN) (GRUNDY AND WILL COUNTIES)$47.75$33.16$80.91LABO0075-001
eff. 06/01/2022
LABORER GROUP 5 GUNNITE NOZZLE MEN; CAISSON LABORERS AND ALL TAMPING HAMMERS FROM 150 LBS AND OVER; FROM 15 FEET BELOW GROUND LEVEL DOWN TO 50 FEET; AND ALL LABORERS WORKING INSIDE OF A SPHERE OR ANY TYPE OF TANK FOR EVERY ADDITIONAL 50 FEET OR PART THEREOF ABOVE 100 FEET IN HEIGHT (GRUNDY AND WILL COUNTIES)$47.60$33.16$80.76LABO0075-001
eff. 06/01/2022
LABORER GROUP 4 TUNNEL MINERS, AND ALL LABORERS INSIDE TUNNEL; AIR BLOW PIPEMEN; TORCHMEN (BURNERS); MORTARING MEN ON SEWER AND DRAIN PIPE (THE APPLYING OF MORTAR AND COMPOSITION MIXES); ALL BOTTOM MEN ON SEWER WORK-ALL SEWER AND DRAIN PIPELAYERS-MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED ON PUBLIC UTILITY WORK-8 FEET OR MORE BELOW GROUND LEVEL, AND ALL OTHER SEWER AND TRENCH LABORERS 8 FEET OR MORE BELOW GROUND LEVEL REGARDLESS OF EXCAVATION AREA; ALL LABOR WORK INSIDE COFFERDAM; USE OF A 10 FOOT OR MORE DRILL STEEL FOR HAND HELD DRILLS; CAISSON LABORERS GROUND LEVEL DOWN 15 FEET; ALL AIR TOOLS 8 FEET OR MORE BELOW GROUND LEVEL; ALL LABORERS WORKING ON SWINGING-SUSPENDED OR ANY TYPE OR MAKE OF SCAFFOLDS, 48 FEET TO 100 FEET; ALL CHIMNEY AND SILO LABORERS WORKING AT A HEIGHT OF 48 TO 100 FEET; ALL TAMPING HAMMERS OVER 150 LBS.; ALL LABORERS WORKING INSIDE OF A SPHERE OR ANY TYPE OR MAKE OF TANK AT A HEIGHT OF 48 FEET TO 100 FEET; ALL HYDRAULIC, ELECTRIC AND AIR TOOLS OR ANY OTHER TYPE 8 FEET OR MORE BELOW GROUND LEVEL; VIBRATORS-ANY TYPE-8 FEET OR MORE BELOW GROUND LEVEL (GRUNDY AND WILL COUNTIES)$47.60$33.16$80.76LABO0075-001
eff. 06/01/2022
LABORER GROUP 3 ASPHALT RAKERS; HOD CARRIERS; PLASTERER LABORERS; GUNNITE LABORERS, SLAB FOR SETTERS ON ROADS, HIGHWAYS, STREETS, AIRPORT RUNAWAYS, AND RADII (ANY TYPE OF FORM) STRINGLINE MEN FOR ALL AFOREMENTIONED WORK; WAGON AND TOWER DRILLERS ON LAND AND FLOATING PLANT USED ON DREDGING; ASPHALT GUNNERS AND PLUG MEN (UNDERCOATING ON ROAD WORK); MORTAR PUMP LABORERS; PLASTER PUMP LABORERS (GRUNDY AND WILL COUNTIES)$47.48$33.16$80.64LABO0075-001
eff. 06/01/2022
LABORER GROUP 2 SEWER AND DRAIN PIPE LAYERS AND MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED, ON PUBLIC UTILITY WORK (GROUND LEVEL TO 8 FEET); PUMPCRETE PIPE HANDLERS (GRUNDY AND WILL COUNTIES)$47.40$33.16$80.56LABO0075-001
eff. 06/01/2022
LABORER GROUP 1 MORTAR MIXERS, HANDLING ASPHALT SHINGLES; SCAFFOLDS; SEWER AND TRENCH WORK (GROUND LEVEL DOWN TO 8 FEET); CATCH BASIN AND MANHOLE DIGGERS, MESH HANDLING ON ROAD WORK; CEMENT AND MINERAL FILLER HANDLER; CONCRETE PUDDLERS; BATCH DUMPERS (CEMENT & ASPHALT); VIBRATOR OPERATORS; SAND AND STONE WHEELERS TO MIXER HANDLERS); CONCRETE WHEELERS; AIRTAMPING HAMMERMEN; CONCRETE & PAVING BREAKERS; ROCK DRILLERS/JACKHAMMERMEN; CHIPPING HAMMERMEN 1-BAG MIXER; ASPHALT LABORER; CHAIN AND POWER SAWS; PIT MEN; FENCING LABORERS; MASON TENDERS (MORTAR AND BRICK WHEELER); KETTLEMEN & TARMEN, TANK CLEANERS; SCAFFOLD AND STAGING LABORERS; POT FIREMEN (TARMEN); HEATERS TENDER FOR ANY PURPOSE; WATER PUMPS (PORTABLE WATER PUMPS SHALL BE TENDED BY LABORERS IF THE EMPLOYER DETERMINES TENDING IS REQUIRED); RIP RAP; HANDLING OF SLAB STEEL ROAD FORMS IN ANY MANNER, EXCEPT ROAD FORM SETTING, SETTING CENTER STRIPS, CONTRACTION AND EXPANSION JOINTS (ROAD WORK); UNLOADING AND HANDLING OF LUMBER, BRICK, TRANSITE MATERIALS, CAST IRON WATER PIPE, REINFORCED CONCRETE RODS, SEWER AND DRAIN TILE, RAILROAD TILES AND ALL OTHER CREOSOTED MATERIALS; PAVING BLOCKS AND CONCRETE FORMS; HANDLING OF INSULATION OF ANY TYPE; ALL WORK INVOLVING THE UNLOADING OF MATERIALS, FIXTURES, OR FURNISHING, WHETHER CRATED OR UNCRATED; ALL MORTAR AND COMPOSITION MIXERS OF SEWER WORK; TRACK LABORERS; CHIMNEY AND SILO LABORERS WORKING AT A HEIGHT OF 1 TO 48 FEET; ALL LABORERS WORKING ON SWINGING SUSPENDED, OR ANY TYPE OR MAKE OF SCAFFOLDING 1 TO 48 FEET; ALL LABORERS WORKING INSIDE A SPHERE OR ANY TYPE OR MAKE OF TANK; WORKING INSIDE A SPHERE OR ANY TYPE OR MAKE OF TANK FROM BOTTOM TO A HEIGHT OF 48 FEET; FORM STRIPPERS (ANY TYPE); MECHANICAL OR MOTORIZED BUGGIES, FOR CONCRETE OR MASONS EMPLOYERS; USE OF SKID STEER LOADS OR ANY OTHER MACHINERY WHICH REPLACES THE WHEELBARROW OR BUGGY; HANDLING MULTIPLE CONCRETE DUCT OR ANY OTHER TYPE OF PIPE USED IN PUBLIC UTILITY WORK UNLESS OTHERWISE SPECIFIED HEREIN; SNAPPING OF WALL TIES AND REMOVAL OF RODS; DRILLING OF ANCHOR BOLT HOLES; CONCRETE OR ASPHALT CLIPPER TYPE SAWS AND SELF-PROPELLED SAWS; SHOULDER AND GRADE LABORERS; ALL HYDRAULIC ELECTRIC AND AIR OR ANY OTHER TYPE OF TOOLS; GROUTING AND CAULKING; CLEANING LUMBER, NAIL PULLING, DECK HAND; DREDGEHAND; SHORE LABORER; BANKMEN ON FLOATING PLANT; TOOL AND MATERIAL CHECKERS; SIGNALMEN AND FLAGMEN ON ALL CONSTRUCTION WORK; CLEANING OF DEBRIS; REMOVAL OF TREES; CONCRETE CURING, TEMPORARY CONCRETE PROTECTION REGARDLESS OF MANNER OR MATERIALS USED; LABORERS ON APSCO; JANITORIAL; WRECKING AND DEMOLITION LABORERS (GRUNDY AND WILL COUNTIES)$47.40$33.16$80.56LABO0075-001
eff. 06/01/2022
LABORER: GROUP 2 POWER VIBRATOR KANE, KENDALL, AND MCHENRY COUNTIES$51.65$36.94$88.59LABO0149-001
eff. 06/01/2025
LABORER: GROUP 1 COMMON LABORER KANE, KENDALL, AND MCHENRY COUNTIES$51.40$36.94$88.34LABO0149-001
eff. 06/01/2025
LABORER GROUP 8 ASBESTOS ABATEMENT LABORERS, TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS, DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSUREANE KENDALL, AND MCHENRY COUNTIES$51.80$36.94$88.74LABO0149-001
eff. 06/01/2025
LABORER GROUP 7 CAISSON LABORERS; DYNAMITERS KANE, KENDALL, AND MCHENRY COUNTIES$52.10$36.94$89.04LABO0149-001
eff. 06/01/2025
LABORER GROUP 6 TILE LAYERS; BOTTOM MEN KANE, KENDALL, AND MCHENRY COUNTIES$52.10$36.94$89.04LABO0149-001
eff. 06/01/2025
LABORER GROUP 5 JACKHAMMER & AIRSPADE; CHAINSAW, SWINGING STAGE AND BOATSWAIN CHAIR; CEMENT GUN NOZZLEMAN; HOD CARRIER; PLASTERER TENDER, AND TUNNEL MAN KANE, KENDALL, AND MCHENRY COUNTIES$51.65$36.94$88.59LABO0149-001
eff. 06/01/2025
LABORER GROUP 4 POWER TAMPER KANE, KENDALL, AND MCHENRY COUNTIES$51.65$36.94$88.59LABO0149-001
eff. 06/01/2025
LABORER GROUP 3 TORCHMAN (DEMOLITION ONLY), MORTARMEN KANE, KENDALL, AND MCHENRY COUNTIES$51.40$36.94$88.34LABO0149-001
eff. 06/01/2025
LABORER GROUP 11 DOSIMETER (ANY DEVICE) MONITORING NUCLEAR EXPOSURE; ASBESTOS ABATEMENT LABORERS; TOXIC AND HAZARDOUS WASTE REMOVAL LABORERS (LAKE COUNTY)$51.60$36.94$88.54LABO0152-001
eff. 06/01/2025
LABORER GROUP 10 BOILER SETTER PLASTIC LABORERS (LAKE COUNTY)$51.95$36.94$88.89LABO0152-001
eff. 06/01/2025
LABORER GROUP 9 WINDLASS AND CAPSTAN PERSONS (LAKE COUNTY)$51.60$36.94$88.54LABO0152-001
eff. 06/01/2025
LABORER GROUP 8 CHIMNEY LABORERS (ON FIRE BRICK); CAISSON DIGGERS; WELL POINT SYSTEM MEN (LAKE COUNTY)$51.75$36.94$88.69LABO0152-001
eff. 06/01/2025
LABORER GROUP 7 FIREBRICK & BOILER LABORER SETTERS (LAKE COUNTY)$51.73$36.94$88.67LABO0152-001
eff. 06/01/2025
LABORER GROUP 6 JACKHAMMERMEN (TAMPERS & VIBRATORS); POWER DRIVEN CONCRETE SAWS (LAKE COUNTY)$51.63$36.94$88.57LABO0152-001
eff. 06/01/2025
LABORER GROUP 5 STONE DERRICKMEN AND HANDLERS (LAKE COUNTY)$51.60$36.94$88.54LABO0152-001
eff. 06/01/2025
LABORER GROUP 4 CEMENT GUN NOZZLE (GUNITE) LABORERS (LAKE COUNTY)$51.60$36.94$88.54LABO0152-001
eff. 06/01/2025
LABORER GROUP 3 CHIMNEY OVER 40 FEET; SCAFFOLD LABORERS; WALL MEN OR WRECKERS (LAKE COUNTY)$51.50$36.94$88.44LABO0152-001
eff. 06/01/2025
LABORER GROUP 2 CEMENT GUN LABORERS AND HOSE (LAKE COUNTY)$51.48$36.94$88.42LABO0152-001
eff. 06/01/2025
LABORER GROUP 1 BUILDING LABORERS; PLASTERER TENDERS, GENERAL LABORERS (WRECKING AND DEMOLITION); FIREPROOFING AND FIRE SHOP LABORERS (LAKE COUNTY)$51.40$36.94$88.34LABO0152-001
eff. 06/01/2025
PAINTER: BRUSH, DECORATOR, AND PAPERHANGER (GRUNDY, LAKE, AND WILL COUNTIES)$53.05$33.91$86.96PAIN0014-002
eff. 06/01/2024
GLAZIER$51.55$44.09$95.64PAIN0027-003
eff. 06/01/2024
PAINTER: BRUSH, DRYWALL TAPER/FINISHER, SANDBLASTER, AND SPRAY (DE KALB, DU PAGE, KANE, KENDALL AND MCHENRY COUNTIES)$53.05$27.63$80.68PAIN0030-001
eff. 06/01/2024
PLASTERER (GRUNDY AND WILL COUNTIES)$42.25$26.65$68.90PLAS0005-003
eff. 07/01/2015
PLASTERER (DU PAGE COUNTY)$42.25$26.65$68.90PLAS0005-006
eff. 07/01/2015
CEMENT MASON/CONCRETE FINISHER (DE KALB, KANE, KENDALL, AND MCHENRY COUNTIES)$50.70$40.60$91.30PLAS0011-008
eff. 06/01/2023
CEMENT MASON/CONCRETE FINISHER (GRUNDY AND WILL COUNTIES)$46.25$45.10$91.35PLAS0011-012
eff. 06/01/2023
PLASTERER (LAKE COUNTY)$49.65$42.17$91.82PLAS0011-014
eff. 06/01/2023
CEMENT MASON/CONCRETE FINISHER (LAKE COUNTY)$48.50$42.82$91.32PLAS0011-014
eff. 06/01/2023
CEMENT MASON/CONCRETE FINISHER (DUPAGE COUNTY)$38.00$24.03$62.03PLAS0803-002
eff. 08/01/2010
PLUMBER (LAKE AND MCHENRY COUNTIES)$45.76$26.92$72.68PLUM0093-001
eff. 06/01/2015
PLUMBER (DUPAGE (ARGONNE NATIONAL LABORATORIES AND FERMI NATIONAL LABORATORY), GRUNDY & WILL COUNTIES)$60.50$39.02$99.52PLUM0130-002
eff. 06/01/2025
PLUMBER/PIPEFITTER (DUPAGE (EXCLUDING ARGONNE NATIONAL LABORATORY AND FERMI NATIONAL LABORATORY), KANE, AND KENDALL (EXCEPT THE MICH-WIS PUMPING STATION IN MILBROOK, SILICAS AND PLANT AND VILLAGE OF NEWARK, EXCLUDES YORKVILLE) COUNTIES)$41.20$29.15$70.35PLUM0501-001
eff. 12/01/2013
PIPEFITTER (DUPAGE (ARGONNE NATIONAL LABORATORIES, AND FERMI NATIONAL LABORATORY), GRUNDY, LAKE, MCHENRY & WILL COUNTIES)$55.00$38.62$93.62PLUM0597-001
eff. 06/01/2023
ROOFER (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES)$50.25$30.43$80.68ROOF0011-004
eff. 12/01/2024
ROOFER$38.50$27.23$65.73ROOF0011-009
eff. 12/01/2024
SPRINKLER FITTER (DUPAGE, KANE, KENDALL, LAKE, MCHENRY, AND WILL COUNTIES)$63.25$36.50$99.75SFIL0281-002
eff. 07/01/2025
SHEET METAL WORKER (LAKE COUNTY)$49.10$42.91$92.01SHEE0073-003
eff. 06/01/2022
SHEET METAL WORKER: ALUMINUM GUTTER WORK (LAKE COUNTY)$31.32$37.02$68.34SHEE0073-004
eff. 06/08/2018
SHEET METAL WORKER (DU PAGE, GRUNDY, KANE, KENDALL, MCHENRY, AND WILL COUNTIES)$56.35$38.65$95.00SHEE0265-001
eff. 06/01/2024
TRUCK DRIVER: 6 AXLE TRUCKS (GRUNDY, KENDALL, AND WILL COUNTIES)
Scope and notes

FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES

$46.67$0.30$46.97TEAM0179-001
eff. 06/01/2025
TRUCK DRIVER: 5 AXLE TRUCKS (GRUNDY, KENDALL, AND WILL COUNTIES)
Scope and notes

FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES

$46.47$0.30$46.77TEAM0179-001
eff. 06/01/2025
TRUCK DRIVER: 4 AXLE TRUCKS (GRUNDY, KENDALL, AND WILL COUNTIES)
Scope and notes

FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES

$46.27$0.30$46.57TEAM0179-001
eff. 06/01/2025
TRUCK DRIVER: 2 OR 3 AXLE TRUCKS (GRUNDY, KENDALL, AND WILL COUNTIES)
Scope and notes

FOOTNOTES: A. $448.80 HEALTH & WELFARE PER WEEK, $562.80 PENSION PER WEEK. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES

$46.12$0.30$46.42TEAM0179-001
eff. 06/01/2025
TRUCK DRIVER: 6 AXLES (LAKE AND MCHENRY COUNTIES)
Scope and notes

FOOTNOTES: A.$500.00 PER WEEK PENSION. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$45.09$13.40$58.49TEAM0301-001
eff. 06/01/2024
TRUCK DRIVER: 5 AXLES (LAKE AND MCHENRY COUNTIES)
Scope and notes

FOOTNOTES: A.$500.00 PER WEEK PENSION. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$44.89$13.40$58.29TEAM0301-001
eff. 06/01/2024
TRUCK DRIVER: 4 AXLES (LAKE AND MCHENRY COUNTIES)
Scope and notes

FOOTNOTES: A.$500.00 PER WEEK PENSION. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$44.69$13.40$58.09TEAM0301-001
eff. 06/01/2024
TRUCK DRIVER: 2-3 AXLES (LAKE AND MCHENRY COUNTIES)
Scope and notes

FOOTNOTES: A.$500.00 PER WEEK PENSION. B. LOWBOY IS AN ADDITIONAL $1.50 PER HOUR AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$44.54$13.40$57.94TEAM0301-001
eff. 06/01/2024
TRUCK DRIVER: 6 AXLES (DU PAGE AND KANE COUNTIES)
Scope and notes

FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$45.86$0.30$46.16TEAM0673-003
eff. 06/01/2025
TRUCK DRIVER: 5 AXLES (DU PAGE AND KANE COUNTIES)
Scope and notes

FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$45.66$0.30$45.96TEAM0673-003
eff. 06/01/2025
TRUCK DRIVER: 4 AXLES (DU PAGE AND KANE COUNTIES)
Scope and notes

FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$45.46$0.30$45.76TEAM0673-003
eff. 06/01/2025
TRUCK DRIVER: 2-3 AXLES (DU PAGE AND KANE COUNTIES)
Scope and notes

FOOTNOTE: A. AN ADDITIONAL $.20 PER AXLE SHALL BE PAID FOR ALL VEHICLES WITH MORE THAN SIX (6) AXLES. LOW-BOY IS AN ADDITIONAL $1.50 PER HOUR HEALTH AND WELFARE: $453.20 PER WEEK PENSON: $589.90 PER WEEK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY. 900 STRAIGHT TIME HOURS OR MORE IN 1 CALENDAR YEAR FOR THE SAME EMPLOYER SHALL RECEIVE 1 WEEK PAID VACATION; 3 YEARS - 2 WEEKS PAID VACATION; 10 YEARS - 3 WEEKS PAID VACATION; 20 YEARS - 4 WEEKS PAID VACATION

$45.31$0.30$45.61TEAM0673-003
eff. 06/01/2025

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 3 published 10/22/2026. We format and check the official text; the determination in your contract is what applies.