Kansas prevailing wage rates: KS20260130
Highway construction in Cheyenne, Comanche, Edwards, Elk, Gove, Greeley, Meade, Morton, Ness, Phillips, Rawlins, Rush, Smith, Stanton, Wichita Counties.
KS20260130, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| POWER EQUIPMENT OPERATOR: DRILL RIG CAISSONS | $38.83 | $20.80 | $59.63 | ENGI0101-002 eff. 05/01/2025 |
| IRONWORKER, STRUCTURAL | $39.00 | $34.25 | $73.25 | IRON0010-007 eff. 04/01/2025 |
| TRUCK DRIVER: OFF ROAD TRUCK | $16.38 | $0.00 | $16.38 | SUKS2019-069 eff. 05/09/2019 |
| TRUCK DRIVER: FLATBED AND LOWBOY | $19.20 | $0.00 | $19.20 | SUKS2019-069 eff. 05/09/2019 |
| TRUCK DRIVER: DUMP AND TANDEM | $15.79 | $0.00 | $15.79 | SUKS2019-069 eff. 05/09/2019 |
| TRUCK DRIVER: WATER TRUCK | $17.07 | $0.00 | $17.07 | SUKS2019-069 eff. 05/09/2019 |
| TRUCK DRIVER: PICKUP TRUCK | $16.19 | $0.00 | $16.19 | SUKS2019-069 eff. 05/09/2019 |
| TRAFFIC CONTROL: SERVICE DRIVER | $14.55 | $0.00 | $14.55 | SUKS2019-069 eff. 05/09/2019 |
| SERVICEMAN: EQUIPMENT | $16.33 | $1.74 | $18.07 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: STRIPING MACHINE | $19.93 | $4.49 | $24.42 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: ROTO MILL GROUNDMAN | $15.35 | $0.00 | $15.35 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: ROTO MILL | $17.80 | $0.00 | $17.80 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: TRACTOR | $16.24 | $0.00 | $16.24 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: SCREED | $15.56 | $0.00 | $15.56 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: SCRAPER | $15.68 | $0.00 | $15.68 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: ROLLER | $14.17 | $0.00 | $14.17 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $16.03 | $0.00 | $16.03 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: MECHANIC | $20.51 | $0.00 | $20.51 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: MATERIAL TRANSFER VEHICLE | $13.92 | $0.00 | $13.92 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: LOADER | $15.75 | $0.00 | $15.75 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: GRADER/BLADE | $17.89 | $1.67 | $19.56 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: DISTRIBUTOR | $15.19 | $0.00 | $15.19 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: CRANE | $20.22 | $7.66 | $27.88 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: CONCRETE SAW | $16.71 | $0.00 | $16.71 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: CONCRETE FINISHING MACHINE | $21.11 | $0.00 | $21.11 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: BULLDOZER | $17.17 | $2.37 | $19.54 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: BROOM/SWEEPER | $13.64 EO 13658 minimum $13.65 may apply | $0.00 | $13.64 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $16.90 | $0.00 | $16.90 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $18.77 | $2.19 | $20.96 | SUKS2019-069 eff. 05/09/2019 |
| OPERATOR: ASPHALT PLANT | $14.81 | $0.00 | $14.81 | SUKS2019-069 eff. 05/09/2019 |
| LABORER: FLAGGER | $12.14 EO 13658 minimum $13.65 may apply | $0.00 | $12.14 | SUKS2019-069 eff. 05/09/2019 |
| LABORER: COMMON OR GENERAL | $14.71 | $0.00 | $14.71 | SUKS2019-069 eff. 05/09/2019 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $14.38 | $0.00 | $14.38 | SUKS2019-069 eff. 05/09/2019 |
| IRONWORKER, REINFORCING | $14.09 | $0.00 | $14.09 | SUKS2019-069 eff. 05/09/2019 |
| FORM WORKER | $15.33 | $1.20 | $16.53 | SUKS2019-069 eff. 05/09/2019 |
| ELECTRICIAN | $26.72 | $4.22 | $30.94 | SUKS2019-069 eff. 05/09/2019 |
| CEMENT MASON/CONCRETE FINISHER | $16.24 | $0.00 | $16.24 | SUKS2019-069 eff. 05/09/2019 |
| CARPENTER | $14.94 | $0.00 | $14.94 | SUKS2019-069 eff. 05/09/2019 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.