Massachusetts prevailing wage rates: MA20260003
Building construction in Berkshire, Franklin, Hampden, Hampshire Counties.
MA20260003, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No existing rate changed amount.
3 classifications added, 5 removed or reworded
- removed BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS was $50.81 + $32.27 fringe
- added BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD BERKSHIRE) $50.81 + $32.27 fringe
- added PAINTER: BRUSH, TAPER (NEW CONSTRUCTION) $38.08 + $31.95 fringe
- removed PAINTER: NEW CONSTRUCTION: Brush, Taper was $38.08 + $31.95 fringe
- removed PAINTER: NEW CONSTRUCTION: Spray, Sandblast was $39.48 + $31.95 fringe
- added PAINTER: SPRAY, SANDBLAST (NEW CONSTRUCTION) $39.48 + $31.95 fringe
- removed Plasterer tender: BARNSTABLE, BRISTOL, DUKES, ESSEX, NANTUCKET, MIDDLESEX (with the exception of Arlington, Belmont, Burlington, Cambridge, Everett, Malden, Medford, Melrose, Reading, Somerville, Stoneham, Wakefield, Winchester, Winthrop and Woburn); NORFOLK (with the exception of Brookline Dedham and Milton) COUNTIES was $38.95 + $29.70 fringe
- removed Plasterer tender: SUFFOLK COUNTY (Boston, Chelsea, Revere, Winthrop, Deer Island, Nut Island); MIDDLESEX COUNTY (Arlington, Belmont, Burlington, Cambridge, Everett, Malden, Medford, Melrose, Reading, Somerville, Stoneham, Wakefield, Winchester, Winthrop and Woburn only); NORFOLK COUNTY (Brookline, Dedham, and Milton only) was $46.20 + $29.70 fringe
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| INSULATOR/ASBESTOS WORKER (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS) | $44.36 | $36.63 | $80.99 | ASBE0006-011 eff. 09/01/2024 |
| BOILERMAKER | $50.62 | $28.82 | $79.44 | BOIL0029-001 eff. 01/01/2025 |
| BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD CHAPTER FRANKLIN, HAMPDEN, AND HAMPSHIRE COUNTIES) | $50.81 | $32.27 | $83.08 | BRMA0001-001 eff. 08/01/2023 |
| BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD BERKSHIRE) | $50.81 | $32.27 | $83.08 | BRMA0001-003 eff. 08/01/2023 |
| PILEDRIVERMAN | $55.79 | $35.47 | $91.26 | CARP0056-014 eff. 08/01/2024 |
| CARPENTER (FRANKLIN COUNTY (ERVING, ORANGE, NORTH ORANGE AND WARWICK)) | $43.33 | $27.82 | $71.15 | CARP0336-006 eff. 09/01/2025 |
| CARPENTER/LATHER/DRYWALL APPLICATOR (HAMPDEN; HAMPSHIRE AND FRANKLIN (REMAINDER)) | $43.33 | $27.82 | $71.15 | CARP0336-009 eff. 09/01/2025 |
| CARPENTER (BERKSHIRE COUNTY) | $43.33 | $27.82 | $71.15 | CARP0336-013 eff. 09/01/2025 |
| MILLWRIGHT | $43.42 | $33.00 | $76.42 | CARP1121-004 eff. 04/21/2025 |
| FLOOR LAYER: CARPET | $43.23 | $27.79 | $71.02 | CARP2168-003 eff. 09/01/2025 |
| ELECTRICIAN (HAMPDEN (EXCEPT CHESTER & HOLYOKE); HAMPSHIRE (BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 | ELEC0007-002 eff. 06/29/2025 |
| ELECTRICIAN (BERKSHIRE; FRANKLIN; HAMPDEN (CHESTER, HOLYOKE); HAMPSHIRE (EXCEPT BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 | ELEC0007-003 eff. 06/29/2025 |
| TELEDATA SYSTEM INSTALLER | $52.16 | $29.56 | $81.72 | ELEC0007-006 eff. 06/29/2025 |
| LINE CONSTRUCTION: MATERIAL MAN, TRACTOR TRAILER DRIVER, EQUIPMENT OPERATOR | $39.92 | $21.80 | $61.72 | ELEC0042-003 eff. 09/03/2017 |
| LINE CONSTRUCTION: LINEMAN, CABLE SPLICER AND DYNAMITE MAN | $46.96 | $25.05 | $72.01 | ELEC0042-003 eff. 09/03/2017 |
| LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATOR | $42.26 | $22.56 | $64.82 | ELEC0042-003 eff. 09/03/2017 |
ELEVATOR MECHANICScope and notesFOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $66.41 | $38.44 | $104.85 | ELEV0041-001 eff. 01/01/2025 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 15 BOOM LENGTHS OVER 350 FEET INCLUDING JIBScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $50.73 | $30.58 | $81.31 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 14 BOOM LENGTHS OVER 300 FEET INCLUDING JIBScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $49.23 | $30.58 | $79.81 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 13 BOOM LENGTHS OVER 250 FEET INCLUDING JIBScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $48.23 | $30.58 | $78.81 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 12 BOOM LENGTHS OVER 200 FEET INCLUDING JIBScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.23 | $30.58 | $77.81 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 11 BOOM LENGTHS OVER 150 FEET INCLUDING JIBScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $45.73 | $30.58 | $76.31 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 10 MASTER MECHANICScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $44.73 | $30.58 | $75.31 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 9 OILERScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $42.72 | $30.58 | $73.30 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 8 TRUCK CRANE CREWSScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $42.41 | $30.58 | $72.99 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 7 COMPRESSORS UP TO 315 CU FT; SMALL MIXERS WITH SKIP; PUMPS UP TO 4 INCHES; POWER HEATERS; OILER; A-FRAME TRUCKS; FORKLIFTS-UP TO 7 FT. LIFT AND UP TO 3 TON CAPACITY; HYDRO BROOM; STUD WELDERScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $52.73 | $30.58 | $83.31 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 6 COMPRESSOR (ONE OR TWO) 315 CU FT TO 900 CU FT; PUMPS 4 INCHES TO 16 INCHES (TOTAL DISCHARGE)Scope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $34.41 | $30.58 | $64.99 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 5 HOISTS; CONVEYORS; POWER PAVEMENT BREAKERS; SELF-POWERED CONCRETE PAVEMENT FINISHINGScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAYMACHINES; TWO BAG MIXERS WITH SKIP; MCCARTHY AND SIMILAR DRILLS; BATCH PLANTS (NOT SELF LOADING); BULK CEMENT PLANTS; SELF-PROPELLED MATERIAL SPREADERS; THREE OR MORE 10 KW LIGHT PLANTS; 30 KW OR MORE GENERATORS; POWER BROOM | $36.35 | $30.58 | $66.93 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 4 ASPHALT ROLLERS; SELF-POWERED ROLLERS AND COMPACTORS; TRACTOR WITHOUT BLADE DRAWING SHEEPSFOOT ROLLER; RUBBER TIRE ROLLER; VIBRATORY ROLLER OR OTHER TYPE OF COMPACTORS INCLUDING MACHINES FOR PULVERIZING AND AERATING SOIL; YORK RAKEScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $37.47 | $30.58 | $68.05 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 3 COMBINATION BACKHOE/LOADER UP TO 3/4 CU YD; SCRAPERS UP TO 21 CU YD (STRUCK LOAD, SELF PROPELLED OR TRACTOR DRAWN); TIREMAN; FRONT END LOADERS UP TO 4 YDS; WELL DRILLERS; ENGINEER OR FIREMAN ON HIGH PRESSURE BOILER; SELF-LOADING BATCH PLANT; WELL POINT OPERATORS ELECTRIC PUMPS USED IN WELL POINT SYSTEM; PUMPS, 16 INCHES AND OVER (TOTAL DISCHARGE); COMPRESSOR, ONE OR TWO 900 CU FT AND OVER; POWERED GREASE TRUCK; TUNNEL LOCOMOTIVES AND DINGYS; GROUT PUMPS; HYDRAULIC JACKS; BOOM TRUCK; HYDRAULIC CRANES- UP TO 10 TONScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $40.70 | $30.58 | $71.28 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 2 ROTARY DRILL WITH MOUNTED COMPRESSOR; COMPRESSOR HOUSE (3 TO 6 COMPRESSORS); ROCK AND EARTH BORING MACHINES (EXCLUDING MCCARTHY AND SIMILAR DRILLS); FRONT END LOADERS 4 CU YDS TO 5 1/2 CU YDS); FORKLIFTS-7 FT LIFT AND OVER 3 TON CAPACITY; SCRAPER 21 YDS AND OVER (STRUCK LOAD); SONIC HAMMER CONSOLE; RECLAIMERS ROAD PLANER/MILLING MACHINE; CAL TRACKS; BALLAST REGULATORS; RAIL ANCHOR MACHINES; SWITCH TAMPERS, ASPHALT PAVERS; MECHANIC; WELDER AND TRANSFER MACHINE. HAZARDOUS WASTE PREMIUM $2.00Scope and notesFOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $40.92 | $30.58 | $71.50 | ENGI0098-001 eff. 06/01/2024 |
POWER EQUIPMENT OPERATORS:, BUILDING & RESIDENTIAL: GROUP 1 SHOVELS; CRAWLERS AND TRUCK CRANES INCLUDING ALL TOWER; SELF-PROPELLED HYDRAULIC CRANES 10 TONS AND OVER; DRAGLINES; CLAM SHELLS; CABLEWAYS; SHAFT HOISTS; MUCKING MACHINES DERRICKS; BACKHOES; BULLDOZERS; GRADALLS; ELEVATING GRADERS; PILE DRIVERS; CONCRETE PAVERS; TRENCHING MACHINES; FRONT END LOADERS- 5 1/2 CU YDS AND OVER; DUAL DRUM PAVER; AUTOMATIC GRADER-EXCAVATOR(C.M.I. OR EQUAL); SCRAPERS TOWING PAN OR WAGON; TANDEM DOZERS OR PUSH CATS(2 UNITS IN TANDEM); SHOTCRETE MACHINE; TUNNEL BORING MACHINE; COMBINATION BACKHOE/LOADER 3/4 CU YD HOE OR OVER; JET ENGINE DRYER; TREE SHREDDER; POST HOLE DIGGER; POST HOLE HAMMER; POST EXTRACTOR; TRUCK MOUNTED CONCRETE PUMP WITH BOOM; ROTO-MILL; GRADER; HORIZONTAL DRILLING MACHINE; JOHN HENRY ROCK DRILL AND SIMILAR EQUIPMENTScope and notesHAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.23 | $30.58 | $71.81 | ENGI0098-001 eff. 06/01/2024 |
| IRONWORKER (BERKSHIRE (BECKET, EAST OTIS, HINSDALE, MONTEREY, NEW MARLBORO, NORTH OTIS, OTIS, PERU, SANDISFIELD, SAVOY, SHEFFIELD, WASHINGTON, WINDSOR); FRANKLIN; HAMPDEN; HAMPSHIRE) | $41.89 | $33.90 | $75.79 | IRON0007-014 eff. 09/16/2025 |
| IRONWORKER (BERKSHIRE (LEE)) | $40.75 | $31.91 | $72.66 | IRON0012-003 eff. 07/01/2025 |
| IRONWORKERS: STRUCTURAL, ORNAMENTAL, REINFORCING, FENCE ERECTOR, MACHINERY MOVER, RIGGER, RODMAN, STONE DERRICKMAN (BERKSHIRE (REMAINDER OF COUNTY)) | $40.75 | $31.91 | $72.66 | IRON0012-004 eff. 07/01/2025 |
| IRONWORKERS: SHEETER (BERKSHIRE (REMAINDER OF COUNTY)) | $41.00 | $31.91 | $72.91 | IRON0012-004 eff. 07/01/2025 |
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (ORANGE, WARWICK)) | $40.95 | $29.70 | $70.65 | LABO0022-002 eff. 12/01/2024 |
| LABORERS: GROUP 5 PRECAST FLOOR AND ROOF, PLANK ERECTOR (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 | LABO0022-002 eff. 12/01/2024 |
| LABORERS: GROUP 4 BLASTER; POWDERMAN (FRANKLIN (ORANGE, WARWICK)) | $39.95 | $29.70 | $69.65 | LABO0022-002 eff. 12/01/2024 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 | LABO0022-002 eff. 12/01/2024 |
| LABORERS: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENMDER; PIPELAYER; PNEUMATIC DRILL OPERATOR; PNEUMATIC TOOL OPERATOR; WAGON DRILL OPERATORM JACKHAMMER OPERATOR, PAVEMENT BREAKER, CARBIDE CORE DRILLING MACHINE, CHAIN SAW OPERATOR, BARCO TYPE JUMPING TAMPERS, CONCRETE PUMP, MOTORIZED MORTAR MINER, RIDE-ON MOTORIZED BUGGY (FRANKLIN (ORANGE, WARWICK)) | $39.20 | $29.70 | $68.90 | LABO0022-002 eff. 12/01/2024 |
| LABORERS: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS (FRANKLIN (ORANGE, WARWICK)) | $38.95 | $29.70 | $68.65 | LABO0022-002 eff. 12/01/2024 |
| LABORERS: (BERKSHIRE COUNTY, FRANKLIN COUNTY, (THE TOWNS OF ASHFIELD, BUCKLAND, CHARLEMONT, HAWLEY, HEATH, AND ROWE ONLY) HAMPSHIRE COUNTY (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $31.54 | $25.63 | $57.17 | LABO0473-001 eff. 12/01/2024 |
| LABORERS: GROUP 5 POWDERMAN AND BLASTER (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $36.00 | $28.87 | $64.87 | LABO0596-001 eff. 12/02/2024 |
| LABORERS: GROUP 4 AIR TRACK OPERATORS, BLOCK PAVERS, RAMMERS AND CURB SETTERS, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.75 | $28.87 | $64.62 | LABO0596-001 eff. 12/02/2024 |
| LABORERS: GROUP 3 PRECAST FLOOR AND ROOF PLANK ERECTORS, SIGN ERECTORS, ASBESTOS REMOVAL LABORERS, HAZ-MAT LABORERS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.75 | $28.87 | $64.62 | LABO0596-001 eff. 12/02/2024 |
| LABORERS: GROUP 2 ASPHALT RAKERS, CARBIDE CORE DRILLER OPERATORS, CHAIN SAW OPERATORS, PIPELAYERS, JACKHAMMER AND PAVING BREAKER OPERATORS, BARCO TYPE JUMPING TAMPERS, LASER BEAM OPERATORS, CONCRETE PUMP OPERATORS, MASON TENDERS, MOTORIZED MORTAR MIXERS, RIDE-ON MOTORIZED BUGGY OPERATORS, WAGON DRILL OPERATORS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.25 | $28.87 | $64.12 | LABO0596-001 eff. 12/02/2024 |
| LABORERS: GROUP 1 LABORERS, CARPENTER TENDERS, WRECKING LABORERS (HAMPDEN COUNTY, HAMPSHIRE COUNTY (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINNGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON) FRANKLIN COUNTY (WITH THE EXCEPTION OF ASHFIELD, BUCKLAND, CHARLEMONT, HAULY, HEATH, ORANGE,ROWE AND WARWICK)) | $35.00 | $28.87 | $63.87 | LABO0596-001 eff. 12/02/2024 |
| MARBLE FINISHER | $28.43 | $25.85 | $54.28 | MARB0097-001 eff. 03/01/2012 |
GLAZIERScope and notesFOOTNOTE: A. PAID HOLIDAY: LABOR DAY (PROVIDED EMPLOYEE HAS WORKED ANY PART OF THE WEEK PRIOR TO LABOR DAY AND ANY PART OF THE WEEK AFTER LABOR DAY | $43.13 | $21.00 | $64.13 | PAIN0011-008 eff. 06/01/2025 |
| PAINTER: SPRAY, SANDBLAST (NEW CONSTRUCTION) | $39.48 | $31.95 | $71.43 | PAIN0035-007 eff. 07/01/2024 |
| PAINTER: BRUSH, TAPER (NEW CONSTRUCTION) | $38.08 | $31.95 | $70.03 | PAIN0035-007 eff. 07/01/2024 |
| PAINTER REPAINT: SPRAY, SANDBLAST | $36.80 | $31.95 | $68.75 | PAIN0035-007 eff. 07/01/2024 |
| PAINTER REPAINT: BRUSH, TAPER | $35.40 | $31.95 | $67.35 | PAIN0035-007 eff. 07/01/2024 |
| PLUMBER AND STEAMFITTER (FRANKLIN (ORANGE)) | $55.00 | $31.57 | $86.57 | PLUM0004-003 eff. 09/01/2025 |
| PLUMBERS AND PIPEFITTERS (BERKSHIRE (BECKET, OTIS, SANDISFIELD); FRANKLIN (EXCEPT MONROE, ROWE, AND THE WESTERN PART OF CHARLEMONT); HAMPDEN; HAMPSHIRE) | $52.26 | $31.05 | $83.31 | PLUM0104-004 eff. 09/17/2025 |
| PLUMBER AND STEAMFITTER (BERKSHIRE (EXCEPT OTIS, BECKET, SANDISFIELD); FRANKLIN (MONROE, ROWE AND THE WESTERN PART OF CHARLEMONT)) | $52.26 | $31.05 | $83.31 | PLUM0104-009 eff. 09/17/2025 |
| ROOFERS: PITCH,SLATE, TILE AND PRECAST CONCRETE ALL TEAR-OFF AND/OR REMOVAL (OF ANY TYPES OF ROOFING), AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL AREAS OF ANY TYPE WHERE A ROOF IS TO BE RELAID | $42.48 | $30.14 | $72.62 | ROOF0248-001 eff. 07/16/2025 |
| ROOFERS: COMPOSITION ROOFERS & DAMP WATERPROOFERS ALL TEAR-OFF AND/OR REMOVAL (OF ANY TYPES OF ROOFING), AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL AREAS OF ANY TYPE WHERE A ROOF IS TO BE RELAID | $42.48 | $30.14 | $72.62 | ROOF0248-001 eff. 07/16/2025 |
SPRINKLER FITTER A.Scope and notesPAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN THE EMPLOYMENT OF A CONTRACTOR 20 WORKING DAYS PRIOR TO ANY SUCH PAID HOLIDAYS | $64.85 | $40.76 | $105.61 | SFMA0550-003 eff. 10/01/2025 |
| SHEET METAL WORKER | $43.48 | $36.46 | $79.94 | SHEE0063-001 eff. 07/01/2025 |
TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT (DOUBLE HOOKUP) POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.82 | $37.35 | $79.17 | TEAM0379-001 eff. 06/01/2025 |
TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.53 | $37.35 | $78.88 | TEAM0379-001 eff. 06/01/2025 |
TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTORATION EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.24 | $37.35 | $78.59 | TEAM0379-001 eff. 06/01/2025 |
TRUCK DRIVERS: GROUP 4 FOUR AND FIVE AXLE EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.14 | $37.35 | $78.49 | TEAM0379-001 eff. 06/01/2025 |
TRUCK DRIVERS: GROUP 3 THREE AXLE EQUIPMENT AND TIREMAN POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.02 | $37.35 | $78.37 | TEAM0379-001 eff. 06/01/2025 |
TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.95 | $37.35 | $78.30 | TEAM0379-001 eff. 06/01/2025 |
TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUMScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.78 | $37.35 | $78.13 | TEAM0379-001 eff. 06/01/2025 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.