Michigan prevailing wage rates: MI20260090
Building construction in Livingston County.
MI20260090, modification 2, published 08/13/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 1
- changed PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIP OF BRIGHTON) base $40.30 → $45.96 (+$5.66), fringe $38.80 → $43.90 (+$5.10) New rates effective 05/04/2026 (previously 06/05/2024).
- changed PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIPS OF GREEN OAK & HAMBURG) base $51.30 → $53.15 (+$1.85), fringe $25.87 → $26.07 (+$0.20) New rates effective 06/01/2026 (previously 06/01/2025).
- changed PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION base $46.29 → $46.56 (+$0.27), fringe $25.43 → $26.23 (+$0.80) New rates effective 06/01/2026 (previously 06/01/2025).
- changed PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIP OF BRIGHTON) base $43.34 → $45.34 (+$2.00), fringe $32.92 → $37.21 (+$4.29) New rates effective 06/01/2026 (previously 06/01/2025).
- changed PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIPS OF GREEN OAK & HAMBURG) base $51.30 → $53.15 (+$1.85), fringe $25.87 → $26.07 (+$0.20) New rates effective 06/01/2026 (previously 06/01/2025).
- changed PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION base $46.29 → $46.56 (+$0.27), fringe $25.43 → $26.23 (+$0.80) New rates effective 06/01/2026 (previously 06/01/2025).
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 | $63.65 | ASBE0047-002 eff. 07/01/2025 |
| BOILERMAKER | $43.50 | $36.74 | $80.24 | BOIL0169-001 eff. 07/01/2025 |
BRICKLAYER (TOWNSHIPS OF CONWAY, HANDY, IOSCO & UNADILLA)Scope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $36.10 | $26.22 | $62.32 | BRMI0009-004 eff. 08/01/2024 |
TILE FINISHER (TOWNSHIPS OF CONWAY, HANDY, IOSCO & UNADILLA)Scope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $33.50 | $23.52 | $57.02 | BRMI0009-004 eff. 08/01/2024 |
TILE SETTER (TOWNSHIPS OF CONWAY, HANDY, IOSCO & UNADILLA)Scope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $40.53 | $23.62 | $64.15 | BRMI0009-004 eff. 08/01/2024 |
TILE FINISHER (TOWNSHIPS OF BRIGHTON, COHOCTAH, DEERFIELD, GENOA, GREEN OAK, HAMBURG, HARTLAND, HOWELL, MARION, OSCEOLA, PUTNAM & TYRONE)Scope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $33.50 | $23.52 | $57.02 | BRMI0009-020 eff. 06/01/2024 |
TILE SETTER (TOWNSHIPS OF BRIGHTON, COHOCTAH, DEERFIELD, GENOA, GREEN OAK, HAMBURG, HARTLAND, HOWELL, MARION, OSCEOLA, PUTNAM & TYRONE)Scope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $40.53 | $23.62 | $64.15 | BRMI0009-020 eff. 06/01/2024 |
BRICKLAYER (TOWNSHIPS OF BRIGHTON, COHOCTAH, DEERFIELD, GENOA, GREEN OAK, HAMBURG, HARTLAND, HOWELL, MARION, OSCEOLA, PUTNAM & TYRONE)Scope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $40.71 | $28.21 | $68.92 | BRMI0009-020 eff. 08/01/2024 |
| CARPENTER: INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING (REMAINDER OF COUNTY) | $42.44 | $31.43 | $73.87 | CARP0687-002 eff. 06/01/2025 |
| CARPENTER: INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO & MARION) | $36.21 | $21.06 | $57.27 | CARP1004-003 eff. 06/01/2025 |
| CARPENTER: FLOOR LAYER - CARPET, RESILIENT & VINYL FLOORING (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO & MARION) | $36.21 | $21.06 | $57.27 | CARP1004-006 eff. 06/01/2025 |
| CARPENTER: FLOOR LAYER - CARPET, RESILIENT, & VINYL FLOORING (REMAINDER OF COUNTY) | $36.76 | $21.11 | $57.87 | CARP1045-002 eff. 06/01/2025 |
| MILLWRIGHT | $42.92 | $39.13 | $82.05 | CARP1102-002 eff. 06/01/2025 |
| ELECTRICIAN: LOW VOLTAGE WIRING & ALARM INSTALLATION (TOWNSHIPS OF BRIGHTON, DEERFIELD, GENOA, HARTLAND, OCEOLA & TYRONE) | $36.89 | $14.16 | $51.05 | ELEC0058-003 eff. 07/02/2020 |
| ELECTRICIAN: ALARM INSTALLATION & LOW VOLTAGE WIRING (TOWNSHIPS OF GREEN OAK, HAMBURG, PUTNAM AND UNADILLA) | $38.79 | $19.87 | $58.66 | ELEC0252-002 eff. 06/01/2025 |
| ELECTRICIAN: ALARM INSTALLATION & LOW VOLTAGE WIRING (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL, IOSCO AND MARION) | $31.20 | $10.97 | $42.17 | ELEC0665-008 eff. 05/31/2022 |
ELEVATOR MECHANICScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OF 6% BASIC HOURLY RATE FOR 6 MONTHS TO 5 YEARS OF SERVICE AS VACATION PAY CREDIT | $65.45 | $38.44 | $103.89 | ELEV0085-002 eff. 01/01/2025 |
OPERATOR: POWER EQUIPMENT: GROUP 1 CRANE OPERATOR WITH MAIN BOOM AND JIB 400', 300', OR 220' OR LONGER.Scope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 | $72.53 | ENGI0324-011 eff. 06/01/2023 |
OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICKScope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.93 | $25.25 | $69.18 | ENGI0324-011 eff. 06/01/2023 |
OPERATOR: POWER EQUIPMENT: GROUP 3 BACKHOE/EXCAVATOR/TRACKHOE; BULLDOZER; CONCRETE PUMP; CRANE; GRADER/BLADE; HIGHLIFT; HOIST; LOADER; ROLLER; SCRAPER; STIFF LEG DERRICK; TRACTOR; TRENCHERScope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 | $66.53 | ENGI0324-011 eff. 06/01/2023 |
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT)Scope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | $64.82 | ENGI0324-011 eff. 06/01/2023 |
OPERATOR: POWER EQUIPMENT: GROUP 5 BOOM TRUCK (NON-SWINGING)Scope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | $64.82 | ENGI0324-011 eff. 06/01/2023 |
OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK)Scope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 | $58.96 | ENGI0324-011 eff. 06/01/2023 |
OPERATOR: POWER EQUIPMENT: GROUP 7 OILERScope and notesFOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 | $56.48 | ENGI0324-011 eff. 06/01/2023 |
| IRONWORKER: REINFORCING | $36.55 | $33.37 | $69.92 | IRON0025-019 eff. 06/01/2025 |
| IRONWORKER: STRUCTURAL | $36.55 | $35.93 | $72.48 | IRON0025-019 eff. 06/01/2025 |
| IRONWORKER STRUCTURAL (METAL BUILDING ERECTION ONLY) (EAST OF BURKHARDT ROAD) | $30.02 | $27.43 | $57.45 | IRON0025-023 eff. 04/01/2025 |
| IRONWORKER STRUCTURAL (METAL BUILDING ERECTION ONLY) (WEST OF BURKHARDT ROAD) | $30.02 | $27.43 | $57.45 | IRON0025-023 eff. 04/01/2025 |
| LABORER: ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS & CEILINGS) | $39.08 | $15.92 | $55.00 | LABO0259-002 eff. 08/01/2025 |
| LABORER: LANDSCAPE & IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER, SKIDSTEER (OR EQUIVALENT) | $29.93 | $9.10 | $39.03 | LABO0334-005 eff. 06/01/2025 |
| LABORER: LANDSCAPE & IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 | $36.81 | LABO0334-005 eff. 06/01/2025 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; SANDBLASTER (EAST OF OAK GROVE ROAD AND SOUTH OF M-59, NOT INCLUDING THE CITY OF HOWELL) | $38.11 | $15.45 | $53.56 | LABO0499-001 eff. 08/01/2025 |
| LABORER: MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE (EAST OF OAK GROVE ROAD AND SOUTH OF M-59, NOT INCLUDING THE CITY OF HOWELL) | $38.33 | $15.45 | $53.78 | LABO0499-001 eff. 08/01/2025 |
| LABORER: PIPELAYER (EAST OF OAK GROVE ROAD AND SOUTH OF M-59, NOT INCLUDING THE CITY OF HOWELL) | $38.47 | $15.45 | $53.92 | LABO0499-001 eff. 08/01/2025 |
| LABORER: GRADE CHECKER; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; PIPELAYER; SANDBLASTER (WEST OF OAK GROVE ROAD TO WEST OF PINKNEY ROAD AND DEXTER PINKNEY ROAD, INCLUDING THE CITY OF HOWELL) | $32.53 | $13.45 | $45.98 | LABO0499-010 eff. 06/01/2025 |
| LABORER: GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE; PIPELAYER; SANDBLASTER (EAST OF OAK GROVE RD. & NORTH OF M-59 (DOES NOT INCLUDE THE CITY OF HOWELL)) | $38.00 | $18.25 | $56.25 | LABO1076-001 eff. 06/01/2025 |
| PAINTER: SPRAY (EAST OF THE CITY LIMITS OF HOWELL DIRECTLY NORTH TO THE GENESSEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE:) | $26.86 | $17.66 | $44.52 | PAIN0022-001 eff. 06/01/2015 |
| PAINTER: BRUSH AND ROLLER (EAST OF THE CITY LIMITS OF HOWELL DIRECTLY NORTH TO THE GENESSEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE:) | $32.85 | $20.41 | $53.26 | PAIN0022-001 eff. 06/01/2022 |
| PAINTER: DRYWALL FINISHING/TAPING (EAST OF THE CITY LIMITS OF HOWELL DIRECTLY NORTH TO THE GENESSEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE:) | $32.85 | $20.41 | $53.26 | PAIN0022-001 eff. 06/01/2022 |
GLAZIER (EASTERN HALF INCLUDING THE CITY OF HOWELL)Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, DECORATION DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS WORKED THE LAST FULL REGULAR SCHEDULED WORK DAY PRIOR TO THE HOLIDAY, AND THE FIRST FULL REGULAR SCHEDULED WORK DAY FOLLOWING THE HOLIDAY, PROVIDED THE EMPLOYEE IS PHYSICALLY ABLE TO WORK | $42.00 | $25.55 | $67.55 | PAIN0357-001 eff. 06/01/2025 |
| GLAZIER (WESTERN HALF INCLUDING THE CITY OF HOWELL) | $37.41 | $18.99 | $56.40 | PAIN0826-003 eff. 06/01/2025 |
| PAINTER: BRUSH, ROLLER AND SPRAY (WEST OF THE EASTERN CITY LIMITS OF HOWELL, INCLUDING THE CITY OF HOWELL, NORTH TO THE GENESEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE) | $28.75 | $18.68 | $47.43 | PAIN0845-004 eff. 06/01/2025 |
| PAINTER: DRYWALL FINISHING/TAPING (WEST OF THE EASTERN CITY LIMITS OF HOWELL, INCLUDING THE CITY OF HOWELL, NORTH TO THE GENESEE COUNTY LINE AND SOUTH TO THE WASHTENAW COUNTY LINE) | $28.32 | $16.88 | $45.20 | PAIN0845-004 eff. 06/01/2025 |
| PLASTERER (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY & HOWELL) | $25.39 | $12.53 | $37.92 | PLAS0016-002 eff. 04/01/2014 |
| PLASTERER (TOWNSHIPS OF DEERFIELD, HARTLAND, OCEOLA & TYRONE) | $23.73 | $12.88 | $36.61 | PLAS0016-004 eff. 04/01/2014 |
| CEMENT MASON/CONCRETE FINISHER (TOWNSHIPS OF COHOCTAH, CONWAY, HANDY, HOWELL AND THE ENTIRE CITY OF HOWELL) | $24.64 | $12.88 | $37.52 | PLAS0016-010 eff. 04/01/2014 |
| CEMENT MASON/CONCRETE FINISHER (TOWNSHIPS OF DEERFIELD, HARTLAND, OSCEOLA AND TYRONE:) | $25.58 | $12.88 | $38.46 | PLAS0016-010 eff. 04/01/2014 |
| PLASTERER (EXCLUDING TOWNSHIPS OF COHOCTAH, CONWAY, DEERFIELD, HANDY, HARTLAND, HOWELL, OSCEOLA & TYRONE) | $30.63 | $14.07 | $44.70 | PLAS0067-003 eff. 04/01/2014 |
| CEMENT MASON/CONCRETE FINISHER (REMAINDER OF COUNTY) | $32.23 | $22.11 | $54.34 | PLAS0514-008 eff. 06/01/2023 |
| PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIP OF BRIGHTON) | $45.34 | $37.21 | $82.55 | PLUM0098-003 eff. 06/01/2026 |
| PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIPS OF GREEN OAK & HAMBURG) | $53.15 | $26.07 | $79.22 | PLUM0190-001 eff. 06/01/2026 |
| PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIPS OF GREEN OAK & HAMBURG) | $53.15 | $26.07 | $79.22 | PLUM0190-001 eff. 06/01/2026 |
PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATIONScope and notesFOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, IF THE EMPLOYEE WORKS THE WORK DAY PRECEDING AND FOLLOWING THE HOLIDAY UNLESS PROVEN ILLNESS OR INJURY PREVENTS THE EMPLOYEE FROM WORKING | $46.56 | $26.23 | $72.79 | PLUM0333-001 eff. 06/01/2026 |
PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATIONScope and notesFOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, IF THE EMPLOYEE WORKS THE WORK DAY PRECEDING AND FOLLOWING THE HOLIDAY UNLESS PROVEN ILLNESS OR INJURY PREVENTS THE EMPLOYEE FROM WORKING | $46.56 | $26.23 | $72.79 | PLUM0333-001 eff. 06/01/2026 |
| PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION (TOWNSHIP OF BRIGHTON) | $45.96 | $43.90 | $89.86 | PLUM0636-004 eff. 05/04/2026 |
| ROOFER | $42.67 | $21.62 | $64.29 | ROOF0070-001 eff. 05/08/2025 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $41.34 | $27.39 | $68.73 | SFMI0669-001 eff. 01/01/2025 |
| POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $42.74 | $21.53 | $64.27 | SHEE0007-004 eff. 05/01/2024 |
| POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D WHEN CAPPING LANDFILL) | $42.74 | $21.53 | $64.27 | SHEE0007-007 eff. 05/01/2024 |
| ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING FOR AND INSTALLATION OF ALARMS | $28.14 | $8.89 | $37.03 | SUMI2011-015 eff. 02/01/2011 |
| INSTALLER - OVERHEAD DOOR | $27.98 | $0.00 | $27.98 | SUMI2011-015 eff. 02/01/2011 |
| IRONWORKER, ORNAMENTAL | $18.48 | $7.93 | $26.41 | SUMI2011-015 eff. 02/01/2011 |
| LABORER: COMMON OR GENERAL | $17.64 | $4.95 | $22.59 | SUMI2011-015 eff. 02/01/2011 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | $13.57 EO 13658 minimum $13.65 may apply | $1.18 | $14.75 | SUMI2011-015 eff. 02/01/2011 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 2 published 08/13/2026. We format and check the official text; the determination in your contract is what applies.