Michigan prevailing wage rates: MI20260093
Building construction in Muskegon County.
MI20260093, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 | $63.65 | ASBE0047-002 eff. 07/01/2025 |
| BOILERMAKER | $43.50 | $36.74 | $80.24 | BOIL0169-001 eff. 07/01/2025 |
TILE SETTERScope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $32.20 | $23.46 | $55.66 | BRMI0009-003 eff. 08/01/2024 |
TILE FINISHERScope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $27.94 | $21.15 | $49.09 | BRMI0009-003 eff. 08/01/2024 |
BRICKLAYERScope and notesFOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR | $35.83 | $22.18 | $58.01 | BRMI0009-003 eff. 08/01/2024 |
| CARPENTER (INCLUDING FORM WORK; EXCLUDING DRYWALL HANGING) | $31.50 | $21.15 | $52.65 | CARP0100-002 eff. 06/01/2025 |
OPERATOR: POWER EQUIPMENT: GROUP 5 OILERScope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $31.23 | $25.25 | $56.48 | ENGI0324-034 eff. 06/01/2024 |
OPERATOR: POWER EQUIPMENT: GROUP 4 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK)Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $33.71 | $25.25 | $58.96 | ENGI0324-034 eff. 06/01/2024 |
OPERATOR: POWER EQUIPMENT: GROUP 3 BOOM TRUCK (NON-SWINGING)Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | $64.82 | ENGI0324-034 eff. 06/01/2024 |
OPERATOR: POWER EQUIPMENT: GROUP 2 BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT)Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $39.57 | $25.25 | $64.82 | ENGI0324-034 eff. 06/01/2024 |
OPERATOR: POWER EQUIPMENT: GROUP 1 BACKHOE/EXCAVATOR/TRACKHOE; CONCRETE PUMP; GRADER/BLADE; HIGHLIFT; HOIST; ROLLER; SCRAPER; TRENCHERScope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $41.28 | $25.25 | $66.53 | ENGI0324-034 eff. 06/01/2024 |
| IRONWORKER: STRUCTURAL | $36.55 | $29.51 | $66.06 | IRON0025-005 eff. 06/01/2025 |
| IRONWORKER: REINFORCING | $36.55 | $29.51 | $66.06 | IRON0025-005 eff. 06/01/2025 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK; SANDBLASTER | $28.56 | $12.95 | $41.51 | LABO0355-025 eff. 06/01/2024 |
| PAINTER: BRUSH AND SPRAY | $28.75 | $18.68 | $47.43 | PAIN0845-006 eff. 06/01/2025 |
| CEMENT MASON/CONCRETE FINISHER | $21.15 | $12.78 | $33.93 | PLAS0016-001 eff. 04/01/2014 |
| PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION | $47.40 | $23.35 | $70.75 | PLUM0174-002 eff. 07/01/2025 |
| PIPEFITTER (INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION) | $47.40 | $23.35 | $70.75 | PLUM0174-002 eff. 07/01/2025 |
| ROOFER | $32.65 | $14.80 | $47.45 | ROOF0070-005 eff. 06/01/2025 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION | $35.41 | $15.86 | $51.27 | SHEE0007-014 eff. 05/01/2023 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | $13.57 EO 13658 minimum $13.65 may apply | $1.18 | $14.75 | SUMI2011-018 eff. 02/01/2011 |
| TRUCK DRIVER: DUMP TRUCK | $17.00 | $5.71 | $22.71 | SUMI2011-018 eff. 02/01/2011 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $16.70 | $4.02 | $20.72 | SUMI2011-018 eff. 02/01/2011 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $19.05 | $6.51 | $25.56 | SUMI2011-018 eff. 02/01/2011 |
| PAINTER: ROLLER | $17.28 | $3.43 | $20.71 | SUMI2011-018 eff. 02/01/2011 |
| OPERATOR: LOADER | $16.38 | $3.44 | $19.82 | SUMI2011-018 eff. 02/01/2011 |
| OPERATOR: TRACTOR | $15.72 | $1.92 | $17.64 | SUMI2011-018 eff. 02/01/2011 |
| OPERATOR: CRANE | $19.13 | $7.02 | $26.15 | SUMI2011-018 eff. 02/01/2011 |
| OPERATOR: BULLDOZER | $17.56 | $4.95 | $22.51 | SUMI2011-018 eff. 02/01/2011 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $14.96 | $4.01 | $18.97 | SUMI2011-018 eff. 02/01/2011 |
| LABORER: PIPELAYER | $18.32 | $3.28 | $21.60 | SUMI2011-018 eff. 02/01/2011 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $14.82 | $3.59 | $18.41 | SUMI2011-018 eff. 02/01/2011 |
| LABORER: LANDSCAPE & IRRIGATION | $8.93 EO 13658 minimum $13.65 may apply | $1.62 | $10.55 | SUMI2011-018 eff. 02/01/2011 |
| IRONWORKER, ORNAMENTAL | $18.48 | $7.93 | $26.41 | SUMI2011-018 eff. 02/01/2011 |
| HVAC MECHANIC (LOW VOLTAGE WIRING AND INSTALLATION OF HVAC TEMPERATURE CONTROLS) | $21.32 | $8.01 | $29.33 | SUMI2011-018 eff. 02/01/2011 |
| HVAC MECHANIC (INSTALLATION OF HVAC UNIT ONLY, EXCLUDES INSTALLATION OF HVAC PIPE AND DUCT) | $18.92 | $4.71 | $23.63 | SUMI2011-018 eff. 02/01/2011 |
| ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF HVAC/TEMPERATURE CONTROLS | $22.69 | $9.10 | $31.79 | SUMI2011-018 eff. 02/01/2011 |
| CARPENTER (DRYWALL HANGING ONLY) | $17.26 | $2.69 | $19.95 | SUMI2011-018 eff. 02/01/2011 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.