MI20260131, modification 1, published 05/18/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 0

No existing rate changed amount.

0 classifications added, 1 removed or reworded
  • removed IRONWORKER: Metal Building Erection was $24.60 + $21.87 fringe

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

MI20260131 wage rates
ClassificationBaseFringeTotalRate ID
ASBESTOS WORKER/HEAT & FROST INSULATOR (TOWNSHIPS OF BLISSFIELD, CLINTON, DEERFIELD, FAIRFIELD, MACON, OGDEN, PALMYRA, RAISIN, RIDGEWAY, RIGA, & TECUMSEH)$36.00$20.15$56.15ASBE0045-003
eff. 07/01/2023
ASBESTOS WORKER/HEAT & FROST INSULATOR (TOWNSHIPS OF ADRIAN, CAMBRIDGE, DOVER, FRANKLIN, HUDSON, MADISON, MADINA, ROLLIN, ROME, SENECA, & WOODSTOCK)$36.62$19.78$56.40ASBE0047-007
eff. 07/01/2023
BOILERMAKER$43.50$37.64$81.14BOIL0085-004
eff. 01/06/2025
TILE SETTER
Scope and notes

FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR

$35.83$22.18$58.01BRMI0009-005
eff. 08/01/2024
BRICKLAYER
Scope and notes

FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER HAS BEEN EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDAY WITHIN THE CURRENT CALENDAR YEAR

$35.83$22.18$58.01BRMI0009-005
eff. 08/01/2024
CARPENTER (INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION)$35.41$21.06$56.47CARP1004-021
eff. 06/01/2025
MILLWRIGHT$42.92$39.13$82.05CARP1102-003
eff. 06/01/2025
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING)$48.40$17.79$66.19ELEC0008-004
eff. 05/25/2024
POWER EQUIPMENT OPERATOR: GROUP 9 OILER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$35.29$25.35$60.64ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT & EXTEND-A-BOOM FORKLIFT
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$43.63$25.35$68.98ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 7 BOBCAT/SKID LOADER; LOADER;PAVER; SCRAPER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$45.34$25.35$70.69ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 6 REGULAR CRANE OPERATOR
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$46.31$25.35$71.66ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 5 CRANE WITH BOOM AND JIB OR LEADS 120' OR LONGER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$47.17$25.35$72.52ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 4 CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$47.99$25.35$73.34ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 3 CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$48.29$25.35$73.64ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 2 CRANE WITH BOOM AND JIB OR LEADS 300' OR LONGER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$49.79$25.35$75.14ENGI0324-019
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 1 CRANE WITH BOOM AND JIB OR LEADS 400' OR LONGER
Scope and notes

FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM. IF THE WORKER MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL. CRANES WHERE THE OPERATOR MUST CLIMB 50 FT. OR MORE TO THE WORK STATION, $.25 PER HOUR ADDITIONAL TO THE APPLICABLE CRANE OPERATOR RATE

$51.29$25.35$76.64ENGI0324-019
eff. 06/01/2025
IRONWORKER: REINFORCING & STRUCTURAL$35.50$29.20$64.70IRON0055-004
eff. 07/01/2024
LABORER (COMMON OR GENERAL; MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE; PIPELAYER; AND SANDBLASTER)$32.35$13.45$45.80LABO0499-007
eff. 06/01/2025
PAINTER: SPRAY$26.86$17.66$44.52PAIN0022-003
eff. 06/01/2022
PAINTER: DRYWALL FINISHING/TAPING$32.85$20.41$53.26PAIN0022-003
eff. 06/01/2022
PAINTER: BRUSH AND ROLLER$32.85$20.41$53.26PAIN0022-003
eff. 06/01/2022
PLASTERER$27.41$16.10$43.51PLAS0886-007
eff. 07/01/2014
CEMENT MASON/CONCRETE FINISHER$27.18$18.11$45.29PLAS0886-007
eff. 07/01/2014
PIPEFITTER: HVAC PIPE INSTALLATION ONLY (TOWNSHIPS OF CLINTON, MACON, & TECUMSEH)$42.26$23.70$65.96PLUM0190-002
eff. 06/01/2025
PLUMBER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (TOWNSHIPS OF CLINTON, MACON, & TECUMSEH)$49.43$24.36$73.79PLUM0190-002
eff. 06/01/2025
PIPEFITTER: EXCLUDES HVAC PIPE & SYSTEM INSTALLATION (TOWNSHIPS OF CLINTON, MACON, & TECUMSEH)$51.30$25.87$77.17PLUM0190-002
eff. 06/01/2025
PLUMBER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (EXCLUDING TOWNSHIPS OF CLINTON, MACON, & TECUMSEH)$46.29$25.43$71.72PLUM0333-009
eff. 06/01/2025
PIPEFITTER: HVAC PIPE INSTALLATION ONLY (EXCLUDING TOWNSHIPS OF CLINTON, MACON, & TECUMSEH)$46.29$25.43$71.72PLUM0333-009
eff. 06/01/2025
PIPEFITTER: EXCLUDING HVAC PIPE & SYSTEM INSTALLATION (EXCLUDING TOWNSHIPS OF CLINTON, MACON, & TECUMSEH)$46.29$25.43$71.72PLUM0333-009
eff. 06/01/2025
SPRINKLER FITTER (FIRE SPRINKLERS)$41.34$27.39$68.73SFMI0669-003
eff. 01/02/2025
SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION)$30.80$21.51$52.31SHEE0033-033
eff. 07/01/2011
SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION)$30.80$21.51$52.31SHEE0033-033
eff. 07/01/2011
TRUCK DRIVER: FLATBED TRUCK$16.80$3.97$20.77SUMI2011-056
eff. 02/14/2011
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK$15.50$0.00$15.50SUMI2011-056
eff. 02/14/2011
ROOFER$15.73$7.41$23.14SUMI2011-056
eff. 02/14/2011
OPERATOR: TRACTOR$19.60$7.31$26.91SUMI2011-056
eff. 02/14/2011
OPERATOR: ROLLER$28.02$7.07$35.09SUMI2011-056
eff. 02/14/2011
OPERATOR: GRADER/BLADE$24.04$6.03$30.07SUMI2011-056
eff. 02/14/2011
OPERATOR: BULLDOZER$22.34$1.22$23.56SUMI2011-056
eff. 02/14/2011
OPERATOR: BACKHOE/EXCAVATOR$29.04$9.76$38.80SUMI2011-056
eff. 02/14/2011
LABORER: LANDSCAPE & IRRIGATION$12.84
EO 13658 minimum $13.65 may apply
$0.00$12.84SUMI2011-056
eff. 02/14/2011
GLAZIER$16.95$4.74$21.69SUMI2011-056
eff. 02/14/2011
FLOOR LAYER: CARPET$19.59$7.57$27.16SUMI2011-056
eff. 02/14/2011

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.