Missouri prevailing wage rates: MO20260056

Building construction in Crawford County.

MO20260056, modification 1, published 05/18/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 0

No base or fringe rates changed. The modification may have changed notes or other text.

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

MO20260056 wage rates
ClassificationBaseFringeTotalRate ID
BOILERMAKER$46.00$36.25$82.25BOIL0027-001
eff. 01/01/2025
BRICKLAYER$41.15$23.90$65.05BRMO0001-008
eff. 06/04/2025
TILE SETTER$34.09$19.91$54.00BRMO0018-007
eff. 07/05/2023
TILE FINISHER$28.50$18.15$46.65BRMO0018-007
eff. 07/05/2023
CARPENTER (INCLUDING DRYWALL HANGING & FORM WORK)$44.19$21.85$66.04CARP0012-001
eff. 05/01/2024
CARPENTER (FLOOR LAYING-CARPET AND VINYL ONLY)$40.08$21.85$61.93CARP1310-001
eff. 05/01/2024
ELECTRICIAN (INCLUDING LOW VOLTAGE WIRING INSTALLER; ALARM, COMPUTER & TELEPHONE INSTALLATION)$40.50$23.26$63.76ELEC0257-002
eff. 03/01/2025
ELEVATOR MECHANIC.
Scope and notes

FOOTNOTES: A) EMPLOYER CONTRIBUTES 8% OF REGULAR BASIC HOURLY RATE AS AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR LESS THAN 5 YEARS OF SERVICE B) EIGHT PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY FRIDAY AFTER THANKSGIVING DAY, VETERANS' DAY AND CHRISTM

$62.73$38.44$101.17ELEV0003-001
eff. 01/01/2025
POWER EQUIPMENT OPERATORS: ROLLER$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: PAVER$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: LOADER$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: GRADER/BLADE$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: FORKLIFT$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: CRANE$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: BOBCAT/SKID LOADER$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
POWER EQUIPMENT OPERATORS: BACKHOE/EXCAVATOR$39.06$30.38$69.44ENGI0513-005
eff. 05/01/2025
IRONWORKER, ORNAMENTAL, REINFORCING AND STRUCTURAL$41.67$31.25$72.92IRON0396-007
eff. 08/07/2024
LABORER: COMMON OR GENERAL; ASPHALT SHOVELER; PIPELAYER$30.33$15.30$45.63LABO0840-006
eff. 03/01/2025
LABORER: BRICK & CEMENT/CONCRETE MASON TENDER$32.23$15.30$47.53LABO0840-006
eff. 03/01/2025
GLAZIER$40.00$24.25$64.25PAIN0513-001
eff. 11/01/2020
PAINTER (DRYWALL FINISHING/TAPING)$34.90$17.21$52.11PAIN1185-009
eff. 04/01/2025
PAINTER (BRUSH AND ROLLER)$33.90$17.21$51.11PAIN1185-009
eff. 04/01/2025
CEMENT MASON/CONCRETE FINISHER$36.63$9.85$46.48PLAS0527-009
eff. 04/01/2023
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION)$50.60$30.13$80.73PLUM0562-008
eff. 07/01/2024
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER)$48.66$22.79$71.45PLUM0562-008
eff. 07/01/2024
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION)$50.60$30.13$80.73PLUM0562-008
eff. 07/01/2024
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION (MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER)$48.66$22.79$71.45PLUM0562-008
eff. 07/01/2024
ROOFER$40.00$22.05$62.05ROOF0002-001
eff. 03/01/2025
SPRINKLER FITTER (FIRE SPRINKLERS)$45.94$27.52$73.46SFMO0669-004
eff. 04/01/2025
SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION$52.00$27.12$79.12SHEE0036-001
eff. 08/01/2025
PAINTER: SPRAY$17.78$0.00$17.78SUMO2023-001
eff. 06/14/2010
OPERATOR: HOIST$26.02$13.01$39.03SUMO2023-001
eff. 06/14/2010

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.