PrevailCrew

New Jersey prevailing wage rates: NJ20260056

Heavy construction in Mercer County.

NJ20260056, modification 3, published 08/13/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 2

No base or fringe rates changed. The modification may have changed notes or other text.

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

NJ20260056 wage rates
ClassificationBaseFringeTotalRate ID
CEMENT MASON$49.60$37.96$87.56BRNJ0004-001
eff. 05/01/2025
CARPENTER
Scope and notes

(THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER.)

$57.42$34.17$91.59CARP0006-014
eff. 05/01/2025
MILLWRIGHT (WORK OF ERECTION AND DISMANTLING OF ELEVATORS AND TOWERS, SUCH AS CONCRETE CONVEYORS AND TEMPORARY MATERIAL ELEVATORS, SCAFFOLDING OR OTHER STRUCTURES TO BE USED AS SCAFFOLDING INSIDE OR OUTSIDE OF BUILDINGS: THE FIRST SIXTY FEET AT THE REGULAR RATE, 10% PER HOUR ADDITIONAL FOR EACH ADDITIONAL FIFTY FEET THEREAFTER.)$58.84$35.06$93.90CARP0715-007
eff. 05/01/2025
CARPENTER: DOCK BUILDER (CONCRETE FORM WORK) WORK ON LAND PILE DRIVING, FLOATING MARINE CONSTRUCTION AND THE CONSTRUCTION OF WHARVES, WHILE HANDLING AND WORKING WITH CREOSOTE AND CREOSOTE-IMPREGNATED PRODUCTS: $0.25 PER HOUR ADDITIONAL. (WORK ON HAZARDOUS/TOXIC/CONTAMINATED WASTE REMOVAL, ON A HAZARDOUS/TOXIC/CONTAMINATED WASTE SITE, WHERE THE WORKER COMES INTO CONTACT WITH HAZARDOUS/TOXIC/CONTAMINATED WASTE MATERIAL, AND WHEN A, B OR C PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED AND USED FOR RESPIRATORY, SKIN OR EYE PROTECTION: 20% PER HOUR ADDITIONAL.)$52.02$39.23$91.25CARP1556-004
eff. 05/01/2024
CARPENTER: DOCK BUILDER (ALL OTHER WORK) (WORK ON LAND PILE DRIVING, FLOATING MARINE CONSTRUCTION AND THE CONSTRUCTION OF WHARVES, WHILE HANDLING AND WORKING WITH CREOSOTE AND CREOSOTE-IMPREGNATED PRODUCTS: $0.25 PER HOUR ADDITIONAL.) WORK ON HAZARDOUS/TOXIC/CONTAMINATED WASTE REMOVAL, ON A HAZARDOUS/TOXIC/CONTAMINATED WASTE SITE, WHERE THE WORKER COMES INTO CONTACT WITH HAZARDOUS/TOXIC/CONTAMINATED WASTE MATERIAL, AND WHEN A, B OR C PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED AND USED FOR RESPIRATORY, SKIN OR EYE PROTECTION: 20% PER HOUR ADDITIONAL$52.98$52.44$105.42CARP1556-004
eff. 05/01/2024
ELECTRICIAN$63.82$41.99$105.81ELEC0269-021
eff. 01/05/2026
POWER EQUIPMENT OPERATOR: GROUP 5 OILER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$52.88$37.50$90.38ENGI0825-021
eff. 07/01/2025
POWER EQUIPMENT OPERATOR: GROUP 4 BROOM; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); ROLLER, GRADE; PUMP (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$56.59$37.50$94.09ENGI0825-021
eff. 07/01/2025
POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT SPREADER; BULLDOZER; COMPRESSOR(2 OR 3) (IN BATTERY) (WITHIN 100 FT.); CRUSHER; FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$58.22$37.50$95.72ENGI0825-021
eff. 07/01/2025
POWER EQUIPMENT OPERATOR: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); SCRAPER; SIDE BOOM (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$60.13$37.50$97.63ENGI0825-021
eff. 07/01/2025
POWER EQUIPMENT OPERATOR: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE) (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY

$61.72$37.50$99.22ENGI0825-021
eff. 07/01/2025
IRONWORKER: REINFORCING$53.24$40.40$93.64IRON0399-016
eff. 07/01/2025
IRONWORKER: STRUCTURAL, ORNAMENTAL, RIGGER$54.24$40.40$94.64IRON0399-016
eff. 07/01/2025
LABORER: MASON TENDER: CEMENT/CONCRETE$29.35$23.07$52.42LABO0077-008
eff. 07/01/2012
LABORER: PIPELAYER (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS NOT REQUIRED TO WEAR LEVEL A, B, OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED

$51.65$38.53$90.18LABO0172-007
eff. 03/01/2025
LABORER: LANDSACPE LABORER, POWER TOOL OPERATOR (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS REQUIRED TO WEAR LEVEL A, B OR C PERSONAL PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS NOT REQUIRED TO WEAR LEVEL A, B, OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE WORKER WORKS THREE DAYS FOR THE SAME EMPLOYER WITHIN A PERIOD OF TEN WORKING DAYS CONSISTING OF FIVE WORKING DAYS BEFORE AND FIVE WORKING DAYS AFTER THE DAY UPON WHICH THE HOLIDAY FALLS OR IS OBSERVED

$50.95$38.53$89.48LABO0172-007
eff. 03/01/2025
PAINTER: WORK ON BRIDGES (MAJOR BRIDGES DESIGNED FOR COMMERCIAL NAVIGATION)$58.28$33.85$92.13PAIN0711-023
eff. 05/01/2023
PAINTER: BRUSH AND ROLLER (REPAINT WORK, ON PROJECTS ON WHICH NO MAJOR ALTERATIONS OCCUR.)$29.05$18.91$47.96PAIN0711-024
eff. 05/01/2017
PAINTER: BRUSH AND ROLLER (NEW CONSTRUCTION)$40.19$22.72$62.91PAIN0711-024
eff. 05/01/2017
PLUMBER (MERCER COUNTY (SOUTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)))$59.57$46.45$106.02PLUM0009-023
eff. 07/01/2025
PLUMBER: SERVICE AND REPAIR (MERCER COUNTY (SOUTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)))$46.23$29.23$75.46PLUM0009-023
eff. 07/01/2025
PIPEFITTER (MERCER COUNTY (SOUTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)))$59.57$46.45$106.02PLUM0009-023
eff. 07/01/2025
PIPEFITTER: SERVICE AND REPAIR (MERCER COUNTY (SOUTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)))$46.23$29.23$75.46PLUM0009-023
eff. 07/01/2025
PLUMBER (MERCER COUNTY (NORTH OF A LINE DRAWN FROM THE POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)))$62.09$45.05$107.14PLUM0024-018
eff. 05/01/2025
PIPEFITTER (MERCER COUNTY (NORTH OF A LINE DRAWN FROM POINT AT WHICH RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) MEETS THE HUNTERDON/MERCER COUNTY LINE; THEN, SOUTH ALONG RT. 602 (ALSO KNOWN AS HOPEWELL - WERTSVILLE RD.) TO THE BOROUGH OF HOPEWELL, INCLUDES THE BOROUGH OF HOPEWELL; THEN, EAST ALONG THE READING RAILROAD TO THE MERCER/SOMERSET COUNTY LINE (PROVINCE LINE RD.)))$56.34$50.80$107.14PLUM0475-017
eff. 05/01/2025
LABORER: COMMON OR GENERAL$23.75$13.67$37.42SUNJ2004-032
eff. 01/02/2009
TRUCK DRIVER: DUMP TRUCK; FLATBED TRUCK; PICK UP TRUCK (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT WORKING IN A ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY. VACATION PAY CREDIT: WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS); 125 DAYS RECEIVE TWO WEEKS PAID VACATION (96 HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120 HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4 WEEKS PAID VACATION (160 HOURS)

$48.63$42.66$91.29TEAM0469-008
eff. 05/01/2025
TRUCK DRIVER: OFF THE ROAD TRUCK (HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, IN A ZONE REQUIRING LEVEL A PERSONAL PROTECTION FOR ANY WORKERS OTHER THAN THE TRUCK DRIVER: $3.00 PER HOUR ADDITIONAL. WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE WHERE THE WORKER IS NOT WORKING IN A ZONE REQUIRING LEVEL A, B OR C PERSONAL PROTECTION: $1.00 PER HOUR ADDITIONAL.)
Scope and notes

PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY. VACATION PAY CREDIT: WORKERS WORKING OR RECEIVING PAY FOR 80 DAYS WITHIN A YEAR RECEIVE ONE WEEK PAID VACATION (48 HOURS); 125 DAYS RECEIVE TWO WEEKS PAID VACATION (96 HOURS); 145 DAYS RECEIVE 15 DAYS PAID VACATION (120 HOURS); 15 YEARS SENIORITY AND 145 DAYS RECEIVE 4 WEEKS PAID VACATION (160 HOURS)

$48.78$42.66$91.44TEAM0469-008
eff. 05/01/2025

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 3 published 08/13/2026. We format and check the official text; the determination in your contract is what applies.