What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| CARPENTER (METAL STUD INSTALLATION ONLY) | $24.08 | $10.79 | $34.87 | CARP1245-004 eff. 06/01/2018 |
| ELECTRICIAN (EXCLUDING LOW VOLTAGE WIRING FOR ALARMS) | $38.00 | $9.82 | $47.82 | ELEC0583-009 eff. 01/01/2025 |
| POWER EQUIPMENT OPERATOR ((8)CRANE) | $31.43 | $4.65 | $36.08 | ENGI0953-011 eff. 01/01/2024 |
| POWER EQUIPMENT OPERATOR ((4) BOBCAT/SKID LOADER, LOADER (FRONT END)) | $27.70 | $4.65 | $32.35 | ENGI0953-011 eff. 01/01/2024 |
| IRONWORKER: ORNAMENTAL | $28.05 | $18.11 | $46.16 | IRON0495-009 eff. 01/01/2023 |
| IRONWORKER, STRUCTURAL (METAL BUILDING ERECTION ONLY) | $28.05 | $18.11 | $46.16 | IRON0495-009 eff. 01/01/2023 |
| PLUMBER (EXCLUDING HVAC PIPE INSTALLATION) | $43.07 | $16.60 | $59.67 | PLUM0412-007 eff. 01/02/2025 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION | $43.07 | $16.60 | $59.67 | PLUM0412-007 eff. 01/02/2025 |
| SHEET METAL WORKER (HVAC DUCT AND SYSTEM INSTALLATION ONLY) | $37.50 | $18.51 | $56.01 | SHEE0049-012 eff. 01/01/2024 |
| TRUCK DRIVER: WATER TRUCK | $16.25 | $5.00 | $21.25 | SUNM2010-011 eff. 11/09/2010 |
| TRUCK DRIVER: PICKUP TRUCK | $15.91 | $3.13 | $19.04 | SUNM2010-011 eff. 11/09/2010 |
| TRUCK DRIVER: DUMP TRUCK | $15.36 | $5.00 | $20.36 | SUNM2010-011 eff. 11/09/2010 |
| TILE SETTER | $19.00 | $0.00 | $19.00 | SUNM2010-011 eff. 11/09/2010 |
| TILE FINISHER | $14.02 | $0.00 | $14.02 | SUNM2010-011 eff. 11/09/2010 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $22.01 | $9.65 | $31.66 | SUNM2010-011 eff. 11/09/2010 |
| ROOFER | $13.24 EO 13658 minimum $13.65 may apply | $0.50 | $13.74 | SUNM2010-011 eff. 11/09/2010 |
| PLASTERER | $17.65 | $7.15 | $24.80 | SUNM2010-011 eff. 11/09/2010 |
| PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING | $16.58 | $1.75 | $18.33 | SUNM2010-011 eff. 11/09/2010 |
| OPERATOR: ROLLER (DIRT AND GRADE COMPACTION) | $16.80 | $4.43 | $21.23 | SUNM2010-011 eff. 11/09/2010 |
| OPERATOR: GRADER/BLADE | $21.39 | $4.94 | $26.33 | SUNM2010-011 eff. 11/09/2010 |
| OPERATOR: FORKLIFT | $21.13 | $4.83 | $25.96 | SUNM2010-011 eff. 11/09/2010 |
| OPERATOR: BACKHOE | $22.13 | $4.30 | $26.43 | SUNM2010-011 eff. 11/09/2010 |
| LABORER: PIPELAYER | $13.78 | $2.20 | $15.98 | SUNM2010-011 eff. 11/09/2010 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $11.51 EO 13658 minimum $13.65 may apply | $0.85 | $12.36 | SUNM2010-011 eff. 11/09/2010 |
| LABORER: MASON TENDER - BRICK | $13.77 | $4.35 | $18.12 | SUNM2010-011 eff. 11/09/2010 |
| LABORER: LANDSCAPE & IRRIGATION | $10.60 EO 13658 minimum $13.65 may apply | $0.24 | $10.84 | SUNM2010-011 eff. 11/09/2010 |
| LABORER: COMMON OR GENERAL | $13.12 EO 13658 minimum $13.65 may apply | $3.79 | $16.91 | SUNM2010-011 eff. 11/09/2010 |
| IRONWORKER, STRUCTURAL, EXCLUDES METAL BUILDING ERECTION | $22.20 | $8.06 | $30.26 | SUNM2010-011 eff. 11/09/2010 |
| IRONWORKER, REINFORCING | $20.84 | $7.68 | $28.52 | SUNM2010-011 eff. 11/09/2010 |
| INSULATOR - BATT | $24.44 | $8.43 | $32.87 | SUNM2010-011 eff. 11/09/2010 |
| GLAZIER | $20.15 | $3.95 | $24.10 | SUNM2010-011 eff. 11/09/2010 |
| FLOOR LAYER: CARPET | $22.31 | $0.30 | $22.61 | SUNM2010-011 eff. 11/09/2010 |
| DRYWALL FINISHER/TAPER | $19.64 | $2.75 | $22.39 | SUNM2010-011 eff. 11/09/2010 |
| CEMENT MASON/CONCRETE FINISHER | $17.72 | $3.72 | $21.44 | SUNM2010-011 eff. 11/09/2010 |
| ELECTRICIAN (Low Voltage Wiring for Alarms) | $28.25 | $6.62 | $34.87 | SUNM2010-011 eff. 11/09/2010 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, BATT INSULATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION | $20.86 | $1.30 | $22.16 | SUNM2010-011 eff. 11/09/2010 |
| CARPENTER (FORM WORK ONLY) | $19.79 | $6.14 | $25.93 | SUNM2010-011 eff. 11/09/2010 |
| CARPENTER (DRYWALL HANGING ONLY) | $21.39 | $2.85 | $24.24 | SUNM2010-011 eff. 11/09/2010 |
| CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY) | $20.79 | $0.00 | $20.79 | SUNM2010-011 eff. 11/09/2010 |
| BRICKLAYER | $20.36 | $5.74 | $26.10 | SUNM2010-011 eff. 11/09/2010 |
| BOILERMAKER | $21.77 | $3.98 | $25.75 | SUNM2010-011 eff. 11/09/2010 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.