New York prevailing wage rates: NY20260009
Heavy, Highway construction in Jefferson, Lewis, St Lawrence Counties.
NY20260009, modification 3, published 07/30/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 2
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| BOILERMAKER | $35.23 | $26.61 | $61.84 | BOIL0175-001 eff. 01/01/2021 |
CEMENT MASON/CONCRETE FINISHER A.Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY. FOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, AND THANKSGIVING DAY (PROVIDED THE EMPLOYEE IS EMPLOYED ONE DAY BEFORE AND ONE DAY AFTER THE HOLIDAY) | $37.23 | $19.51 | $56.74 | BRNY0002-012 eff. 06/01/2018 |
CARPENTERS: (HEAVY & HIGHWAY CONSTRUCTION) A.Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY | $39.52 | $27.16 | $66.68 | CARP0277-007 eff. 07/01/2025 |
| ELECTRICIAN | $43.50 | $28.38 | $71.88 | ELEC0910-005 eff. 04/01/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMANScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $31.72 | $29.87 | $61.59 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER)Scope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT)Scope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $47.57 | $31.03 | $78.60 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIANScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $52.86 | $35.60 | $88.46 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANICScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIANScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $61.56 | $36.21 | $97.77 | ELEC1249-004 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVERScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT)Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | $63.14 | $33.82 | $96.96 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | $107.51 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | $65.46 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | $35.34 | $30.12 | $65.46 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | $65.46 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | $87.18 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | $87.18 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | $87.18 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | $97.77 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | $97.77 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | $47.80 | ELEC1249-008 eff. 01/01/2025 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | $26.92 | ELEC1249-008 eff. 01/01/2025 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | $45.66 | ELEC1249-008 eff. 01/01/2025 |
ELEVATOR MECHANICScope and notesFOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $58.44 | $38.44 | $96.88 | ELEV0062-002 eff. 01/01/2025 |
| POWER EQUIPMENT OPERATOR GROUP 1 (BUILDING) | $36.84 | $23.80 | $60.64 | ENGI0158-010 eff. 07/01/2017 |
POWER EQUIPMENT OPERATOR GROUP 2 (BUILDING) "A" FRAME TRUCK, BLACKTOP PLANT (NON AUTOMATIC), ALL BACK DUMPS, BORING MACHINE, BULLDOZER, CAGEHOIST, CARRY-ALL SCRAPER, CENTRAL MIX PLANT (NON AUTOMATED), CHERRY PICKER 15 TONS AND UNDER), COMPRESSOR (500 C.F. AND OVER), CONCRETE PAVER (SINGLE DRUM OVER 16S), CONCRETE PUMP, CORE BORING MACHINE, DRILL RIGS (TRACTOR MOUNTED), ELEVATOR (AS A MATERIAL HOIST), FORK LIFT (ALL OTHERS), FRONT END LOADER (UNDER 4 C.Y.), GUNITE MACHINE, HIGH PRESSURE BOILDER 15 LBS & OVER), HOIST (ONE DRUM), HYDRAULIC BREAKING HAMMER (DROP HAMMER), KOLMAN PLANT LOADER (SCREENING GRAVEL), MAINTENANCE GREASE MAN, MIXER FOR STABILIZED BASE (SELF PROPELLED SEAMAN MIXER), MONORAIL MACHINE, PARAPET CONCRETE OR PAVEMENT GRINDER, POST HOLE DIGGER (TRUCK OR TRACTOR MOUNTED), POWER SWEEPER (WAYNE OR SIMILAR), PUMP (4" AND OVER, PUMP-CRETE OR SQEEZE-CRETE, ROAD WIDENER (FRONT END OF GRADER OR SELF PROP.), ROLLER, SELF CONTAINED HYDRAULIC BENCH DRILL, SHELL WINDER (MOTORIZED), SNORKEL (OVERHEAD ARMS), SNOWBLOWER CONTROL MAN, TRENCHING MACHINE (DIGGING CAPACITY OF 4 FT OR LESS), TUGGER HOIST, VIBROTAMP, WELL DRILL, WELL POINT SYSTEM, WINCH (MOTOR DRIVER),WINCH CAT, WINCH TRUCK (SUBMERSIBLE PUMPS WHEN USED IN LIEU OF WELL POINT SYSTEM (LEWIS AND ST LAWRENCE COUNTIES)Scope and notesPREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER .50 CRANE PREMIUMS (ADD TO GROUP 1 RATE): ALL LATTICE BOOM CRANES (65 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (100 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (80 TON CAPACITY TO 99 TON CAPACITY) GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES (65 TON CAPACITY TO 79 TON CAPACITY) GROUP 1 RATE PLUS 1.10 FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED FIVE CONSECUTIVE WORKING DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $34.78 | $23.80 | $58.58 | ENGI0158-010 eff. 07/01/2017 |
POWER EQUIPMENT OPERATOR GROUP 3 (BUILDING) COMPRESSOR (UP TO 500 C.F.), CONCRETE PAVER OR MIXER (UNDER 16S), CONCRETE PAVEMENT SPREADERS AND FINISHERS (NOT AUTOMATED), CONVEYOR (OVER 12 FT), ELECTRIC SUBMERSIBLE PUMP (4" AND OVER), FARM TRACTOR WITH OR WITHOUT ACCESSORIES, FINE GRADE MACHINE (NOT AUTOMATED), FIREMAN, FORM TAMPER, GENERATOR (2,500 WATTS AND OVER), GROUT PUMP, HYDRAULIC PUMP, MECHANICAL HEATERS (MORE THAN 2 MECHANICAL HEATERS OR ANY MECHANICAL HEATER OR HEATERS WHOSE COMBINED OUTPUT EXCEEDS 640,000 BTU PER HOUR (MANUFACTURER'S RATING) PLUS ONE CONTAINED HEATING UNIT (I.E. SUNDOG, AIR HEAT TYPE, NEW HOLLAND HAY DRYER TYPE EXCLUDED), MULCHING MACHINE, OILER, POWER DRIVEN WELDING MACHINE - 300 AMP. AND OVER (OTHER THAN ALL ELECTRIC), POWER HEATERMAN (HAY DRYER), PUMP (UNDER 4"), REVINUS WIDENER (ROAD WIDENER), SINGLE LIGHT PLANT, STEAM CLEANER OR JENNY, TRACTOR WITH OR WITHOUT TOWED ACCESSORIES (LEWIS AND ST LAWRENCE COUNTIES) PREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER .50 CRANE PREMIUMS (ADD TO GROUP 1 RATE): ALL LATTICE BOOM CRANES (65 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (100 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (80 TON CAPACITY TO 99 TON CAPACITY) GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES (65 TON CAPACITY TO 79 TON CAPACITY) GROUP 1 RATE PLUS 1.10Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED FIVE CONSECUTIVE WORKING DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $30.68 | $23.80 | $54.48 | ENGI0158-010 eff. 07/01/2017 |
POWER EQUIPMENT OPERATOR GROUP 4 (BUILDING) MASTER MECHANIC (LEWIS AND ST LAWRENCE COUNTIES)Scope and notesPREMIUMS: HAZMAT WORK 2.50 QUAD 9 BULLDOZER OR MULTIBOWL SCRAPER .50 CRANE PREMIUMS (ADD TO GROUP 1 RATE): ALL LATTICE BOOM CRANES (65 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (100 TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES (80 TON CAPACITY TO 99 TON CAPACITY) GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES (65 TON CAPACITY TO 79 TON CAPACITY) GROUP 1 RATE PLUS 1.10 FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED FIVE CONSECUTIVE WORKING DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $38.84 | $23.80 | $62.64 | ENGI0158-010 eff. 07/01/2017 |
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK , CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORK LIFT, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG , CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVELScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $55.85 | $33.40 | $89.25 | ENGI0158-020 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CATScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $54.97 | $33.40 | $88.37 | ENGI0158-020 eff. 07/01/2025 |
| POWER EQUIPMENT OPERATORS: GROUP 3 | $51.69 | $33.40 | $85.09 | ENGI0158-020 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANESScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $65.51 | $33.40 | $98.91 | ENGI0158-020 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVERScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $60.35 | $33.40 | $93.75 | ENGI0158-020 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOWScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $58.85 | $33.40 | $92.25 | ENGI0158-020 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANICScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY PROVIDED THE EMPLOYEE HAS WORKED THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $57.20 | $33.40 | $90.60 | ENGI0158-020 eff. 07/01/2025 |
| IRONWORKER, STRUCTURAL, ORNAMENTAL, REINFORCING PRECAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICKMAN, WELDER, SHEETER, SHEETER BUCKER-UP (JEFFERSON COUNTY (TOWNSHIPS OF ADAMS, ALEXANDRIA, BROWNSVILLE, CAPE VINCENT, CLAYTON, ELLISBURG, HENDERSON, HOUSFIELD, LE RAY, LORRAINE, LYME, ORLEANS, PAMELIA, RODMAN, RUTLAND, THERESA, WATERTOWN AND WORTH)) | $37.16 | $30.68 | $67.84 | IRON0060-003 eff. 07/01/2025 |
| IRONWORKER, STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVERS & RIGGER, FENCE ERECTOR, REINFORCING, STONE DERRICKMAN (LEWIS AND ST. LAWRENCE COUNTIES BUILDING/HEAVY/HIGHWAY CONSTRUCTION) | $35.50 | $31.39 | $66.89 | IRON0440-005 eff. 07/01/2025 |
| LABORERS: HEAVY & HIGHWAY GROUP 1 | $31.27 | $27.80 | $59.07 | LABO1822-004 eff. 07/01/2023 |
| LABORERS: HEAVY & HIGHWAY GROUP 2 | $31.27 | $27.80 | $59.07 | LABO1822-004 eff. 07/01/2023 |
| LABORERS: HEAVY & HIGHWAY GROUP 3 | $31.47 | $27.80 | $59.27 | LABO1822-004 eff. 07/01/2023 |
| LABORERS: HEAVY & HIGHWAY GROUP 4 | $31.67 | $27.80 | $59.47 | LABO1822-004 eff. 07/01/2023 |
| LABORERS: HEAVY & HIGHWAY GROUP 5 | $34.27 | $27.80 | $62.07 | LABO1822-004 eff. 07/01/2023 |
| PAINTER, BRIDGE BRIDGES (HEAVY & HIGHWAY CONSTRUCTION) | $42.06 | $30.59 | $72.65 | PAIN0004-022 eff. 05/01/2023 |
| PAINTER: BRUSH & ROLL, DRYWALL TAPING/FINISHING (BUILDING CONSTRUCTION) LEWIS COUNTY (TOWNSHIPS OF HIGH MARKET, LEWIS, LEYDEN, LYONSDALE, OSCEOLA, TURIN AND WEST TURIN) | $27.27 | $26.23 | $53.50 | PAIN0004-022 eff. 05/01/2024 |
| PAINTER: SPRAY/SANDBLASTING/STRUCTURAL STEEL (BUILDING CONSTRUCTION) LEWIS COUNTY (TOWNSHIPS OF HIGH MARKET, LEWIS, LEYDEN, LYONSDALE, OSCEOLA, TURIN AND WEST TURIN) | $27.77 | $26.23 | $54.00 | PAIN0004-022 eff. 05/01/2024 |
| PAINTERS: BRIDGE (JEFFERSON COUNTY; LEWIS COUNTY (TOWNSHIPS OF DIANA, CROGHAN, NEW BREMEN, WATSON, GREIG, MARTINSBURG, LWVILLE, DENMARK, HARRISBURG, MONTAGUE AND PINCKNEY); ST. LAWRENCE COUNTY) | $42.06 | $30.59 | $72.65 | PAIN0004-026 eff. 05/01/2023 |
| GLAZIER | $31.05 | $31.55 | $62.60 | PAIN0677-001 eff. 05/01/2025 |
| PLUMBER AND STEAMFITTER (JEFFERSON, LEWIS (TWPS OF DIANA, CROGHAN, NEW BREMEN, WATSON, GREIG, MARTINSBURG, LEWISVILLE, DENMARK, HARRISBURG, MONTAGUE, PINKNEY, HIGHMARKET, OSCELLIA, AND TURIN) AND ST. LAWRENCE COUNTIES) | $31.43 | $23.61 | $55.04 | PLUM0073-003 eff. 05/01/2019 |
| PLUMBER, INCLUDING STEAMFIITTING (LEWIS COUNTY TOWNSHIPS OF LEWIS, LEYDEN, LYONSDALE, WEST TURIN) | $45.93 | $33.77 | $79.70 | PLUM0112-004 eff. 05/01/2025 |
| ROOFER | $35.80 | $25.99 | $61.79 | ROOF0195-001 eff. 07/01/2025 |
| SPRINKLER FITTER | $47.85 | $28.94 | $76.79 | SFNY0669-001 eff. 01/01/2026 |
| SHEET METAL WORKER: INCL. HVAC DUCT (LEWIS AND ST. LAWRENCE COUNTIES) | $36.29 | $23.31 | $59.60 | SHEE0058-004 eff. 05/01/2025 |
| SHEET METAL WORKER: PROJECTS OVER $10 MILLION (LEWIS AND ST. LAWRENCE COUNTIES) | $46.29 | $23.31 | $69.60 | SHEE0058-004 eff. 05/01/2025 |
TRUCK DRIVERS: GROUP 1 (HEAVY & HIGHWAY) PICK-UPS, PANEL TRUCKS, FLATBOY MATERIAL TRUCKS (STRAIT JOBS), SINGLE AXLE DUMP TRUCKS, DUMPSTERS, GREASERS, TRUCK TIREMEN,, PARTS CHASER, TANDEMS AND BATCH TRUCKS, MECHANICS, SEMI TRAILER, LOWBOY TRUCKS, ASPHALT DISTRIBUTOR TRUCKS AND AGITATOR, MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES, TRUCK MECHANIC, FUEL TRUCK AND BUSScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $34.81 | $27.02 | $61.83 | TEAM0687-001 eff. 07/01/2025 |
TRUCK DRIVERS: GROUP 2 (HEAVY & HIGHWAY) SPECIAL EARTH MOVING QUIPMENT (EUCLID TYPE), OR SIMILAR OFF HIGHWAY EQUIPMENT, WHERE NOT SELF LOADED, STRADDLE (ROSS) CARRIER, AND SELF CONTAINED CONCRETE MOBILE UNIT, OFF HIGHWAY TANDEM BACK DUMP, TWIN ENGINE EQUIPMENT AND DOUBLE HITCHED EQUIPMENT WHERE NOT SELF LOADEDScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $35.03 | $27.02 | $62.05 | TEAM0687-001 eff. 07/01/2025 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 3 published 07/30/2026. We format and check the official text; the determination in your contract is what applies.