New York prevailing wage rates: NY20260045
Building, Heavy, Highway construction in Tioga County.
NY20260045, modification 2, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 1
We do not have the previous modification on file, so changes are not listed. Rate groups marked “changed” in the table were flagged by the Department of Labor in this modification.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| HAZARDOUS MATERIAL HANDLER (SCOPE OF WORK: DUTIES LIMITED TO PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING, AND DISPOSING OF ALL INSULATION MATERIALS, WHETHER THEY CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEM) | $38.50 | $25.04 | $63.54 | ASBE0030-001 eff. 05/01/2025 |
| ASBESTOS/INSULATOR WORKER (INCLUDES APPLICATION OF ALL MATERIALS, PROTECTIVE COVERINGS, COATINGS AND FINISHINGS TO ALL TYPES OF MECHANICAL SYSTEMS. ALSO THE APPLICATION OF FIRESTOPPING MATERIAL TO OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS, CURTAIN WALLS AND ALL LEAD ABATEMENT.) | $43.25 | $27.29 | $70.54 | ASBE0030-001 eff. 05/01/2025 |
| BOILERMAKER | $43.34 | $27.66 | $71.00 | BOIL0197-001 eff. 01/01/2025 |
| MARBLE MASONS, TILE LAYER, TERRAZZO WORKER: BUILDING CONSTRUCTION (CORNING CHAPTER TIOGA COUNTY (TOWNSHIPS OF BARTON, SPENCER AND PART OF NICHOLS AND TIOGA)) | $34.34 | $28.46 | $62.80 | BRNY0003-014 eff. 07/01/2025 |
| CEMENT MASONS: HEAVY & HIGHWAY CONSTRUCTION (CORNING CHAPTER TIOGA COUNTY (TOWNSHIPS OF BARTON, SPENCER AND PART OF NICHOLS AND TIOGA)) | $38.63 | $25.05 | $63.68 | BRNY0003-014 eff. 07/01/2025 |
| BRICKLAYERS, CEMENT MASONS, PLASTERERS, STONE MASONS, TILE SETTERS, TERRAZZO WORKERS, MARBLE MASONS, POINTERS, CAULKERS AND CLEANERS: BUILDING CONSTRUCTION (CORNING CHAPTER TIOGA COUNTY (TOWNSHIPS OF BARTON, SPENCER AND PART OF NICHOLS AND TIOGA)) | $34.34 | $28.46 | $62.80 | BRNY0003-014 eff. 07/01/2025 |
| CEMENT MASON/CONCRETE FINISHER: HEAVY & HIGHWAY CONSTRUCTION (BINGHAMTON CHAPTER TIOGA COUNTY (TOWNSHIPS OF BERKSHIRE, NEWARK VALLEY, OWEGO, RICHFORD, PARTS OF CANDOR, NICHOLS AND TIOGA)) | $38.63 | $25.05 | $63.68 | BRNY0003-015 eff. 07/01/2025 |
| CEMENT MASON/CONCRETE FINISHER (HEAVY & HIGHWAY CONSTRUCTION) | $38.63 | $25.05 | $63.68 | BRNY0008-003 eff. 07/01/2025 |
| BRICKLAYER (BUILDING CONSTRUCTION MARBLE, TILE AND TERRAZZO FINISHERS) | $34.44 | $20.38 | $54.82 | BRNY0008-003 eff. 07/01/2025 |
| BRICKLAYER (BUILDING CONSTRUCTION BRICKLAYERS, CEMENT MASONS, PLASTERERS, STONE MASONS, TILE SETTERS, TERRAZZO WORKERS, MARBLE MASONS, POINTERS, CAULKERS, TUCKERS) | $34.34 | $28.46 | $62.80 | BRNY0008-003 eff. 07/01/2025 |
MILLWRIGHT BUILDING CONSTRUCTIONScope and notesFOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKGIVING DAY (PROVIDED THE EMPLOYEE IS EMPLOYED (1) DAY BEFORE AND (1) DAY AFTER THE HOLIDAY | $31.69 | $21.92 | $53.61 | CARP0277-011 eff. 07/01/2025 |
CARPENTERS: (HEAVY & HIGHWAY CONSTRUCTION)Scope and notesFOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKGIVING DAY (PROVIDED THE EMPLOYEE IS EMPLOYED (1) DAY BEFORE AND (1) DAY AFTER THE HOLIDAY | $39.52 | $27.16 | $66.68 | CARP0277-011 eff. 07/01/2025 |
CARPENTER BUILDING CONSTRUCTIONScope and notesFOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKGIVING DAY (PROVIDED THE EMPLOYEE IS EMPLOYED (1) DAY BEFORE AND (1) DAY AFTER THE HOLIDAY | $31.69 | $21.92 | $53.61 | CARP0277-011 eff. 07/01/2025 |
| ELECTRICIAN (BARTON AND NICHOLS TOWNSHIPS) | $43.40 | $31.72 | $75.12 | ELEC0139-008 eff. 06/01/2025 |
| ELECTRICIAN (CANDOR AND SPENCER TOWNSHIPS) | $44.50 | $31.89 | $76.39 | ELEC0241-001 eff. 06/01/2025 |
| ELECTRICIAN (BERKSHIRE, NEWARK VALLEY, OWEGO, RICHFORD AND TIOGA TOWNSHIPS) | $42.68 | $33.06 | $75.74 | ELEC0325-004 eff. 06/01/2025 |
| CABLE SPLICER (BERKSHIRE, NEWARK VALLEY, OWEGO, RICHFORD AND TIOGA TOWNSHIPS) | $50.43 | $33.29 | $83.72 | ELEC0325-004 eff. 06/01/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS MECHANICScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS LINEMAN & TECHNICIANScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $52.86 | $35.60 | $88.46 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT)Scope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $47.57 | $31.03 | $78.60 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS GROUNDMAN (TRUCK DRIVER)Scope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $42.29 | $30.66 | $72.95 | ELEC1249-003 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONITORING SYSTEMS AND ROAD WEATHER INFORMATION SYSTEMS FLAGMANScope and notesFOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PLUS PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF THE STATE OF NEW YORK, PROVIDED THE EMPLOYEE WORKS THE DAY BEFORE OR THE DAY AFTER THE HOLIDAY | $31.72 | $29.87 | $61.59 | ELEC1249-003 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | $97.77 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | $97.77 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | $87.18 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | $87.18 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | $87.18 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | $65.46 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | $35.34 | $30.12 | $65.46 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | $65.46 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | $107.51 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | $63.14 | $33.82 | $96.96 | ELEC1249-004 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TRANSMISSION CONDUIT AND CABLE INSTALLATIONS (INCLUDING ANY AND ALL FIBER OPTIC GROUND PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES), PIPETYPE CABLE INSTALLATION AND MAINTENANCE JOBS OR PROJECTS, AND MAINTENANCE BONDING OF RAILS; PIPETYPE CABLE INSTALLATION GROUNDMAN TRUCK DRIVER (TRACTOR-TRAILER UNIT)Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVERScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $49.25 | $31.15 | $80.40 | ELEC1249-004 eff. 05/05/2025 |
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLUDING ANY AND ALL FIBER OPTIC GROUND WIRE, FIBER OPTIC SHIELD WIRE OR ANY OTHER LIKE PRODUCT BY ANY OTHER NAME MANUFACTURED FOR THE DUAL PURPOSE OF GROUND FAULT PROTECTION AND FIBER OPTIC CAPABILITIES : LINEMAN AND TECHNICIANScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRIDAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, AND ELECTION DAY FOR THE PRESIDENT OF THE UNITED STATES AND ELECTION DAY FOR THE GOVERNOR OF NEW YORK STATE, PROVIDED THE EMPLOYEE WORKS TWO DAYS BEFORE OR TWO DAYS AFTER THE HOLIDAY | $61.56 | $36.21 | $97.77 | ELEC1249-004 eff. 05/05/2025 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $38.73 | $6.93 | $45.66 | ELEC1249-008 eff. 01/01/2025 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $20.53 | $6.39 | $26.92 | ELEC1249-008 eff. 01/01/2025 |
| ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $40.81 | $6.99 | $47.80 | ELEC1249-008 eff. 01/01/2025 |
ELEVATOR MECHANICScope and notesFOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. B. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING DAY; AND CHRISTMAS DAY | $58.44 | $38.44 | $96.88 | ELEV0062-002 eff. 01/01/2025 |
POWER EQUIPMENT OPERATORS: GROUP A(1) CRANE, HYDRAULIC CRANES, TOWER CRANE, LOCOMOTIVE CRANE, PILEDRIVER, CABLEWAY, DERRICKS, WHIRLIES, DRAGLINE, BOOM TRUCKS OVER 5 TONS BUILDING HAZARDOUS WORK- ANYTIME OPERATING ENGINEERS ARE INVOLVED WITH LEVEL C OR ABOVE, $3.00 PER HOUR OVER REGULAR RATE.Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY | $51.71 | $32.80 | $84.51 | ENGI0158-007 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: BUILDING: GROUP C FORK LIFT, HIGH LIFT, LULL, OILER, FIREMAN AND HEAVY-DUTY GREASER, BOILERS AND STEAM GENERATORS, PUMP, VIBRATOR, MOTOR MIXER, AIR COMPRESSOR, DUST COLLECTOR, SELDING MACHINE, WELL POINT, MECHANICAL HEATER, GENERATORS, TEMPORARY LIGHT PLANTS, CONCRETE PUMPS, ELECTRIC SUBMERSIBLE PUMP 4" AND OVER, MURPHY TYPE DISEL GENERATOR, CONVEYOR, ELEVATORS, CONCRETE MIXER AND BELTCRETE POWER PACK (BELCRETE SYSTEM SEEDING AND MULCHING MACHINES PUMPS. HAZARDOUS WORK- ANYTIME OPERATING ENGINEERS ARE INVOLVED WITH LEVEL C OR ABOVE, $3.00 PER HOUR OVER REGULAR RATE.Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY | $46.54 | $32.80 | $79.34 | ENGI0158-007 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: BUILDING: GROUP B BACKHOES (RUBBER TIRED BACKHOE/LOADER COMBINATION), BULLDOZER, PUSHCAT, TRACTOR, TRAXCAVATOR, SCRAPER, LETOURNEAU GRADER, FORM FINE GRADER, ROAD ROLLER, BLACKTOP ROLLER, BLACKTOP SPREADER, POWER BROOMS, SWEEPERS, TRENCHING MACHINE, BARBER GREEN LOADER, SIDE BOOMS, HYDRO HAMMER, CONCRETE SPREADER, CONCRETE FINISHING MACHINE, ONE DRUM HOIST, POWER HOISTING (SINGLE DRUM), HOIST TWO DRUM OR MORE, THREE DRUM ENGINE, POWER HOISTING (TWO DRUM AND OVER), TWO DRUM AND SWINGING ENGINE, THREE DRUM SWINGING ENGINE, HOD HOIST, A-L FRAME WINCHES, CORE AND WELL DRILLERS (ONE DRUM), POST HOLE DIGGER, MODEL CHB VIBROTAMP OR SIMILAR MACHINE, BATCH BIN AND PLANT OPERATOR, DINKEY LOCOMOTIVE, SKID STEER LOADER, TRACK EXCAVATOR 5/8 CU. YD. OR SMALLER. HAZARDOUS WORK- ANYTIME OPERATING ENGINEERS ARE INVOLVED WITH LEVEL C OR ABOVE, $3.00 PER HOUR OVER REGULAR RATE.Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY | $48.85 | $32.80 | $81.65 | ENGI0158-007 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS: BUILDING: GROUP A SHOVEL, ALL EXCAVATORS (INCLUDING RUBBER TIRE, FULL SWING), GRADALLS, POWER ROAD GRADER ALL CMI EQUIPMENT, FRONT-END RUBBER TIRE LOADER, TRACTOR-MOUNTED DRILL (QUARRY MASTER), MUCKING MACHINE, CONCRETE CENTRAL MIX PLANT, CONCRETE PUMP, BELCRETE SYSTEM, AUTOMATED ASPHALT CONCRETE PLANT, TRACTOR ROAD PAVER, BOOM TRUCKS 5 TONS AND UNDER, MAINTENANCE ENGINEER, SELF CONTAINED CRAWLER DRILL-HYDRAULIC ROCK DRILL. HAZARDOUS WORK- ANYTIME OPERATING ENGINEERS ARE INVOLVED WITH LEVEL C OR ABOVE, $3.00 PER HOUR OVER REGULAR RATE.Scope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY | $49.31 | $32.80 | $82.11 | ENGI0158-007 eff. 07/01/2025 |
| POWER EQUIPMENT OPERATORS: GROUP 3 | $53.82 | $33.55 | $87.37 | ENGI0158-030 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 7 MASTER MECHANICScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $58.91 | $33.55 | $92.46 | ENGI0158-030 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 6 CRANES 49 TONS AND BELOWScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $60.30 | $33.55 | $93.85 | ENGI0158-030 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 5 CRANES 50 TONS AND OVERScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $61.80 | $33.55 | $95.35 | ENGI0158-030 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 4 TOWER CRANESScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $63.30 | $33.55 | $96.85 | ENGI0158-030 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CATScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $56.39 | $33.55 | $89.94 | ENGI0158-030 eff. 07/01/2025 |
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK , CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG , CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVELScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY | $57.30 | $33.55 | $90.85 | ENGI0158-030 eff. 07/01/2025 |
| IRONWORKER (STRUCTURAL, ORNAMENTAL, REINFORCING, PRE-CAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICKMAN, WELDER, SHEETER, SHEETER BUCKER-UP) | $37.16 | $30.68 | $67.84 | IRON0060-006 eff. 07/01/2025 |
LABORERS: HEAVY AND HIGHWAY GROUP 5: HAZARDOUS WASTE REMOVAL TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $38.76 | $25.60 | $64.36 | LABO0785-011 eff. 07/01/2024 |
LABORERS: HEAVY AND HIGHWAY GROUP 4: BLASTERS, FORM SETTERS, STONE OR GRANITE CURB SETTERS TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $36.16 | $25.60 | $61.76 | LABO0785-011 eff. 07/01/2024 |
LABORERS: HEAVY AND HIGHWAY GROUP 3: ALL ROCK OR DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE), ACETYLENE TORCH OPERATORS AND ASPHALT PAVER, POWERMAN TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $35.96 | $25.60 | $61.56 | LABO0785-011 eff. 07/01/2024 |
LABORERS: HEAVY AND HIGHWAY GROUP 2: BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACKHAMMER, MASON TENDER, MORTOR MIXER, PAVEMENT BREAKER, HANDLERS OF ALL STEEL MESH, SMALL GENERATORS FOR LABORERS' TOOLS, INSTALLATION OF BRIDGE DRAINAGE PIPE, PIPELAYERS, VIBRATOR TYPE ROLLERS, TAMPER, DRILL DOCTOR TAIL OR SCREW OPERATOR ON ASPHALT PAVER, WATER PUMP OPERATOR (1 1/2' AND SINGLE DIAPHRAM), NOZZLE (ASPHALT GUNNITE, SEEDING AND SANDBLASTING), LABORERS ON CHAIN LINK FENCE ERECTION, ROCK SPLITTER AND POWER UNIT, PUSHER TYPE CONCRETE SAW AND ALL OPERATOR (1 1/2' AND SINGLE DEAPHRAM), NOZZLER (ASPHALT GUNNITE, SEEDING AND SANDBLASTING), LABORERS ON CHAIN LINK FENCE ERECTION, OTHER GAS ELECTRIC, OIL AND AIR TOOL OPERATORS, WRECKING LABORERS TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY. | $35.76 | $25.60 | $61.36 | LABO0785-011 eff. 07/01/2024 |
LABORERS: HEAVY AND HIGHWAY GROUP 1: COMMON LABORERS, FLAGGERS TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $35.56 | $25.60 | $61.16 | LABO0785-011 eff. 07/01/2024 |
LABORERS: GROUP 3 (BUILDING) ASBESTOS ABATEMENT AND HAZARDOUS WASTE REMOVAL TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $28.50 | $22.46 | $50.96 | LABO0785-011 eff. 07/01/2024 |
LABORERS: GROUP 2 (BUILDING) MASONARY FORKLIFTS, BOB CATS, ROCK DRILLING EQUIPMENT, BLASTERS TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $28.50 | $22.46 | $50.96 | LABO0785-011 eff. 07/01/2024 |
LABORERS: GROUP 1 (BUILDING) BASIC LABORER TOWNSHIPS OF RICHFORD, BERKSHIRE, NEWARK VALLEY, OWEGO, TIOGA, BARTON AND NICHOLSScope and notesFOOTNOTE A. PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY | $26.50 | $22.46 | $48.96 | LABO0785-011 eff. 07/01/2024 |
LABORER: HEAVY & HIGHWAY: GROUP 5: HAZARDOUS WASTE REMOVAL REMAINDER OF COUNTYScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $38.76 | $25.60 | $64.36 | LABO0785-019 eff. 07/01/2024 |
LABORER: HEAVY & HIGHWAY: GROUP 4: BLASTERS; FORM SETTERS; STONE OR GRANITE CURB SETTERS REMAINDER OF COUNTYScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $35.76 | $25.60 | $61.36 | LABO0785-019 eff. 07/01/2024 |
LABORER: HEAVY & HIGHWAY: GROUP 3: ALL ROCK OR DRILL MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE); ACETYLENE TORCH OPERATOR; ASPHALT RAKER; POWDERMAN REMAINDER OF COUNTYScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $35.96 | $25.60 | $61.56 | LABO0785-019 eff. 07/01/2024 |
LABORER: HEAVY & HIGHWAY: GROUP 2: BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER; MORTAR MIXER; PAVEMENT BREAKER; HANDLERS OF ALL STEEL MESH; SMALL GENERATORS FOR LABORERS' TOOLS; INSTALLATION OF BRIDGE DRAINAGE PIPE; PIPELAYERS; VIBRATOR TYPE ROLLERS; TAMPERS; DRILL DOCTOR; TAIL OR SCREW OPERATOR ON ASPHALT PAVER; WATER PUMP OPERATOR (1-1/2" AND SINGLE DIAPHRAM); NOZZLE (ASPHALT, GUNNITE, SEEDING AND SANDBLASTING); LABORERS ON CHAIN LINK FENCE ERECTION; ROCK SPLITTER AND POWER UNIT; PUSHER TYPE CONCRETE SAW AND ALL OTHER GAS, ELECTRIC, OIL AND AIR TOOL OPERATORS; WRECKING LABORERS REMAINDER OF COUNTYScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $36.16 | $25.60 | $61.76 | LABO0785-019 eff. 07/01/2024 |
LABORER: HEAVY & HIGHWAY: GROUP 1: LABORERS; FLAGGERS; OUTBOARD AND HAND BOATS REMAINDER OF COUNTYScope and notesFOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $35.56 | $25.60 | $61.16 | LABO0785-019 eff. 07/01/2024 |
| PAINTERS: (SWING SCAFFOLD, BOATSWAIN CHAIR, SPRAY, SANDBLASTING, STEAM CLEANING, ACID AND HIGH PRESSURE WATER, PAPERHANGERS, VINYL HANGERS, POWER GRINDERS W/RESPIRATOR) | $29.10 | $23.83 | $52.93 | PAIN0004-032 eff. 05/01/2024 |
| PAINTERS: (STRUCTURAL STEEL (BUILDINGS) SPRAY WORK) | $29.10 | $23.83 | $52.93 | PAIN0004-032 eff. 05/01/2024 |
| PAINTERS: (SPRAY WORK/STEEPLE JACK (OVER 100 FT)) | $29.50 | $23.83 | $53.33 | PAIN0004-032 eff. 05/01/2024 |
| PAINTERS: (SPRAY EPOXY) | $30.00 | $23.83 | $53.83 | PAIN0004-032 eff. 05/01/2024 |
| PAINTERS: (PAINTERS AND TAPERS) | $29.93 | $23.83 | $53.76 | PAIN0004-032 eff. 05/01/2024 |
| PAINTERS: (EPOXY-BRUSH & ROLLER) | $29.60 | $23.83 | $53.43 | PAIN0004-032 eff. 05/01/2024 |
| GLAZIER | $30.00 | $31.95 | $61.95 | PAIN0677-003 eff. 05/01/2025 |
| PLUMBER, INCLUDING STEAMFITTING (TOWNSHIPS OF NEWARK VALLEY AND OWEGO) | $44.91 | $33.31 | $78.22 | PLUM0112-007 eff. 05/01/2025 |
| PLUMBER, PIPEFITTER, STEAMFITTER: INCLUDING HVAC WORK (THE TOWNS OF BARTON, BERKSHIRE, CANDOR, NICHOLS, RICHFORD, SPENCER AND TIOGA) | $35.51 | $24.57 | $60.08 | PLUM0267-005 eff. 05/01/2019 |
| ROOFER | $30.50 | $19.84 | $50.34 | ROOF0203-001 eff. 06/01/2023 |
| SPRINKLER FITTER | $47.85 | $28.94 | $76.79 | SFNY0669-001 eff. 01/01/2026 |
| SHEET METAL WORKER | $35.94 | $20.89 | $56.83 | SHEE0112-004 eff. 05/01/2023 |
TRUCK DRIVER GROUP 3 EUCLID-TYPE; OFF HIGHWAY EQUIPMENT-BACK OR DOUBLE BOTTOM DUMP TRUCKS (OVER 20 TONS); STRADDLE TRUCKS; PUSHER; ARTICULATE DUMPED TRUCKS; LOW BOY TRAILERS; SEMI TRAILERS; ASPHALT DISTRIBUTORS; FUEL TRUCKScope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $26.52 | $15.91 | $42.43 | TEAM0529-001 eff. 05/01/2025 |
TRUCK DRIVER GROUP 2 DUMP TRUCK (OVER 10 YDS); TRANSIT MIX (UNDER 5 YDS); TRANSIT MIX (OVER 5 YDS); FLAT OR STAKE BODY (TANDEM); A-FRAME/WINCH TRUCKS; DRY BATCH TRUCK; TRUCK MOUNTED SWEEPER AND VAC TRUCKS; DUMPSTER (TANDEM)Scope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $26.03 | $15.91 | $41.94 | TEAM0529-001 eff. 05/01/2025 |
TRUCK DRIVER GROUP 1 FLAT BED TRUCK (SINGLE AXLE); DUMP TRUCKS (UNDER 10 YDS SINGLE AXLE); STAKE BODY TRUCK (SINGLE AXLE); DUMPSTER (SINGLE AXLE)Scope and notesFOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE WORKS THE WORKING DAY BEFORE AND THE WORKING DAY AFTER THE HOLIDAY | $25.96 | $15.91 | $41.87 | TEAM0529-001 eff. 05/01/2025 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 2 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.