New York prevailing wage rates: NY20260074
Residential construction in Allegany County.
NY20260074, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| PLUMBER (EXCLUDES HVAC UNIT INSTALLATION) | $27.44 | $23.40 | $50.84 | PLUM0022-014 eff. 05/02/2016 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $17.41 | $2.46 | $19.87 | SUNY2013-001 eff. 03/17/2015 |
| ROOFER | $16.64 | $0.00 | $16.64 | SUNY2013-001 eff. 03/17/2015 |
| PLUMBER (HVAC UNIT INSTALLATION ONLY) | $20.91 | $0.00 | $20.91 | SUNY2013-001 eff. 03/17/2015 |
| PAINTER (BRUSH AND ROLLER), EXCLUDES DRYWALL FINISHING/TAPING | $18.47 | $0.00 | $18.47 | SUNY2013-001 eff. 03/17/2015 |
| OPERATOR: BULLDOZER | $21.72 | $0.00 | $21.72 | SUNY2013-001 eff. 03/17/2015 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $27.74 | $0.00 | $27.74 | SUNY2013-001 eff. 03/17/2015 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $21.73 | $0.00 | $21.73 | SUNY2013-001 eff. 03/17/2015 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $16.00 | $10.45 | $26.45 | SUNY2013-001 eff. 03/17/2015 |
| LABORER: COMMON OR GENERAL | $14.25 | $0.00 | $14.25 | SUNY2013-001 eff. 03/17/2015 |
| ELECTRICIAN | $17.08 | $0.00 | $17.08 | SUNY2013-001 eff. 03/17/2015 |
| DRYWALL FINISHER/TAPER | $21.51 | $0.00 | $21.51 | SUNY2013-001 eff. 03/17/2015 |
| CEMENT MASON/CONCRETE FINISHER | $22.60 | $5.75 | $28.35 | SUNY2013-001 eff. 03/17/2015 |
| CARPENTER, EXCLUDING SIDING INSTALLATION (METAL, ALUMINUM, VINYL) AND DRYWALL HANGING AND METAL STUD INSTALLATION | $20.89 | $0.00 | $20.89 | SUNY2013-001 eff. 03/17/2015 |
| CARPENTER (SIDING INSTALLATION ONLY - METAL, ALUMINUM, VINYL) | $16.35 | $0.00 | $16.35 | SUNY2013-001 eff. 03/17/2015 |
| CARPENTER (DRYWALL HANGING AND METAL STUD INSTALLATION ONLY) | $23.14 | $0.00 | $23.14 | SUNY2013-001 eff. 03/17/2015 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.