Ohio prevailing wage rates: OH20260081
Building construction in Greene County.
OH20260081, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
- changed ROOFER base $33.00 → $34.38 (+$1.38), fringe $19.42 → $19.94 (+$0.52) New rates effective 08/01/2025 (previously 08/01/2024).
0 classifications added, 3 removed or reworded
- removed OPERATOR: Backhoe/Excavator/Trackhoe was $34.84 + $14.76 fringe
- removed OPERATOR: Oiler was $27.56 + $16.37 fringe
- removed SHEET METAL WORKER, Excludes HVAC Duct and Unit Installation was $28.10 + $23.41 fringe
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $35.23 | $23.04 | $58.27 | ASBE0008-010 eff. 03/01/2025 |
| BRICKLAYER | $33.30 | $18.28 | $51.58 | BROH0018-003 eff. 06/01/2024 |
| TILE SETTER | $30.98 | $15.82 | $46.80 | BROH0022-010 eff. 07/01/2024 |
| TILE FINISHER | $28.28 | $11.05 | $39.33 | BROH0022-010 eff. 07/01/2024 |
| CARPENTER | $30.96 | $18.44 | $49.40 | CARP0002-017 eff. 06/01/2025 |
| ELECTRICIAN | $38.00 | $22.49 | $60.49 | ELEC0082-004 eff. 12/02/2024 |
ELEVATOR MECHANICScope and notesPAID HOLIDAYS: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERN'S DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE TO VACATION PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE | $57.41 | $38.44 | $95.85 | ELEV0011-002 eff. 01/01/2025 |
| POWER EQUIPMENT OPERATOR: CRANE | $44.14 | $16.41 | $60.55 | ENGI0018-034 eff. 05/01/2024 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $32.42 | $19.66 | $52.08 | ENGI0066-045 eff. 06/01/2017 |
| POWER EQUIPMENT OPERATOR: FORKLIFT | $28.87 | $19.66 | $48.53 | ENGI0066-045 eff. 06/01/2017 |
| POWER EQUIPMENT OPERATOR (MECHANIC) | $32.92 | $19.66 | $52.58 | ENGI0066-045 eff. 06/01/2017 |
| IRONWORKER: ORNAMENTAL | $37.77 | $23.90 | $61.67 | IRON0044-020 eff. 06/01/2025 |
| IRONWORKER (REINFORCING AND STRUCTURAL) | $37.39 | $25.35 | $62.74 | IRON0290-006 eff. 06/01/2025 |
| LABORER: MASON TENDER - BRICK | $27.30 | $18.75 | $46.05 | LABO0265-018 eff. 06/01/2025 |
| LABORER: COMMON OR GENERAL; ASBESTOS ABATEMENT (REMOVAL FROM CEILINGS, FLOORS, AND WALLS) | $31.65 | $12.95 | $44.60 | LABO1410-004 eff. 04/01/2024 |
| PAINTER: BRUSH AND ROLLER | $29.15 | $13.97 | $43.12 | PAIN0249-005 eff. 05/01/2025 |
| GLAZIER | $31.95 | $18.20 | $50.15 | PAIN0387-002 eff. 11/01/2023 |
| CEMENT MASON/CONCRETE FINISHER | $32.71 | $19.27 | $51.98 | PLAS0132-020 eff. 06/01/2025 |
| PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION) | $51.00 | $32.56 | $83.56 | PLUM0050-009 eff. 06/30/2025 |
| PLUMBER (INCLUDES HVAC PIPE INSTALLATION) | $43.05 | $27.18 | $70.23 | PLUM0162-009 eff. 06/01/2024 |
| ROOFER | $34.38 | $19.94 | $54.32 | ROOF0042-001 eff. 08/01/2025 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $48.28 | $28.08 | $76.36 | SFOH0669-009 eff. 04/01/2025 |
| TRUCK DRIVER: DUMP (ALL TYPES) | $22.08 | $11.51 | $33.59 | SUOH2012-083 eff. 08/29/2014 |
| SHEET METAL WORKER (HVAC DUCT AND HVAC UNIT INSTALLATION ONLY) | $26.41 | $17.34 | $43.75 | SUOH2012-083 eff. 08/29/2014 |
| PAINTER: SPRAY | $22.78 | $12.40 | $35.18 | SUOH2012-083 eff. 08/29/2014 |
| OPERATOR: ROLLER | $28.25 | $12.61 | $40.86 | SUOH2012-083 eff. 08/29/2014 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $30.28 | $13.29 | $43.57 | SUOH2012-083 eff. 08/29/2014 |
| OPERATOR: LOADER | $29.99 | $12.80 | $42.79 | SUOH2012-083 eff. 08/29/2014 |
| OPERATOR: BULLDOZER | $26.01 | $4.95 | $30.96 | SUOH2012-083 eff. 08/29/2014 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $30.26 | $12.58 | $42.84 | SUOH2012-083 eff. 08/29/2014 |
| LABORER: PIPELAYER | $23.98 | $8.58 | $32.56 | SUOH2012-083 eff. 08/29/2014 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $22.95 | $8.60 | $31.55 | SUOH2012-083 eff. 08/29/2014 |
| FORM WORKER | $22.41 | $9.01 | $31.42 | SUOH2012-083 eff. 08/29/2014 |
| DRYWALL HANGER AND METAL STUD INSTALLER | $21.02 | $4.21 | $25.23 | SUOH2012-083 eff. 08/29/2014 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.