Oklahoma prevailing wage rates: OK20260022
Highway construction in Canadian, Cleveland, Grady, Lincoln, Logan, McClain Counties.
OK20260022, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (REMAINING COUNTIES) | $13.72 | $0.00 | $13.72 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (CLEVELAND COUNTY) | $12.37 EO 13658 minimum $13.65 may apply | $0.00 | $12.37 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER: TANDEM AXLE/SEMI TRAILER (CANADIAN COUNTY) | $12.00 EO 13658 minimum $13.65 may apply | $0.00 | $12.00 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER: DUMP TRUCK (REMAINING COUNTIES) | $12.88 EO 13658 minimum $13.65 may apply | $0.00 | $12.88 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER: DUMP TRUCK (CLEVELAND COUNTY) | $12.32 EO 13658 minimum $13.65 may apply | $0.00 | $12.32 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER (WATER TRUCK) | $12.00 EO 13658 minimum $13.65 may apply | $0.00 | $12.00 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER (PICKUP TRUCK) | $12.48 EO 13658 minimum $13.65 may apply | $0.00 | $12.48 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER (OFF THE ROAD TRUCK) | $13.75 | $0.00 | $13.75 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER (LOWBOY/FLOAT) | $13.90 | $0.00 | $13.90 | SUOK2011-009 eff. 04/18/2011 |
| TRUCK DRIVER (FLATBED TRUCK) | $14.69 | $0.00 | $14.69 | SUOK2011-009 eff. 04/18/2011 |
| TRAFFIC SIGNAL INSTALLER | $17.37 | $0.00 | $17.37 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: SCRAPER (REMAINING COUNTIES) | $13.19 EO 13658 minimum $13.65 may apply | $0.00 | $13.19 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: SCRAPER (CLEVELAND COUNTY) | $13.06 EO 13658 minimum $13.65 may apply | $0.00 | $13.06 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: SCRAPER (CANADIAN COUNTY) | $12.00 EO 13658 minimum $13.65 may apply | $0.00 | $12.00 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (REMAINING COUNTIES) | $12.73 EO 13658 minimum $13.65 may apply | $0.00 | $12.73 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (MCCLAIN COUNTY) | $12.94 EO 13658 minimum $13.65 may apply | $0.00 | $12.94 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (CLEVELAND COUNTY) | $12.86 EO 13658 minimum $13.65 may apply | $0.00 | $12.86 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ROLLER (ASPHALT) (CANADIAN COUNTY) | $11.67 EO 13658 minimum $13.65 may apply | $0.00 | $11.67 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: LOADER (FRONT END) (REMAINING COUNTIES) | $12.85 EO 13658 minimum $13.65 may apply | $0.00 | $12.85 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: LOADER (FRONT END) (CLEVELAND COUNTY) | $12.76 EO 13658 minimum $13.65 may apply | $0.00 | $12.76 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE (REMAINING COUNTIES) | $14.98 | $0.00 | $14.98 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE (CLEVELAND COUNTY) | $14.46 | $0.00 | $14.46 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE (CANADIAN COUNTY) | $12.00 EO 13658 minimum $13.65 may apply | $0.00 | $12.00 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: CONCRETE SAW (REMAINING COUNTIES) | $11.70 EO 13658 minimum $13.65 may apply | $0.00 | $11.70 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: CONCRETE SAW (CLEVELAND COUNTY) | $11.64 EO 13658 minimum $13.65 may apply | $0.00 | $11.64 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: BULLDOZER (REMAINING COUNTIES) | $14.24 | $0.00 | $14.24 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: BULLDOZER (MCCLAIN COUNTY) | $13.36 EO 13658 minimum $13.65 may apply | $0.00 | $13.36 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (REMAINING COUNTIES) | $13.64 EO 13658 minimum $13.65 may apply | $0.00 | $13.64 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: BACKHOE/TRACKHOE (CLEVELAND COUNTY) | $12.91 EO 13658 minimum $13.65 may apply | $0.00 | $12.91 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ASPHALT PAVING MACHINE (REMAINING COUNTIES) | $14.08 | $0.00 | $14.08 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ASPHALT PAVING MACHINE (MCCLAIN COUNTY) | $14.04 | $0.00 | $14.04 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ASPHALT PAVING MACHINE (CLEVELAND COUNTY) | $14.57 | $0.00 | $14.57 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: ASPHALT PAVING MACHINE (CANADIAN COUNTY) | $13.32 EO 13658 minimum $13.65 may apply | $0.00 | $13.32 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (TRENCHER) | $13.63 EO 13658 minimum $13.65 may apply | $0.00 | $13.63 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (TRACTOR/BOX BLADE) | $16.50 | $0.00 | $16.50 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (STRIPING MACHINE) | $12.56 EO 13658 minimum $13.65 may apply | $0.00 | $12.56 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (ROLLER (DIRT COMPACTION)) | $12.27 EO 13658 minimum $13.65 may apply | $0.00 | $12.27 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (OILER) | $14.06 | $0.00 | $14.06 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (MIXER) | $14.43 | $0.00 | $14.43 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (MILLING MACHINE) | $14.93 | $0.00 | $14.93 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (MECHANIC) | $15.60 | $0.00 | $15.60 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (EXCAVATOR) | $15.10 | $0.00 | $15.10 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (DISTRIBUTOR TRUCK) | $13.81 | $0.00 | $13.81 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (CRANE) | $16.99 | $0.00 | $16.99 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (CONCRETE PAVING MACHINE) | $13.61 EO 13658 minimum $13.65 may apply | $0.00 | $13.61 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (BROOM) | $11.97 EO 13658 minimum $13.65 may apply | $0.00 | $11.97 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (BOBCAT/SKID LOADER) | $12.71 EO 13658 minimum $13.65 may apply | $0.00 | $12.71 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (ASPHALT PLANT) | $14.70 | $0.00 | $14.70 | SUOK2011-009 eff. 04/18/2011 |
| POWER EQUIPMENT OPERATOR: (ASPHALT PAVER SCREED) | $12.44 EO 13658 minimum $13.65 may apply | $0.00 | $12.44 | SUOK2011-009 eff. 04/18/2011 |
| LABORER, COMMON OR GENERAL (MCCLAIN COUNTY) | $10.37 EO 13658 minimum $13.65 may apply | $0.00 | $10.37 | SUOK2011-009 eff. 04/18/2011 |
| LABORER, COMMON OR GENERAL (LINCOLN COUNTY) | $10.17 EO 13658 minimum $13.65 may apply | $0.00 | $10.17 | SUOK2011-009 eff. 04/18/2011 |
| LABORER, COMMON OR GENERAL (GRADY AND LOGAN COUNTIES) | $10.55 EO 13658 minimum $13.65 may apply | $0.00 | $10.55 | SUOK2011-009 eff. 04/18/2011 |
| LABORER, COMMON OR GENERAL (CLEVELAND COUNTY) | $10.62 EO 13658 minimum $13.65 may apply | $0.00 | $10.62 | SUOK2011-009 eff. 04/18/2011 |
| LABORER, COMMON OR GENERAL (CANADIAN COUNTY) | $10.05 EO 13658 minimum $13.65 may apply | $0.00 | $10.05 | SUOK2011-009 eff. 04/18/2011 |
| LABORER (TRAFFIC CONTROL (INCLUDES FLAGGER, SETTING UP AND MOVING CONES/BARRELS)) | $11.12 EO 13658 minimum $13.65 may apply | $0.00 | $11.12 | SUOK2011-009 eff. 04/18/2011 |
| LABORER (POWER TOOL OPERATOR (INCLUDES CHIPPING GUNS AND HANDHELD CONCRETE SAWS)) | $12.89 EO 13658 minimum $13.65 may apply | $0.00 | $12.89 | SUOK2011-009 eff. 04/18/2011 |
| LABORER (PIPELAYER) | $12.50 EO 13658 minimum $13.65 may apply | $0.00 | $12.50 | SUOK2011-009 eff. 04/18/2011 |
| LABORER (LANDSCAPE) | $9.63 EO 13658 minimum $13.65 may apply | $0.00 | $9.63 | SUOK2011-009 eff. 04/18/2011 |
| LABORER (ASPHALT RAKER AND SHOVELER) | $11.31 EO 13658 minimum $13.65 may apply | $0.00 | $11.31 | SUOK2011-009 eff. 04/18/2011 |
| IRONWORKER: REINFORCING | $13.63 EO 13658 minimum $13.65 may apply | $0.00 | $13.63 | SUOK2011-009 eff. 04/18/2011 |
| IRONWORKER, STRUCTURAL | $14.21 | $0.00 | $14.21 | SUOK2011-009 eff. 04/18/2011 |
| CEMENT MASON/CONCRETE FINISHER (MCCLAIN) | $11.93 EO 13658 minimum $13.65 may apply | $0.00 | $11.93 | SUOK2011-009 eff. 04/18/2011 |
| CEMENT MASON/CONCRETE FINISHER (GRADY, LINCOLN, LOGAN) | $12.47 EO 13658 minimum $13.65 may apply | $0.00 | $12.47 | SUOK2011-009 eff. 04/18/2011 |
| CEMENT MASON/CONCRETE FINISHER (CLEVELAND) | $12.55 EO 13658 minimum $13.65 may apply | $0.00 | $12.55 | SUOK2011-009 eff. 04/18/2011 |
| CEMENT MASON/CONCRETE FINISHER (CANADIAN) | $12.44 EO 13658 minimum $13.65 may apply | $0.00 | $12.44 | SUOK2011-009 eff. 04/18/2011 |
| CARPENTER (INCLUDES FORM WORK) | $13.32 EO 13658 minimum $13.65 may apply | $0.00 | $13.32 | SUOK2011-009 eff. 04/18/2011 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.