PrevailCrew

Oregon prevailing wage rates: OR20260005

Residential construction in Douglas County.

OR20260005, modification 2, published 05/18/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 1

No base or fringe rates changed. The modification may have changed notes or other text.

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

OR20260005 wage rates
ClassificationBaseFringeTotalRate ID
ELECTRICIAN (DOUGLAS (THAT PORTION EAST OF THE COASTAL WATERSHED DIVIDE) COUNTY)$33.41$18.20$51.61ELEC0659-007
eff. 01/01/2026
ELECTRICIAN (DOUGLAS (REMAINDER OF COUNTY))$39.34$22.45$61.79ELEC0932-007
eff. 01/01/2025
POWER EQUIPMENT OPERATOR GROUP 6 LOADERS: (LESS THAN 1 CU YD.); GRADE CHECKER; ROLLER (NON-ASPHALT)$45.81$16.90$62.71ENGI0701-017
eff. 01/01/2024
POWER EQUIPMENT OPERATOR GROUP 5 ROLLER OPERATOR; BULLDOZERS: BULLDOZER OPERATOR, 20,000 LBS. OR LESS OR 100 HORSE OR LESS; HYDRAULIC HOES EXCAVATORS/TRACKHOE: HYDRAULIC BACKHOE OPERATOR, WHEEL TYPE (FORD, JOHN DEERE, CASE TYPE); HYDRAULIC BACKHOE OPERATOR TRACK TYPE UP TO AND INCLUDING 20,000 LBS.; LOADERS: LOADERS, RUBBER- TIRED TYPE, LESS THAN 25,000 LBS; CONCRETE PUMPER; CONCRETE PAVER$49.03$16.90$65.93ENGI0701-017
eff. 01/01/2024
POWER EQUIPMENT OPERATOR GROUP 4 BULLDOZERS: BULLDOZER OPERATOR OVER 20,000 LBS AND MORE THAN 100 HORSE UP TO 70,000 LBS; HYDRAULIC HOES EXCAVATOR/TRACKHOE: ROBOTIC HYDRAULIC BACKHOE OPERATOR, TRACK AND WHEEL TYPE UP TO AND INCLUDING 20,0000 LBS. WITH ANY OR ALL ATTACHMENTS; EXCAVATOR OPERATOR OVER 20,000 LBS THROUGH 80,000 LBS.; LOADERS: LOADERS OPERATOR, FRONT END AND OVERHEAD, 25,000 LBS AND LESS THAN 60,000 LBS; RUBBER-TIRED DOZERS; ASPHALT PAVER; SCREED OPERATOR; BLADE OPERATOR; RUBBER-TIRED SCRAPER, SINGLE ENGINE, SINGLE SCRAPER$50.27$16.90$67.17ENGI0701-017
eff. 01/01/2024
POWER EQUIPMENT OPERATOR GROUP 3 BULLDOZERS: BULLDOZER OPERATOR, OVER 70,000 LBS. UP TO AND INCLUDING 120,000 LBS.; HYDRAULIC HOES-EXCAVATOR: EXCAVATOR OVER 80,000 LBS. THROUGH 130,000 LBS.; LOADERS: LOADER OPERATOR 60,000 AND LESS THAN 120,000; RUBBER TIRED SCRAPER: WITH TANDOM SCRAPERS; SELF LOADING, PADDLE WHEEL, AUGER TYPE, FINISH AND/OR 2 OR MORE UNITS$53.60$16.90$70.50ENGI0701-017
eff. 01/01/2024
POWER EQUIPMENT OPERATOR GROUP 2 BULLDOZERS: BULLDOZER OPERATOR OVER 120,000 LBS AND ABOVE; BULLDOZER OPERATOR, TWIN ENGINE; BULLDOZER OPERATOR,TANDEM, QUADNINE, D10, D11, AND SIMILAR TYPE; LOADERS: LOADER OPERATOR, 120,000 LBS. AND ABOVE; HYDRAULIC HOES-EXCAVATOR: EXCAVATOR OVER 130,000 LBS; BLADE OPERATOR-ROBOTIC; RUBBER TIRED SCRAPER WITH TANDOM SCRAPERS, MULTI-ENGINE$54.75$16.90$71.65ENGI0701-017
eff. 01/01/2024
LABORERS: (MASON TENDER-CEMENT/CONCRETE)$43.79$17.05$60.84LABO0737-005
eff. 06/01/2024
LABORERS: (GENERAL LABORER)$39.00$17.30$56.30LABO0737-009
eff. 06/01/2024
CEMENT MASON/CONCRETE FINISHER$46.13$20.31$66.44PLAS0555-003
eff. 06/01/2025
ROOFER$14.41$0.00$14.41SUOR2009-003
eff. 10/16/2009
CARPENTER, EXCLUDES FORM WORK$19.99$7.78$27.77SUOR2009-003
eff. 10/16/2009
TRUCK DRIVERS: GROUP 7 DUMP TRUCKS, SIDE, END AND BOTTOM DUMPS: OVER 80 CU. YDS. AND INCLUDING 100 CU. YDS., INCLUDES ARTICULATED DUMP TRUCKS$36.82$18.30$55.12TEAM0037-008
eff. 06/01/2025
TRUCK DRIVERS: GROUP 6 DUMP TRUCKS, SIDE, END AND BOTTOM DUMPS: OVER 60 CU. YDS. AND INCLUDING 80 CU. YDS. AND INCLUDES ARTICULATED DUMP TRUCKS$36.57$18.30$54.87TEAM0037-008
eff. 06/01/2025
TRUCK DRIVERS: GROUP 5 DUMP TRUCKS, SIDE, END AND BOTTOM DUMPS: OVER 50 CU. YDS. AND INCLUDING 60 CU. YDS. AND INCLUDES ARTICULATED DUMP TRUCKS$36.35$18.30$54.65TEAM0037-008
eff. 06/01/2025
TRUCK DRIVERS: GROUP 4 DUMP TRUCKS, SIDE, END AND BOTTOM DUMPS: OVER 30 CU. YDS. AND INCLUDING 50 CU. YDS. AND INCLUDES ARTICULATED DUMP TRUCKS$36.08$18.30$54.38TEAM0037-008
eff. 06/01/2025
TRUCK DRIVERS: GROUP 3 DUMP TRUCKS, SIDE, END AND BOTTOM DUMPS: OVER 10 CU. YDS. AND INCLUDING 30 CU. YDS., INCLUDES ARTICULATED DUMP TRUCKS$35.74$18.30$54.04TEAM0037-008
eff. 06/01/2025
TRUCK DRIVERS: GROUP 2 DUMP TRCUKS/ARTICULATED DUMPS 6 CU TO 10 CU.;$35.57$18.30$53.87TEAM0037-008
eff. 06/01/2025
TRUCK DRIVERS: GROUP 1 DUMP TRUCKS, SIDE, END AND BOTTOM DUMPS: UP TO AND INCLUDING 10 CU. YDS$35.41$18.30$53.71TEAM0037-008
eff. 06/01/2025

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 2 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.