PA20260107, modification 2, published 05/18/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 1

  • changed LABORER (ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, AND CEILINGS)) base $27.97 → $27.47 (−$0.50), fringe $20.39 → $19.89 (−$0.50) DOL moved this rate group back to its 01/01/2025 rates in this modification (the previous modification listed rates effective 01/01/2026).
  • changed SPRINKLER FITTER (FIRE SPRINKLERS) base $49.75 → $49.75, fringe $30.26 → $28.96 (−$1.30) DOL moved this rate group back to its 04/01/2025 rates in this modification (the previous modification listed rates effective 01/01/2026).
0 classifications added, 1 removed or reworded
  • removed OPERATOR: Bulldozer was $37.85 + $22.72 fringe

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

PA20260107 wage rates
ClassificationBaseFringeTotalRate ID
ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) (ASBESTOS ABATEMENT, REMOVAL FROM MECHANICAL SYSTEMS ONLY)$40.00$29.81$69.81ASBE0023-007
eff. 07/01/2024
BOILERMAKER$55.00$35.48$90.48BOIL0013-008
eff. 01/01/2025
BRICKLAYER (INCLUDING POINTING, CAULKING, AND CLEANING)$33.99$16.87$50.86BRPA0005-062
eff. 05/03/2020
PILEDRIVERMAN$36.87$20.49$57.36CARP0274-004
eff. 05/01/2025
CARPENTER (INCLUDES DRYWALL HANGING, METAL STUD INSTALLATION, FORM WORK AND SCAFFOLD BUILDING; EXCLUDES ACOUSTICAL CEILING INSTALLATION)$36.84$20.19$57.03CARP0287-013
eff. 06/01/2025
MILLWRIGHT$43.00$23.44$66.44CARP0443-003
eff. 06/01/2024
ELECTRICIAN (INCLUDES ALARM INSTALLATION; COMMUNICATION TECHNICIAN, HVAC/TEMPERATURE CONTROLS INSTALLATION AND LOW VOLTAGE WIRING)$40.31$23.93$64.24ELEC0229-005
eff. 07/21/2025
ELEVATOR MECHANIC
Scope and notes

FOOTNOTES: A. EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE AS VACATION PAY CREDIT, AND 6% OF BASIC HOURLY RATE FOR LESS THAN 5 YEARS OF SERVICE. B. EIGHT PAID HOLIDAYS (PROVIDED EMPLOYEE HAS WORKED 5 CONSECUTIVE DAYS BEFORE AND THE WORKING DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING DAY, AND CHRISTMAS DAY

$58.70$38.44$97.14ELEV0059-004
eff. 01/01/2025
POWER EQUIPMENT OPERATOR (PUMP)$32.25$21.32$53.57ENGI0066-044
eff. 07/01/2024
POWER EQUIPMENT OPERATOR (MECHANIC)$36.87$21.32$58.19ENGI0066-044
eff. 07/01/2024
POWER EQUIPMENT OPERATOR: CRANE$44.89$30.92$75.81ENGI0542-043
eff. 05/01/2025
POWER EQUIPMENT OPERATOR (OILER)$39.42$29.30$68.72ENGI0542-043
eff. 05/01/2025
POWER EQUIPMENT OPERATOR (HOIST(SINGLE DRUM), FORKLIFT (UNDER 20 FT, EXCLUDES MASONRY WORK))$41.88$30.03$71.91ENGI0542-043
eff. 05/01/2025
POWER EQUIPMENT OPERATOR (BOBCAT/SKID STEER/SKID LOADER; HOIST (WITH TWO TOWERS); FORKLIFT (20 FT AND OVER, EXCLUDES MASONRY WORK))$44.61$30.83$75.44ENGI0542-043
eff. 05/01/2025
IRONWORKER, STRUCTURAL, REINFORCING AND ORNAMENTAL$37.26$32.63$69.89IRON0404-022
eff. 07/01/2024
LABORER (ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS, AND CEILINGS))$27.47$19.89$47.36LABO0373-001
eff. 01/01/2025
LABORER (JACK HAMMER; MASON TENDER-BRICK, CEMENT/CONCRETE)$26.37$17.18$43.55LABO1180-018
eff. 05/01/2022
LABORER (FORKLIFT (MASONRY WORK ONLY))$27.87$17.18$45.05LABO1180-018
eff. 05/01/2022
LABORER (COMMON OR GENERAL; CONCRETE WORKER; CONCRETE SAW (WALK BEHIND/HAND HELD))$23.01$17.18$40.19LABO1180-018
eff. 05/01/2022
PAINTER (SPRAY ONLY)$26.98$15.65$42.63PAIN0057-036
eff. 06/01/2014
PAINTER: BRUSH AND ROLLER ONLY$25.84$16.30$42.14PAIN0411-005
eff. 05/01/2021
PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION)$41.36$29.45$70.81PLUM0520-013
eff. 05/01/2023
SPRINKLER FITTER (FIRE SPRINKLERS)$49.75$28.96$78.71SFPA0669-004
eff. 04/01/2025
SHEET METAL WORKER: INCLUDES HVAC DUCT INSTALLATION:
Scope and notes

FOOTNOTE: PAID HOLIDAY: ELECTION DAY

$43.09$42.52$85.61SHEE0019-015
eff. 06/01/2024
TRUCK DRIVER: DUMP TRUCK$29.65$6.84$36.49SUPA2011-065
eff. 08/20/2014
TILE SETTER$24.87$10.14$35.01SUPA2011-065
eff. 08/20/2014
TILE FINISHER$20.65$8.24$28.89SUPA2011-065
eff. 08/20/2014
ROOFER: WATERPROOFING ONLY$28.60$18.02$46.62SUPA2011-065
eff. 08/20/2014
ROOFER, EXCLUDES WATERPROOFING$24.10$13.47$37.57SUPA2011-065
eff. 08/20/2014
PLUMBER$27.75$14.46$42.21SUPA2011-065
eff. 08/20/2014
OPERATOR: ROLLER$30.39$13.72$44.11SUPA2011-065
eff. 08/20/2014
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE)$30.39$15.05$45.44SUPA2011-065
eff. 08/20/2014
OPERATOR: LOADER$27.05$14.52$41.57SUPA2011-065
eff. 08/20/2014
OPERATOR: GRADER/BLADE$32.51$17.98$50.49SUPA2011-065
eff. 08/20/2014
OPERATOR: GRADALL$32.70$18.43$51.13SUPA2011-065
eff. 08/20/2014
OPERATOR: DRILL$25.58$17.07$42.65SUPA2011-065
eff. 08/20/2014
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$26.47$12.66$39.13SUPA2011-065
eff. 08/20/2014
LABORER: LANDSCAPE$15.01$0.00$15.01SUPA2011-065
eff. 08/20/2014
HVAC MECHANIC (INSTALLATION OF HVAC UNIT ONLY, EXCLUDES INSTALLATION OF HVAC PIPE AND DUCT)$30.80$22.58$53.38SUPA2011-065
eff. 08/20/2014
GLAZIER$20.19$6.92$27.11SUPA2011-065
eff. 08/20/2014
FLOOR LAYER: VINYL FLOORING ONLY$24.67$11.22$35.89SUPA2011-065
eff. 08/20/2014
FLOOR LAYER: HARDWOOD FLOORS ONLY$26.91$11.88$38.79SUPA2011-065
eff. 08/20/2014
FLOOR LAYER: CARPET ONLY$18.78$5.02$23.80SUPA2011-065
eff. 08/20/2014
CEMENT MASON/CONCRETE FINISHER$23.23$8.13$31.36SUPA2011-065
eff. 08/20/2014
CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY)$37.73$4.59$42.32SUPA2011-065
eff. 08/20/2014

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 2 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.