Texas prevailing wage rates: TX20260295
Highway construction in Anderson, Angelina, Bosque, Camp, Cass, Cherokee, Erath, Falls, Fannin, Franklin, Freestone, Grimes, Hamilton, Henderson, Hill, Hood, Hopkins, Houston, Jack, Jasper, Lamar, Leon, Limestone, Madison, Marion, Milam, Morris, Nacogdoches, Navarro, Newton, Palo Pinto, Panola, Polk, Rains, Red River, Sabine, San Augustine, Shelby, Somervell, Titus, Trinity, Tyler, Van Zandt, Walker, Washington, Wood Counties.
TX20260295, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| WORK ZONE BARRICADE SERVICER | $16.89 | $0.00 | $16.89 | SATX2025-009 eff. 11/15/2023 |
| TRUCK DRIVER, TANDEM AXLE TRACTOR WITH SEMI TRAILER | $20.32 | $0.00 | $20.32 | SATX2025-009 eff. 11/15/2023 |
| TRUCK DRIVER, SINGLE OR TANDEM AXLE DUMP TRUCK | $20.30 | $0.00 | $20.30 | SATX2025-009 eff. 11/15/2023 |
| TRUCK DRIVER, SINGLE AXLE | $19.22 | $0.00 | $19.22 | SATX2025-009 eff. 11/15/2023 |
| TRUCK DRIVER LOWBOY FLOAT | $23.97 | $0.00 | $23.97 | SATX2025-009 eff. 11/15/2023 |
| SPREADER BOX OPERATOR | $18.52 | $0.00 | $18.52 | SATX2025-009 eff. 11/15/2023 |
| SERVICER | $20.94 | $0.00 | $20.94 | SATX2025-009 eff. 11/15/2023 |
| SCRAPER OPERATOR | $17.71 | $0.00 | $17.71 | SATX2025-009 eff. 11/15/2023 |
| ROLLER OPERATOR, OTHER | $17.09 | $0.00 | $17.09 | SATX2025-009 eff. 11/15/2023 |
| ROLLER OPERATOR, ASPHALT | $18.34 | $0.00 | $18.34 | SATX2025-009 eff. 11/15/2023 |
| REINFORCING STEEL WORKER | $22.24 | $0.00 | $22.24 | SATX2025-009 eff. 11/15/2023 |
| RECLAIMER/PULVERIZER OPERATOR | $18.15 | $0.00 | $18.15 | SATX2025-009 eff. 11/15/2023 |
| PIPELAYER | $19.97 | $0.00 | $19.97 | SATX2025-009 eff. 11/15/2023 |
| PAVEMENT MARKING MACHINE OPERATOR | $22.96 | $0.00 | $22.96 | SATX2025-009 eff. 11/15/2023 |
| OFF ROAD HAULER | $16.90 | $0.00 | $16.90 | SATX2025-009 eff. 11/15/2023 |
| MOTOR GRADER OPERATOR, ROUGH | $21.43 | $0.00 | $21.43 | SATX2025-009 eff. 11/15/2023 |
| MOTOR GRADER OPERATOR, FINE GRADE | $24.43 | $0.00 | $24.43 | SATX2025-009 eff. 11/15/2023 |
| MILLING MACHINE OPERATOR | $19.99 | $0.00 | $19.99 | SATX2025-009 eff. 11/15/2023 |
| MECHANIC | $24.13 | $0.00 | $24.13 | SATX2025-009 eff. 11/15/2023 |
| LOADER/BACKHOE OPERATOR | $20.42 | $0.00 | $20.42 | SATX2025-009 eff. 11/15/2023 |
| LABORER, UTILITY | $18.80 | $0.00 | $18.80 | SATX2025-009 eff. 11/15/2023 |
| LABORER, COMMON | $16.72 | $0.00 | $16.72 | SATX2025-009 eff. 11/15/2023 |
| FRONT END LOADER OPERATOR, OVER 3 CY | $19.55 | $0.00 | $19.55 | SATX2025-009 eff. 11/15/2023 |
| FRONT END LOADER OPERATOR, 3 CY OR LESS | $18.58 | $0.00 | $18.58 | SATX2025-009 eff. 11/15/2023 |
| FOUNDATION DRILL OPERATOR, TRUCK MOUNTED | $25.95 | $0.00 | $25.95 | SATX2025-009 eff. 11/15/2023 |
| FORM SETTER, PAVING & CURB | $18.25 | $0.00 | $18.25 | SATX2025-009 eff. 11/15/2023 |
| FORM BUILDER/SETTER, STRUCTURES | $20.05 | $0.00 | $20.05 | SATX2025-009 eff. 11/15/2023 |
| FLAGGER | $13.99 | $0.00 | $13.99 | SATX2025-009 eff. 11/15/2023 |
| EXCAVATOR OPERATOR, OVER 50,000 POUNDS | $22.80 | $0.00 | $22.80 | SATX2025-009 eff. 11/15/2023 |
| EXCAVATOR OPERATOR, 50,000 POUNDS OR LESS | $21.05 | $0.00 | $21.05 | SATX2025-009 eff. 11/15/2023 |
| ELECTRICIAN | $32.38 | $0.00 | $32.38 | SATX2025-009 eff. 11/15/2023 |
| CRAWLER TRACTOR OPERATOR | $19.82 | $0.00 | $19.82 | SATX2025-009 eff. 11/15/2023 |
| CRANE OPERATOR, LATTICE BOOM OVER 80 TONS | $23.75 | $0.00 | $23.75 | SATX2025-009 eff. 11/15/2023 |
| CRANE OPERATOR, LATTICE BOOM 80 TONS OR LESS | $24.33 | $0.00 | $24.33 | SATX2025-009 eff. 11/15/2023 |
| CRANE OPERATOR, HYDRAULIC 80 TONS OR LESS | $27.22 | $0.00 | $27.22 | SATX2025-009 eff. 11/15/2023 |
| CONCRETE SAW OPERATOR | $25.50 | $0.00 | $25.50 | SATX2025-009 eff. 11/15/2023 |
| CONCRETE PAVING, CURING, FLOAT, TEXTURING MACHINE OPERATOR | $23.12 | $0.00 | $23.12 | SATX2025-009 eff. 11/15/2023 |
| CONCRETE PAVEMENT FINISHING MACHINE OPERATOR | $23.11 | $0.00 | $23.11 | SATX2025-009 eff. 11/15/2023 |
| CONCRETE FINISHER, PAVING AND STRUCTURES | $20.66 | $0.00 | $20.66 | SATX2025-009 eff. 11/15/2023 |
| BROOM OR SWEEPER OPERATOR | $17.58 | $0.00 | $17.58 | SATX2025-009 eff. 11/15/2023 |
| ASPHALT RAKER | $19.53 | $0.00 | $19.53 | SATX2025-009 eff. 11/15/2023 |
| ASPHALT PAVING MACHINE OPERATOR | $21.26 | $0.00 | $21.26 | SATX2025-009 eff. 11/15/2023 |
| ASPHALT DISTRIBUTOR OPERATOR | $22.69 | $0.00 | $22.69 | SATX2025-009 eff. 11/15/2023 |
| AGRICULTURAL TRACTOR OPERATOR | $19.97 | $0.00 | $19.97 | SATX2025-009 eff. 11/15/2023 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.