PrevailCrew

Utah prevailing wage rates: UT20260019

Heavy construction in Iron County.

UT20260019, modification 2, published 05/20/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 1

No existing rate changed amount.

2 classifications added, 2 removed or reworded
  • added TRUCK DRIVER: GROUP 1- ARTICULATD END DUMP, LOW BOY, ROLLAGON OR SIMILAR TYPE EQUIPMENT, TRUCK MECHANIC. (NATURAL GAS PIPELINE CONSTRUCTION ONLY) $46.65 + $15.75 fringe
  • added TRUCK DRIVER: GROUP 2- A-FRAME, CHALLENGE (FOR TRANSPORTATION PURPOSES), FORKLIFT, FUEL TRUCK, GIN POLE, RUBBER-TIRED TRACTOR, TANDEM FLOAT (4 & 5 AXLE), TRACK TRUCK/ALL-TRACK DUMPER EQUIPMENT, VACUUM TRUCK, WINCH TRUCK. (NATURAL GAS PIPELINE CONSTRUCTION ONLY) $46.02 + $15.75 fringe
  • removed TRUCK DRIVER: NATURAL GAS PIPELINE CONSTRUCTION ONLY: GROUP 1 LOW BOY AND TRUCK MECHANIC: was $46.65 + $15.75 fringe
  • removed TRUCK DRIVER: NATURAL GAS PIPELINE CONSTRUCTION ONLY: GROUP 2 STRINGER TRUCK was $46.02 + $15.75 fringe

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

UT20260019 wage rates
ClassificationBaseFringeTotalRate ID
OPERATOR: POWER EQUIPMENT (3) BACKHOE/EXCAVATOR. (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION)$30.78$16.09$46.87ENGI0003-046
eff. 07/01/2020
OPERATOR: POWER EQUIPMENT OILER (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$22.03$11.88$33.91ENGI0003-054
eff. 07/01/2013
OPERATOR: POWER EQUIPMENT BACKHOE/EXCAVATOR/TRACKHOE, BLADE/GRADER, BOOM, BULLDOZER, CRANE, MECHANIC, TRENCHER: (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$35.68$17.57$53.25ENGI0003-054
eff. 07/01/2013
LABORER: SANDBLASTER (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$20.85$8.65$29.50LABO0295-018
eff. 07/01/2014
LABORER: POWDERMAN (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$21.65$8.65$30.30LABO0295-018
eff. 07/01/2014
LABORER: FORMWORKER (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$20.85$8.65$29.50LABO0295-018
eff. 07/01/2014
LABORER: COMMON OR GENERAL, NAIL GUN, PIPELAYER, POT TENDER (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$20.59$8.65$29.24LABO0295-018
eff. 07/01/2014
LABORER: CHAIN SAW AND POWER DRILL (NATURAL GAS PIPELINE CONSTRUCTION ONLY)$20.85$8.65$29.50LABO0295-018
eff. 07/01/2014
TRUCK DRIVER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION)$12.00
EO 13658 minimum $13.65 may apply
$0.00$12.00SUUT2008-025
eff. 08/19/2008
OPERATOR: TRACKHOE (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION)$13.63
EO 13658 minimum $13.65 may apply
$0.00$13.63SUUT2008-025
eff. 08/19/2008
OPERATOR: ROLLER (DIRT AND GRADE COMPACTION)$10.89
EO 13658 minimum $13.65 may apply
$0.00$10.89SUUT2008-025
eff. 08/19/2008
OPERATOR: LOADER (FRONT END)$11.38
EO 13658 minimum $13.65 may apply
$0.00$11.38SUUT2008-025
eff. 08/19/2008
OPERATOR: GRADER/BLADE, EXCLUDES NATURAL GAS PIPELINE CONSTRUCTION$13.61
EO 13658 minimum $13.65 may apply
$0.00$13.61SUUT2008-025
eff. 08/19/2008
LABORER: PIPELAYER (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION)$9.00
EO 13658 minimum $13.65 may apply
$0.00$9.00SUUT2008-025
eff. 08/19/2008
LABORER: COMMON OR GENERAL (EXCLUDING NATURAL GAS PIPELINE CONSTRUCTION)$9.00
EO 13658 minimum $13.65 may apply
$0.00$9.00SUUT2008-025
eff. 08/19/2008
LABORER: MASON TENDER - CEMENT/CONCRETE$9.00
EO 13658 minimum $13.65 may apply
$0.36$9.36SUUT2008-025
eff. 08/19/2008
CEMENT MASON/CONCRETE FINISHER$14.00$0.56$14.56SUUT2008-025
eff. 08/19/2008
CARPENTER, INCLUDES FORM WORK (EXCLUDES NATURAL GAS PIPELINE CONSTRUCTION FORM WORK)$14.75$3.03$17.78SUUT2008-025
eff. 08/19/2008
TRUCK DRIVER: GROUP 2- A-FRAME, CHALLENGE (FOR TRANSPORTATION PURPOSES), FORKLIFT, FUEL TRUCK, GIN POLE, RUBBER-TIRED TRACTOR, TANDEM FLOAT (4 & 5 AXLE), TRACK TRUCK/ALL-TRACK DUMPER EQUIPMENT, VACUUM TRUCK, WINCH TRUCK. (NATURAL GAS PIPELINE CONSTRUCTION ONLY)
Scope and notes

PREMIUM PAY: ADD $2.25 TO THE ABOVE RATE FOR THE FOLLOWING CLASSIFICATIONS: STRINGER TRUCK

$46.02$15.75$61.77TEAM0222-020
eff. 07/01/2025
TRUCK DRIVER: GROUP 1- ARTICULATD END DUMP, LOW BOY, ROLLAGON OR SIMILAR TYPE EQUIPMENT, TRUCK MECHANIC. (NATURAL GAS PIPELINE CONSTRUCTION ONLY)
Scope and notes

PREMIUM PAY: ADD $2.25 TO THE ABOVE RATE FOR THE FOLLOWING CLASSIFICATIONS: LOW BOY AND TRUCK MECHANIC

$46.65$15.75$62.40TEAM0222-020
eff. 07/01/2025
TRUCK DRIVER: GROUP 3- AMBULANCE , BUS, DUMP TRUCK (2 AND 3 AXLE), FLATBED TRUCK (2 AND 3 AXLE), GREASE TRUCK, HOT PASS TRUCK (3 AXLE), JEEP, PICK-UP, SINGLE AXLE FLOAT (3 AXLE), SKID TRUCK (2 AND 3 AXLE), STATION WAGON, STRINGER BEAD & HOT PASS (2 AXLE), SWAMP BUGGY/ MARSH BUGGY, OR SIMILAR TYPE EQUIPMENT, TEAM DRIVER, WATER TRUCK (2 AND 3 AXLE) (NATURAL GAS PIPELINE CONSTRUCTION ONLY)
Scope and notes

PREMIUM PAY: ADD $2.25 TO THE ABOVE RATE FOR THE FOLLOWING CLASSIFICATIONS

$41.90$15.75$57.65TEAM0222-020
eff. 07/01/2025

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 2 published 05/20/2026. We format and check the official text; the determination in your contract is what applies.