What changed since modification 0

No base or fringe rates changed. The modification may have changed notes or other text.

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

UT20260089 wage rates
ClassificationBaseFringeTotalRate ID
CARPENTER (DRYWALL HANGING AND METAL STUD INSTALLATION ONLY)$31.66$13.97$45.63CARP0801-002
eff. 12/01/2022
ELECTRICIAN$41.23$17.66$58.89ELEC0354-001
eff. 06/11/2025
ELECTRICIAN (LOW VOLTAGE WIRING ONLY)$31.86$15.83$47.69ELEC0354-001
eff. 06/11/2025
DRYWALL FINISHER/TAPER$26.00$8.78$34.78PAIN0077-003
eff. 07/01/2025
PLUMBER/PIPEFITTER$46.10$15.83$61.93PLUM0140-001
eff. 08/01/2025
SPRINKLER FITTER (FIRE SPRINKLERS)$42.17$26.63$68.80SFUT0669-003
eff. 01/01/2025
SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION)$46.79$14.89$61.68SHEE0312-002
eff. 07/01/2025
TRUCK DRIVER: DUMP TRUCK$17.74$2.66$20.40SUUT2012-021
eff. 07/29/2014
TILE SETTER$23.00$0.00$23.00SUUT2012-021
eff. 07/29/2014
TILE FINISHER$13.54
EO 13658 minimum $13.65 may apply
$0.00$13.54SUUT2012-021
eff. 07/29/2014
ROOFER$15.62$0.00$15.62SUUT2012-021
eff. 07/29/2014
PAINTER (BRUSH, ROLLER AND SPRAY, EXCLUDING DRYWALLING/TAPING)$15.33$0.00$15.33SUUT2012-021
eff. 07/29/2014
OPERATOR: LOADER$19.34$0.00$19.34SUUT2012-021
eff. 07/29/2014
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE$16.92$0.00$16.92SUUT2012-021
eff. 07/29/2014
LABORER: PIPELAYER$13.57
EO 13658 minimum $13.65 may apply
$0.00$13.57SUUT2012-021
eff. 07/29/2014
LABORER: MASON TENDER - CEMENT/CONCRETE$13.87$0.14$14.01SUUT2012-021
eff. 07/29/2014
LABORER: MASON TENDER - BRICK$16.38$1.00$17.38SUUT2012-021
eff. 07/29/2014
LABORER: IRRIGATION$9.50
EO 13658 minimum $13.65 may apply
$0.00$9.50SUUT2012-021
eff. 07/29/2014
LABORER: COMMON OR GENERAL$12.78
EO 13658 minimum $13.65 may apply
$0.00$12.78SUUT2012-021
eff. 07/29/2014
IRONWORKER, STRUCTURAL$20.21$3.22$23.43SUUT2012-021
eff. 07/29/2014
INSULATOR - MECHANICAL (DUCT, PIPE & MECHANICAL SYSTEM INSULATION)$17.76$1.83$19.59SUUT2012-021
eff. 07/29/2014
CEMENT MASON/CONCRETE FINISHER$16.00$0.00$16.00SUUT2012-021
eff. 07/29/2014
CARPENTER (EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, AND METAL STUD INSTALLATION)$20.68$5.49$26.17SUUT2012-021
eff. 07/29/2014
CARPENTER (ACOUSTICAL CEILING INSTALLATION ONLY)$21.00$3.20$24.20SUUT2012-021
eff. 07/29/2014
BRICKLAYER$22.13$1.67$23.80SUUT2012-021
eff. 07/29/2014

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.