Virginia prevailing wage rates: VA20260112
Highway construction in Clarke County.
VA20260112, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| ELECTRICIAN, INCLUDES TRAFFIC SIGNALIZATION | $36.85 | $14.13 | $50.98 | ELEC0080-011 eff. 06/01/2025 |
| CEMENT MASON/CONCRETE FINISHER | $20.70 | $8.03 | $28.73 | PLAS0891-011 eff. 06/01/2020 |
| TRUCK DRIVER: SINGLE & MULTI AXLE | $18.84 | $0.00 | $18.84 | SUVA2016-048 eff. 07/02/2018 |
| TRUCK DRIVER: HEAVY OVER 7 CY | $18.05 | $0.00 | $18.05 | SUVA2016-048 eff. 07/02/2018 |
| TRUCK DRIVER: FUEL AND LUBRICANT SERVICE | $18.25 | $0.00 | $18.25 | SUVA2016-048 eff. 07/02/2018 |
| TRUCK DRIVER : HEAVY 7CY & UNDER | $15.53 | $0.00 | $15.53 | SUVA2016-048 eff. 07/02/2018 |
| TRAFFIC CONTROL: FLAGGER | $13.64 EO 13658 minimum $13.65 may apply | $0.00 | $13.64 | SUVA2016-048 eff. 07/02/2018 |
| PAVEMENT MARKING TRUCK DRIVER | $18.78 | $0.00 | $18.78 | SUVA2016-048 eff. 07/02/2018 |
| PAVEMENT MARKING OPERATOR | $22.15 | $0.00 | $22.15 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: BULLDOZER, INCLUDING UTILITY | $20.64 | $0.00 | $20.64 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: ASPHALT SPREADER AND DISTRIBUTOR | $20.58 | $2.31 | $22.89 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: SCREED | $22.13 | $4.89 | $27.02 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: ROLLER (FINISHING) | $18.73 | $3.23 | $21.96 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: ROLLER | $18.92 | $0.00 | $18.92 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: PILEDRIVER | $21.83 | $4.08 | $25.91 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $20.33 | $2.81 | $23.14 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: PAVEMENT PLANER GROUNDSMEN | $19.75 | $0.00 | $19.75 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: PAVEMENT PLANER | $21.14 | $0.00 | $21.14 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: MILLING MACHINE | $23.19 | $2.94 | $26.13 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: MECHANIC | $22.84 | $0.00 | $22.84 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: LOADER | $18.92 | $0.00 | $18.92 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: HYDROSEEDER | $16.64 | $0.00 | $16.64 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: GRADER/BLADE | $23.21 | $0.00 | $23.21 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: GRADALL | $19.26 | $0.00 | $19.26 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: DRILL | $24.89 | $0.00 | $24.89 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: CRANE | $29.46 | $0.00 | $29.46 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: BROOM/SWEEPER | $17.40 | $2.01 | $19.41 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $19.00 | $3.49 | $22.49 | SUVA2016-048 eff. 07/02/2018 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $23.93 | $0.00 | $23.93 | SUVA2016-048 eff. 07/02/2018 |
| LABORER: POWER TOOL OPERATOR | $15.69 | $0.00 | $15.69 | SUVA2016-048 eff. 07/02/2018 |
| LABORER: PIPELAYER | $20.48 | $0.00 | $20.48 | SUVA2016-048 eff. 07/02/2018 |
| LABORER: GRADE CHECKER | $14.88 | $0.00 | $14.88 | SUVA2016-048 eff. 07/02/2018 |
| LABORER: COMMON OR GENERAL | $16.27 | $0.00 | $16.27 | SUVA2016-048 eff. 07/02/2018 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $19.05 | $1.75 | $20.80 | SUVA2016-048 eff. 07/02/2018 |
| IRONWORKER, STRUCTURAL | $34.18 | $0.00 | $34.18 | SUVA2016-048 eff. 07/02/2018 |
| IRONWORKER, REINFORCING | $34.18 | $0.00 | $34.18 | SUVA2016-048 eff. 07/02/2018 |
| FENCE ERECTOR | $15.28 | $0.00 | $15.28 | SUVA2016-048 eff. 07/02/2018 |
| CARPENTER, INCLUDES FORM WORK | $20.97 | $0.00 | $20.97 | SUVA2016-048 eff. 07/02/2018 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.