Washington prevailing wage rates: WA20260119
Building construction in Yakima County.
WA20260119, modification 1, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 0
No existing rate changed amount.
0 classifications added, 4 removed or reworded
- removed LABORER: Grade Checker was $45.01 + $18.51 fringe
- removed OPERATOR: Concrete Pump was $52.92 + $22.63 fringe
- removed OPERATOR: Crane was $53.35 + $17.57 fringe
- removed OPERATOR: Drill was $56.42 + $21.15 fringe
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| HEAT & FROST INSULATOR (INCLUDES DUCT, PIPE AND MECHANICAL SYSTEMS) | $75.37 | $18.82 | $94.19 | ASBE0007-007 eff. 06/01/2025 |
| BRICKLAYER | $39.57 | $20.50 | $60.07 | BRWA0001-021 eff. 06/01/2025 |
| TILE SETTER | $36.35 | $14.57 | $50.92 | BRWA0001-023 eff. 06/01/2025 |
| TILE FINISHER | $27.26 | $11.99 | $39.25 | BRWA0001-023 eff. 06/01/2025 |
| CARPENTER | $44.21 | $17.28 | $61.49 | CARP0059-018 eff. 06/01/2025 |
| ELECTRICIAN | $60.00 | $27.78 | $87.78 | ELEC0112-012 eff. 06/01/2025 |
| OPERATOR: BULLDOZER: D9 & UNDER (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN) | $59.23 | $27.57 | $86.80 | ENGI0302-099 eff. 06/13/2025 |
| OPERATOR: BLADE FINISH (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN) | $59.88 | $27.57 | $87.45 | ENGI0302-099 eff. 06/13/2025 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN) | $60.67 | $27.57 | $88.24 | ENGI0302-099 eff. 06/13/2025 |
| OPERATOR: GRADER/BLADE (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN) | $60.67 | $27.57 | $88.24 | ENGI0302-099 eff. 06/13/2025 |
| OPERATOR: LOADER: OVERHEAD UNDER 6 YARDS (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN) | $59.88 | $27.57 | $87.45 | ENGI0302-104 eff. 06/01/2025 |
| OPERATOR: LOADER: OVERHEAD 6 YARDS BUT NOT INCLUDING 8 YARDS (COUNTY WHICH LIES WEST OF THE 120TH MERIDIAN) | $60.67 | $27.57 | $88.24 | ENGI0302-104 eff. 06/01/2025 |
| IRONWORKER | $57.94 | $34.52 | $92.46 | IRON0086-006 eff. 07/07/2025 |
| LABORER: FORM STRIPPING | $50.38 | $16.96 | $67.34 | LABO0242-015 eff. 06/01/2025 |
| LABORER: JACKHAMMER | $51.52 | $16.99 | $68.51 | LABO0242-018 eff. 06/01/2025 |
| LABORER: NOZZLE PERSON | $52.31 | $17.01 | $69.32 | LABO0242-020 eff. 06/01/2025 |
| LABORER, MASON TENDER BRICK | $50.38 | $16.96 | $67.34 | LABO0252-017 eff. 06/01/2025 |
| LABORER: FIRE WATCH | $40.56 | $15.60 | $56.16 | LABO0335-007 eff. 06/01/2025 |
| LABORER: HOD CARRIER | $48.14 | $15.60 | $63.74 | LABO0335-012 eff. 06/01/2025 |
| SCAFFOLD BUILDER | $44.06 | $15.60 | $59.66 | LABO0335-021 eff. 06/01/2025 |
| PAINTER | $41.24 | $14.70 | $55.94 | PAIN0300-003 eff. 07/01/2025 |
| PIPEFITTER | $65.20 | $34.91 | $100.11 | PLUM0598-001 eff. 06/01/2025 |
| ROOFER, EXCLUDES METAL ROOFS | $48.01 | $16.44 | $64.45 | ROOF0153-007 eff. 02/01/2024 |
| SHEETMETAL WORKER (INCLUDING METAL ROOFING) | $50.00 | $28.41 | $78.41 | SHEE0055-010 eff. 06/01/2025 |
| SPRINKLER FITTER | $25.80 | $8.32 | $34.12 | SUWA2018-019 eff. 03/01/2024 |
| PLUMBER | $47.74 | $28.52 | $76.26 | SUWA2018-019 eff. 03/01/2024 |
| OPERATOR: ROLLER | $42.04 | $12.79 | $54.83 | SUWA2018-019 eff. 03/01/2024 |
| OPERATOR: OILER | $36.39 | $16.62 | $53.01 | SUWA2018-019 eff. 03/01/2024 |
| OPERATOR: MECHANIC | $40.77 | $15.91 | $56.68 | SUWA2018-019 eff. 03/01/2024 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $40.53 | $9.56 | $50.09 | SUWA2018-019 eff. 03/01/2024 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $37.76 | $7.02 | $44.78 | SUWA2018-019 eff. 03/01/2024 |
| LABORER: PIPELAYER | $32.17 | $11.49 | $43.66 | SUWA2018-019 eff. 03/01/2024 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $26.66 | $9.76 | $36.42 | SUWA2018-019 eff. 03/01/2024 |
| LABORER: CONCRETE SAW CHAIN | $35.03 | $10.86 | $45.89 | SUWA2018-019 eff. 03/01/2024 |
| LABORER: COMMON OR GENERAL | $27.94 | $7.89 | $35.83 | SUWA2018-019 eff. 03/01/2024 |
| CEMENT MASON/CONCRETE FINISHER | $28.26 | $9.29 | $37.55 | SUWA2018-019 eff. 03/01/2024 |
| TRUCK DRIVER: CONCRETE TRUCK | $55.43 | $27.52 | $82.95 | TEAM0174-009 eff. 06/01/2025 |
| TRUCK DRIVER: DUMP TRUCK (LESS THAN 16 YARD CAPACITY) | $53.84 | $27.52 | $81.36 | TEAM0589-002 eff. 06/01/2025 |
| TRUCK DRIVER: DUMP TRUCK (16 TO 30 YARD CAPACITY) | $54.68 | $27.52 | $82.20 | TEAM0589-002 eff. 06/01/2025 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.