What changed since modification 2

No existing rate changed amount.

7 classifications added, 7 removed or reworded
  • removed POWER EQUIPMENT OPERATOR: Group 1 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $38.17 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 1- ROLLER $38.17 + $23.40 fringe
  • removed POWER EQUIPMENT OPERATOR: Group 2 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $38.56 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 2- TRUCK CRANE OILER/DRIVER $38.56 + $23.40 fringe
  • removed POWER EQUIPMENT OPERATOR: Group 3 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $39.31 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 3- BOBCAT/SKID STEER/SKID LOADER; BULLDOZER (D9 & UNDER) $39.31 + $23.40 fringe
  • removed POWER EQUIPMENT OPERATOR: Group 4 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $39.51 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 4- CONCRETE PUMP-SQUEEZE-CRETE, FLOW-CRETE, WHITMAN & SIMILAR; DRILL OILERS: AUGER TYPE, TRUCK OR CRANE MOUNT; LOADER-OVERHEAD UNDER 4 YARDS $39.51 + $23.40 fringe
  • removed POWER EQUIPMENT OPERATOR: Group 5 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $39.71 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 5- BACKHOE/EXCAVATOR/TRACKHOE (45,000 GW & UNDER) $39.71 + $23.40 fringe
  • removed POWER EQUIPMENT OPERATOR: Group 6 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $40.05 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 6- CONCRETE PUMP-BOOM TRUCK; GRADER/BLADE; LOADER-OVERHEAD 4 YARDS, INDCLUDING 8 YARDS; PAVER (ASPHALT, AGGREGATE, AND, CONCRETE); SCRAPER $40.05 + $23.40 fringe
  • removed POWER EQUIPMENT OPERATOR: Group 7 Power Equipment Operators Classifications Group 1: Roller Group 2: Truck Crane Oiler/Driver Group 3: Bobcat/Skid Steer/Skid Loader; Bulldozer (D9 & Under) Group 4: Concrete Pump-Squeeze-Crete, Flow-Crete, Whitman & Similar; Drill Oilers: Auger Type, Truck or Crane Mount; Loader-Overhead Under 4 Yards Group 5: Backhoe/Excavator/Trackhoe (45,000 GW & Under) Group 6: Concrete Pump-Boom Truck; Grader/Blade; Loader-Overhead 4 Yards, Including 8 Yar was $40.39 + $23.40 fringe
  • added POWER EQUIPMENT OPERATOR: GROUP 7- MECHANIC (90% OF THE REGULAR RATE) $40.39 + $23.40 fringe

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

WA20260133 wage rates
ClassificationBaseFringeTotalRate ID
CARPENTER$44.21$17.28$61.49CARP0059-012
eff. 06/01/2025
LINE CONSTRUCTION: LINE PERSON$64.17$24.54$88.71ELEC0077-002
eff. 02/01/2024
TREE TRIMMER: GROUND PERSON$22.60$16.37$38.97ELEC0077-003
eff. 02/01/2023
TREE TRIMMER$42.57$17.97$60.54ELEC0077-003
eff. 02/01/2023
LINE CONSTRUCTION: EQUIPMENT OPERATOR$55.19$20.94$76.13ELEC0077-005
eff. 02/01/2024
LINE CONSTRUCTION: (GROUND PERSON)$37.53$17.74$55.27ELEC0077-006
eff. 02/01/2023
ELECTRICIAN$60.00$27.78$87.78ELEC0112-010
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 1- ROLLER$38.17$23.40$61.57ENGI0302-143
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 2- TRUCK CRANE OILER/DRIVER$38.56$23.40$61.96ENGI0302-143
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 3- BOBCAT/SKID STEER/SKID LOADER; BULLDOZER (D9 & UNDER)$39.31$23.40$62.71ENGI0302-143
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 4- CONCRETE PUMP-SQUEEZE-CRETE, FLOW-CRETE, WHITMAN & SIMILAR; DRILL OILERS: AUGER TYPE, TRUCK OR CRANE MOUNT; LOADER-OVERHEAD UNDER 4 YARDS$39.51$23.40$62.91ENGI0302-143
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 5- BACKHOE/EXCAVATOR/TRACKHOE (45,000 GW & UNDER)$39.71$23.40$63.11ENGI0302-143
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 6- CONCRETE PUMP-BOOM TRUCK; GRADER/BLADE; LOADER-OVERHEAD 4 YARDS, INDCLUDING 8 YARDS; PAVER (ASPHALT, AGGREGATE, AND, CONCRETE); SCRAPER$40.05$23.40$63.45ENGI0302-143
eff. 06/01/2025
POWER EQUIPMENT OPERATOR: GROUP 7- MECHANIC (90% OF THE REGULAR RATE)$40.39$23.40$63.79ENGI0302-143
eff. 06/01/2025
IRONWORKER$43.40$32.77$76.17IRON0014-010
eff. 07/07/2025
TRAFFIC CONTROL: FLAGGER$34.03$16.90$50.93LABO0238-040
eff. 06/01/2025
LABORER: NOZZLE PERSON$52.31$17.01$69.32LABO0242-010
eff. 06/01/2025
LABORER: PIPELAYER$37.80$16.90$54.70LABO0348-010
eff. 06/01/2025
PAINTER$41.24$14.70$55.94PAIN0300-002
eff. 07/01/2025
CEMENT MASON/CONCRETE FINISHER$40.89$18.64$59.53PLAS0072-005
eff. 06/01/2025
TRUCK DRIVER: WATER TRUCK$31.62$16.84$48.46SUWA2018-033
eff. 03/01/2024
TRUCK DRIVER: DUMP TRUCK$27.94$17.30$45.24SUWA2018-033
eff. 03/01/2024
TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER$30.61$10.89$41.50SUWA2018-033
eff. 03/01/2024
OPERATOR: FORKLIFT$45.93$19.20$65.13SUWA2018-033
eff. 03/01/2024
OPERATOR: BULLDOZER$28.14$15.76$43.90SUWA2018-033
eff. 03/01/2024
LABORER: FENCE ERECTOR$30.21$0.00$30.21SUWA2018-033
eff. 03/01/2024
LABORER: MASON TENDER - CEMENT/CONCRETE$27.51$2.96$30.47SUWA2018-033
eff. 03/01/2024
LABORER: HOD CARRIER$35.06$10.94$46.00SUWA2018-033
eff. 03/01/2024
LABORER: CONCRETE SAW CHAIN$36.24$10.89$47.13SUWA2018-033
eff. 03/01/2024
LABORER: COMMON OR GENERAL$37.83$0.00$37.83SUWA2018-033
eff. 03/01/2024
LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR$36.96$8.56$45.52SUWA2018-033
eff. 03/01/2024
GRADE CHECKER$31.40$14.10$45.50SUWA2018-033
eff. 03/01/2024
TRUCK DRIVER: ASPHALT MIX$55.43$27.52$82.95TEAM0313-001
eff. 06/01/2025

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.