WV20260026, modification 1, published 05/18/2026. Official source on SAM.gov

Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.

What changed since modification 0

No existing rate changed amount.

0 classifications added, 2 removed or reworded
  • removed LABORER: Group 2 was $24.13 + $16.05 fringe
  • removed LABORER: Grouting was $22.11 + $17.25 fringe

Rates per hour

Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.

WV20260026 wage rates
ClassificationBaseFringeTotalRate ID
ASBESTOS WORKER/HEAT & FROST INSULATOR$38.05$30.87$68.92ASBE0080-002
eff. 02/24/2025
BOILERMAKER$47.13$28.93$76.06BOIL0667-005
eff. 01/01/2025
BRICK POINTER/CAULKER/CLEANER$31.65$25.56$57.21BRWV0009-001
eff. 12/01/2022
MASON - STONE$33.00$26.18$59.18BRWV0015-010
eff. 06/01/2024
CARPENTER (SCAFFOLD BUILDER ONLY)$30.00$21.15$51.15CARP1024-001
eff. 06/01/2023
CARPENTER (INCLUDING FLOOR LAYING - CARPET, HARDWOOD, RESILIENT AND VINYL)$30.03$23.65$53.68CARP1911-007
eff. 12/01/2020
POWER EQUIPMENT OPERATOR: GROUP 4 BOBCAT/SKID STEER/SKID LOADER, ROLLER, OILER$34.71$22.05$56.76ENGI0132-007
eff. 12/01/2024
POWER EQUIPMENT OPERATOR: GROUP 3 BACKHOE, ALL OTHER CRANES$45.21$22.05$67.26ENGI0132-007
eff. 12/01/2024
POWER EQUIPMENT OPERATOR: GROUP 2 OPERATING CRANES AND TOWER CRANES WITH A LIFTING CAPACITY OF 15 TONS AND OVER$46.21$22.05$68.26ENGI0132-007
eff. 12/01/2024
POWER EQUIPMENT OPERATOR: GROUP 1 ALL FRICTION CRANES, TOWER CRANES AND ALL CRANES WITH 180 FT. OR MORE OF BOOM INCLUDING MAST AND JIBS OR LIFTING CAPACITY OF 100 TONS OR MORE AND HOISTS WITH 30,000 POUND LINE PULL OR MORE$46.56$22.05$68.61ENGI0132-007
eff. 12/01/2024
IRONWORKER: ORNAMENTAL$35.19$25.66$60.85IRON0549-006
eff. 12/01/2022
IRONWORKER: REINFORCING$36.10$24.65$60.75IRON0787-006
eff. 12/01/2025
LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND)$22.76$16.75$39.51LABO0453-003
eff. 12/01/2017
LABORER: ASPHALT RAKER, JACK HAMMER, MOTORIZED BUGGY OPERATOR, WATER BOY$25.41$16.75$42.16LABO0543-003
eff. 06/01/2020
PAINTER: DRYWALL FINISHING/TAPING$30.57$20.06$50.63PAIN0970-007
eff. 12/01/2024
TRUCK DRIVER: SINGLE AND DOUBLE AXLE DUMP TRUCKS$27.21$8.97$36.18SUWV2012-024
eff. 08/13/2012
ROOFER$24.28$9.32$33.60SUWV2012-024
eff. 08/13/2012
PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION$27.64$18.09$45.73SUWV2012-024
eff. 08/13/2012
PAINTER: BRUSH, ROLLER AND SPRAY$28.55$3.00$31.55SUWV2012-024
eff. 08/13/2012
OPERATOR: FORKLIFT$33.09$3.00$36.09SUWV2012-024
eff. 08/13/2012
OPERATOR: EXCAVATOR$37.69$3.00$40.69SUWV2012-024
eff. 08/13/2012
OPERATOR: BULLDOZER$30.24$10.26$40.50SUWV2012-024
eff. 08/13/2012
LABORER: MASON TENDER - CEMENT/CONCRETE$22.05$8.54$30.59SUWV2012-024
eff. 08/13/2012
LABORER: MASON TENDER - BRICK$21.47$8.29$29.76SUWV2012-024
eff. 08/13/2012
LABORER: DEMOLITION$20.58$9.47$30.05SUWV2012-024
eff. 08/13/2012
LABORER: COMMON OR GENERAL$25.27$3.00$28.27SUWV2012-024
eff. 08/13/2012
IRONWORKER, STRUCTURAL$26.01$12.18$38.19SUWV2012-024
eff. 08/13/2012
ELECTRICIAN$28.16$15.11$43.27SUWV2012-024
eff. 08/13/2012
CARPENTER (DRYWALL HANGING ONLY)$25.08$12.58$37.66SUWV2012-024
eff. 08/13/2012
BRICKLAYER$27.50$12.35$39.85SUWV2012-024
eff. 08/13/2012

Footnotes

Executive Order 13658
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

About this determination

Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.

Page built from modification 1 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.