Louisiana prevailing wage rates: LA20260044
Building construction in St Tammany County.
LA20260044, modification 2, published 05/18/2026. Official source on SAM.gov
Verify against the official determination before bidding. These rates are formatted from the published SAM.gov wage determination. The determination in your contract documents is what applies.
What changed since modification 1
No base or fringe rates changed. The modification may have changed notes or other text.
Rates per hour
Total = base + fringe. Fringe may be paid to bona fide benefit plans, in cash, or both.
| Classification | Base | Fringe | Total | Rate ID |
|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $32.66 | $9.86 | $42.52 | ASBE0053-001 eff. 09/02/2024 |
| ELECTRICIAN (COMMUNICATION TECHNICIAN AND LOW VOLTAGE WIRING ONLY) | $36.00 | $16.66 | $52.66 | ELEC0130-013 eff. 12/01/2025 |
| ELECTRICIAN (EXCLUDING COMMUNICATION TECHNICIAN AND LOW VOLTAGE WIRING) | $30.35 | $12.46 | $42.81 | ELEC1077-009 eff. 05/26/2025 |
ELEVATOR MECHANIC A.Scope and notesPAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANKSGIVING DAY AND CHRISTMAS DAY. B. VACATION: EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE; 6% OF BASIC HOURLY RATE FOR UNDER 5 YEARS OF SERVICE AS VACATION PAY CREDIT | $51.11 | $38.44 | $89.55 | ELEV0016-001 eff. 01/01/2025 |
POWER EQUIPMENT OPERATOR: CRANE CRANEScope and notesPREMIUMS: 50-150 TONS $1.75 OVER 150 TONS $2.25 | $23.46 | $8.35 | $31.81 | ENGI0406-002 eff. 07/01/2014 |
| IRONWORKER (REINFORCING AND STRUCTURAL) | $34.75 | $13.86 | $48.61 | IRON0623-021 eff. 07/01/2024 |
| GLAZIER | $25.44 | $12.20 | $37.64 | PAIN1244-006 eff. 09/01/2024 |
| PAINTER (SPRAY, EXCLUDING DRYWALL FINISHING/TAPING) | $18.83 | $9.48 | $28.31 | PAIN1244-012 eff. 12/01/2021 |
| CEMENT MASON/CONCRETE FINISHER | $30.47 | $7.97 | $38.44 | PLAS0567-001 eff. 08/01/2022 |
| PLUMBER (INSTALLATION OF HVAC TEMPERATURE CONTROLS; EXCLUDING HVAC PIPE AND UNIT INSTALLATION) | $33.30 | $14.98 | $48.28 | PLUM0060-009 eff. 06/02/2025 |
| PIPEFITTER (INCLUDING HVAC PIPE AND UNIT INSTALLATION; EXCLUDING INSTALLATION OF HVAC TEMPERATURE CONTROLS) | $34.87 | $17.79 | $52.66 | PLUM0060-009 eff. 06/02/2025 |
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $26.71 | $11.93 | $38.64 | SHEE0214-009 eff. 09/01/2013 |
| TRUCK DRIVER: DUMP TRUCK | $15.00 | $0.00 | $15.00 | SULA2012-029 eff. 09/22/2014 |
| TILE SETTER | $20.00 | $0.00 | $20.00 | SULA2012-029 eff. 09/22/2014 |
| SPRINKLER FITTER (FIRE SPRINKLERS) | $20.98 | $5.46 | $26.44 | SULA2012-029 eff. 09/22/2014 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION | $20.66 | $0.00 | $20.66 | SULA2012-029 eff. 09/22/2014 |
| ROOFER | $16.77 | $5.66 | $22.43 | SULA2012-029 eff. 09/22/2014 |
| PAINTER: DRYWALL FINISHING/TAPING | $18.63 | $3.43 | $22.06 | SULA2012-029 eff. 09/22/2014 |
| PAINTER (BRUSH AND ROLLER), EXCLUDES DRYWALL FINISHING/TAPING | $18.95 | $8.91 | $27.86 | SULA2012-029 eff. 09/22/2014 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $21.03 | $0.00 | $21.03 | SULA2012-029 eff. 09/22/2014 |
| LABORER: MASON TENDER - BRICK | $12.39 EO 13658 minimum $13.65 may apply | $0.00 | $12.39 | SULA2012-029 eff. 09/22/2014 |
| LABORER: COMMON OR GENERAL | $13.41 EO 13658 minimum $13.65 may apply | $0.00 | $13.41 | SULA2012-029 eff. 09/22/2014 |
| DRYWALL HANGER AND METAL STUD INSTALLER | $18.35 | $4.33 | $22.68 | SULA2012-029 eff. 09/22/2014 |
| CARPENTER, EXCLUDES DRYWALL HANGING AND METAL STUD INSTALLATION, AND FORM WORK | $19.36 | $2.13 | $21.49 | SULA2012-029 eff. 09/22/2014 |
| CARPENTER (FORM WORK ONLY) | $15.00 | $0.00 | $15.00 | SULA2012-029 eff. 09/22/2014 |
| BRICKLAYER | $18.88 | $0.00 | $18.88 | SULA2012-029 eff. 09/22/2014 |
Footnotes
- Executive Order 13658
- Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
About this determination
Welders receive the rate for the craft performing the work to which welding is incidental. Classifications not listed may be added after award through the conformance process (29 CFR 5.5(a)(1)(iii)). Executive Order minimum wages and paid sick leave may also apply; the official document has the full text.
Page built from modification 2 published 05/18/2026. We format and check the official text; the determination in your contract is what applies.